| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹3.3 CrAdmitted-Finance 2 560 GOMTI NAGAR VIRAM KHAND LUCKNOW | LUCKNOW | LUCKNOW | UTTAR PRADESH | 226010 | -1.00% | ₹3.3 Cr | L1 | Admitted-Finance |
Tender Value
₹3.5 Cr
EMD Value
₹7.1 L
Closing Date
20 Mar 2026, 3:00 pmClosed
CHIEF ENGINEER
NAGAR NIGAM BAREILLY
Ward-04/07 Covering of drain from Sugar Factory Rangeela Paan to Narayan Dairy via Sonu Sweets (Chungi Road) and construction of remaining CC road on both sides of the drain from Rangeela to Sonu Sweets.
2026_DOLBU_1124872_1
417/CE/CD/25-26 (21 To 24) Sr No 22 Tender List 24 Date-11.03.2026
Open Tender
Civil Works
Percentage
180 days
BAREILLY
Please refer Tender documents.
2 documents required · 2 mandatory
₹11,800
Bareillye-tender.com
₹7.1 L
21 Apr 2026
13 Mar 2026
20 Mar 2026
13 Mar 2026
20 Mar 2026
13 Mar 2026
Part-A
Dismantling of cement concrete or brick or dismantlled materials as directed by E/I.within a distance of 60.00M
Dismantling of old damage Brick workand stone work i/c stacking of dismantlled materials as directed by E/I.within a distance of 60.00M
Supply of Earth for filling or embankment in ordinary soil earth work in filling or embankment to be in 20 cm layers, including ,watering ,Dressing ,compacting ,ramming the soil to achive 95% proctor density ,and dressing the surface to be required levels and slope and also including 1.50m lift and 30 m lead . The earth from cutting to be used in making embankment or to be deposited as spoil banks within 30m distance as directed by the Engineer-in-charge. (Excluding Royalty) Analysis rate
S/L of empty cement bags filled with local earth sand and carriage upto site of work including stiching loading and unloading stackimg and also including supply of all material, labour T&P required for proper complition of the work etc. as per direction of E/I as per NEW ITEM No. 1
Providing cost of Dewatering I/C cost of boaring, laying of 4" dia PVC pipe, hire charges of pump set with diesel PVC pipeall omplete As per Non Schedule Item No. A
Providing and layingConcrete with 4cm gauge brick ballast, fine sand of 1.25 fineness modulous and cement in prportion of 1:6:12 in foundation in under floor , including supply of all material labour and T&P etc rfequired of proper completetion of the work .
First class B/w in 1:4 Cement C'sand mortor in F/P including supply of all meterial labour T&P etc required for proper completion of work. 305+310
12 mm thick plaster in 1:5 cement & c'sand mortor over brick work minimume thickness not less then 10 mm including all supply of meterial , Labour T&P etc
Providing and laying cement concrete in 4:2:1 of not less than strength of M-150 stone ballast (20 mm nominal size), approved coarse sand and cement, curing complete including of cost of form work in foundation and floors-completion of the work as per direction of the E / I.
R.C.C. work with cement approved coarse sand and 2 cm. (3/4") gauge approved stone ballast in the proportion of 1:1:5:3 in slab of doors and windows excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.I binding wire and including necessary centering and shuttering etc. and also including supply of all materials, labour & T&P etc. required for proper completion of the work. Binding wire cost being included in the item.
RCC 1:2:4 with cement c'sand stone grit of 20 mm gauge in Slabs excluding supply of reinforcement with its bending but including its binding & fixing with supply of all meterial labour T&P etc. required for proper completion of the work.
Mild steel or iron in plain work such as reinforced concrete or reinforced brick work (when not included in an over all rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of all steel and wastage & overlapping & hooks.
P/L of Granular sub base with coarse graded materials (Table 404 ) in granular sub base by providing coare graded materials, spreading in uniform layer with motor grader on preparing surface mixing by mix in place method with rotovator O.M.C. and compacting with power vibratory roller to achieve the desired density complete as per clause 401compected incluing lighting, guarding, barricating and maintance of diversion etc.
Providing and Laying of 125 micron plastic sheet,
Cement concrete with 2 cm. gauge approved stone, ballast, approved coarse sand and cement in the proportion of 3:1.50:1 including supply of all materials, labour and T&P etc. required for proper completion of the work
Deduction cost of brick bats
Deduction cost of bricks
Part-B Chingi Road to Narayan Dairy
Dismantling of old damage RCC or RB work i/c stacking of dismantlled materials as directed by E/I.within a distance of 60.00M. (S.I.No.694)
Dismantling of old damage brick work and stone work i/c stacking of dismantlled materials as directed by E/I.within a distance of 60.00M. (S.I.No.692)
S/L of empty cement bags filled with local earth sand and carriage upto site of work including stiching loading and unloading stackimg and also including supply of all material, labour T&P required for proper complition of the work etc. as per direction of E/I as per NEW ITEM No. 1
Providing cost of Dewatering I/C cost of boaring, laying of 4" dia PVC pipe, hire charges of pump set with diesel PVC pipeall omplete As per Non Schedule Item No. A
Providing and layingConcrete with 4cm gauge brick ballast, fine sand of 1.25 fineness modulous and cement in prportion of 1:6:12 in foundation in under floor , including supply of all material labour and T&P etc rfequired of proper completetion of the work .
First class B/w in 1:4 Cement C'sand mortor in F/P including supply of all meterial labour T&P etc required for proper completion of work.
12 mm thick plaster in 1:5 cement & c'sand mortor over brick work minimum thickness not less then 10 mm including all supply of meterial , Labour T&P etc required for proper completetion of the work.
Providing laying C.C with 2cm gauge approved stone ballast, approved coarse sand and cement in praportion of 1:2:4 including supply of all materials, labour and T&P etc required for proper completetion of the work.
RCC 1:1.5:3 with cement c'sand stone grit of 20 mm gauge in lighter beam excluding supply of reinforcement with its bending but including its binding & fixing with supply of all meterial labour T&P etc. required for proper completion of the work. SI No. 285
RCC 1:2:4 with cement c'sand stone grit of 20 mm gauge in Slabs excluding supply of reinforcement with its bending but including its binding & fixing with supply of all meterial labour T&P etc. required for proper completion of the work.
Mild steel or Iron for plain work such as reinforced concrete brought to proper shape as necessary including its bending with supply of steel with overlaps & wastage also required for proper completion of the work as directed by E/I.
Deduction cost of brick bats
Deduction cost of bricks
stage.html
html • 0.02 MB
techsummary_2096408.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 17.78 MB
BOQ_2096408.xls
BOQ • 0.38 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .