| 1 | L1₹1.6 LAccepted-AOC | ₹1.6 L | L1 | Accepted-AOC L1 |
| Sl No | Description | Qty | Unit | PP Abdul kareem L1 |
|---|---|---|---|---|
| 1.00APPENDIX (A) - DEMOLISHING DAMAGED OHSR | ||||
| 1.00 | 2.32:Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared. | 150 | sqm | 5.47 ₹820.50 |
| 1.00 | 2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil | 4.86 | cum | 152 ₹738.72 |
| 1.00 | 14.72:Providing and fixing double scaffolding system (cup lock type) on the exterior side, upto seven story hight made with 40 mm dia. M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staricase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after. The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required location with essential safety features for the workmen etc. complete as per directions and approval of Engineer- in Charge. The elevational area of the scaffolding shall be measured for payment purpose. The payment will be made once irrespective of duration of scaffolding. Note:- This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done . | 327.82 | sqm | 210.85 ₹69,120 |
| 1.00 | OD158177/2025-2026:Supplying and providing 400 G polythene sheet to cover the outer circumferential area of dismantling structure completely to avoid air pollution and to avoid spilling of dust and broken
concrete particles to the nearby locality as a safety measure including cost and conveyance of 400 G polythene sheet , rope, fixing charges etc complete per the direction of engineer in charge | 365.5 | sqm | 20.69 ₹7,562.11 |
| 1.00 | 15.3:Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge. | 40.23 | cum | 2,166.42 ₹87,165.91 |
| 1.01 | 15.44.2:Dismantling G.I. pipes ( external work) including excavation and refilling trenches after taking out the pipes, manually / by mechanical means including stacking of pipes within 50 metres lead as per direction of Engineer- in- Charges:Above 40 mm nominal bore | 25 | metre | 99.33 ₹2,483.25 |
| 1.01 | 15.18:Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates,bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50 metres lead. | 180.55 | kg | 3.45 ₹622.90 |
| 1.01 | OD158176/2025-2026:Deduct scrap value of steel (to be recovered) - Rate (highest rate) circulated vide Lt No.KWA/HO/SP-8174/2014-15/Scrap dated 11/01/2016 of the CE(HRD&GL) | 2,605.41 | kg | -9.59 -₹24,985.88 |
| 1.01 | OD158175/2025-2026:Deduct Scrap value of demolished concrete waste | 28.16 | cum | -513.97 -₹14,475.97 |
Tender Value
₹2.8 L
EMD Value
₹6,877
Closing Date
25 Feb 2026, 2:00 pmClosed
ASST EXECUTIVE ENGINEER
WSP SUBDIVISION HARIPPAD
O AND M - Water Supply Schemes-DEMOLISHING OLD DAMAGED OHSR AND PUMP HOUSE-MACE OF RWSS TO CHINGOLI DEMOLISHING DILAPIDATED CIVIL STRUCTURES - DEMOLISHING OLD DAMAGED OHSR AND PUMP HOUSE NEAR IDEAL COLLEGE AT VAYANASALA JUNCTION IN WARD 9 OF CHINGOLI
2026_KWA_836781_1
WRD/KWA-CE(CR)/TR/23721/2025
Open Tender
Civil Works - Water Works
30 days
WSP SUBDIVISION HARIPPAD
Please refer Tender documents.
7 documents required · 7 mandatory
₹610
Yes
₹6,877
Yes
9 Jun 2026
16 Feb 2026
26 Feb 2026
16 Feb 2026
25 Feb 2026
16 Feb 2026
APPENDIX (A) - DEMOLISHING DAMAGED OHSR
2.32:Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared.
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil
14.72:Providing and fixing double scaffolding system (cup lock type) on the exterior side, upto seven story hight made with 40 mm dia. M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staricase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after. The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required location with essential safety features for the workmen etc. complete as per directions and approval of Engineer- in Charge. The elevational area of the scaffolding shall be measured for payment purpose. The payment will be made once irrespective of duration of scaffolding. Note:- This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done .
OD158177/2025-2026:Supplying and providing 400 G polythene sheet to cover the outer circumferential area of dismantling structure completely to avoid air pollution and to avoid spilling of dust and broken concrete particles to the nearby locality as a safety measure including cost and conveyance of 400 G polythene sheet , rope, fixing charges etc complete per the direction of engineer in charge
15.3:Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge.
15.44.2:Dismantling G.I. pipes ( external work) including excavation and refilling trenches after taking out the pipes, manually / by mechanical means including stacking of pipes within 50 metres lead as per direction of Engineer- in- Charges:Above 40 mm nominal bore
15.18:Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates,bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50 metres lead.
OD158176/2025-2026:Deduct scrap value of steel (to be recovered) - Rate (highest rate) circulated vide Lt No.KWA/HO/SP-8174/2014-15/Scrap dated 11/01/2016 of the CE(HRD&GL)
OD158175/2025-2026:Deduct Scrap value of demolished concrete waste
APPENDIX (B) - DEMOLISHING OLD PUMP HOUSE
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil
15.12.1:Dismantling doors, windows and clerestory windows (steel or wood ) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres lead:Of area 3 sq. metres and below
15.3:Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge.
15.7.4:Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.In cement mortar
15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix)
15.9.2:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:In cement mortar
OD158172/2025-2026:Deduct Scrap value of demolished concrete waste
OD158171/2025-2026:Deduct scrap value of demolished rubble masonry
OD158173/2025-2026:Deduct scrap value of demolished brick work
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1408855.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
KWAGeneralConditionsforeTenderingV5.pdf
PDF • 0.69 MB
Tendernotice_1.pdf
PDF • 0.41 MB
Tendernotice_2.pdf
PDF • 0.05 MB
Tendernotice_3.pdf
PDF • 0.15 MB
BOQ_1408855.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid