Tender Value
₹13.3 L
EMD Value
₹13,300
Closing Date
20 Apr 2026, 6:00 pmClosed
Similar tender results from the same govt authority in the past 3 years.
Chief Officer, UNJHA NAGARPALIKA, UNJHA
CONSTRUCTION OF PERCOLATING WELL AT DIFFERENT 8 SITE AT UNJHA.(THIRD ATTEMPT)
292144
1 OF 2025 – 2026
Open
Civil Works
Mehsana
18 documents required · 18 mandatory
₹900
Chief Officer , UNJHA Nagar Seva Sadan, UNJHA
₹13,300
31 Mar 2026
31 Mar 2026
31 Mar 2026
20 Apr 2026
31 Mar 2026
Name Of Work : CONSTRUCTION OF PERCOLATING WELL AT DIFFERENT 8 SITE AT UNJHA.
Schedule-B1 : CONSTRUCTION OF PERCOLATING WELL AT DIFFERENT 8 SITE AT UNJHA.
Sr. No. Description Quantity Unit Rate Amount
1 Dimolition and disposal of unserviceable 0.15 Cu.M. 622.37
materials with all lead and lift .(ii)
unreinforcement cement concrete.
2 Excavation for foundation upto 1.5M depth 10.26 Cu.M. 212.52
including sorting out and stacking of useful
materials and disposing of the excavated stuff
upto 50 Meter Lead.
Loose or Soft Soil.
3 Excavation for foundation 1.5M to 3.0m depth 0.00 Cu.M. 235.05
including sorting out and stacking of useful
materials and disposing of the excavated stuff
upto 50 Meter Lead.
Loose or Soft Soil.
4 Excavation for foundation 3M to 5.0m depth 0.00 Cu.M. 257.58
including sorting out and stacking of useful
materials and disposing of the excavated stuff
upto 50 Meter Lead.
Loose or Soft Soil.
5 Providing and laying cement concrete 1:3:6 ( 1: 0.68 Cu.M. 2968.91
Cement : 3- Coarse Sand : 6- hand broken stone
aggregates 40mm nominal size) and curing
complete excluding cost of formwork in
(A) Foundation & Plinth
6 Providing and laying controlled cement concrete 2.56 Cu.M. 4425.62
M250 and curing complete including the cost of
formwork but excluding reinforcement for
reinforced concrete work in Foundation, footing,
Base of Columns and mass concrete
7 Brickwork using common burnt clay building 4.27 Cu.M. 3424.52
bricks having crushing strength not less than
35kg/Sq.cm. In foundation and plinth in Cement
mortar 1:6 ( 1-Cement :6- Fine Sand )
(B) Conventional
8 Providing 15mm thick cement plaster in single 23.91 Sq.M. 184.78
coat on Rough (Similar)side of single or half brick
walls for interior plastering upto floor two level
and finished even and smooth in (i) Cement
mortar 1:3 (1-cement:3-sand)
9 Filling available excavated earth ( excluding rock ) 10.26 Cu.M. 136.92
in trenches, plinth, sides of foundation etc. in
layers not exceeding 20cm in depth consolidating
each deposited layer by ramming and watering.
10 Providing TMT Bar FE 500D reinforcement for 179.20 Kg 77.29
R.C.C. work including bending, binding and
placing in position complete upto floor two level
11 Drilling 250/300mm dia.Pllot bore at above 60.00 R.Mt. 568.63
village site in all strata by mud flush direct rotary
Ring from 0.00 mtr. To 230 mtrs.
12 Reaming of 250/300mm dia. Bore hole to 60.00 R.Mt. 347.44
following bore hole including assembling, joining,
lowering of housing casing strainer pipes and
other assemble item with gravel packing and
other assemble items with packing and clay ball
packing etc. (2)550dia.bore hole from 0.00 to
13 Supply crushed stone aggregate size 20mm to 14.53 Cu.M. 452.13
14 Supplying and Supplying ISI Standard R.C.C.Pipes 61.80 R.Mt. 630.24
in standard lengths of following class and
diameter suitable for either M.S.clamp jionts
taxes,insurance,transportation,freight
charges,octroi,inspection
charges,loading,unloding,conveyance to
department stores,stacking etc (i) NP3 of
following internal daimeters.(iv) 250mm dia.
15 Labour Charge For Making holes in R.C.C. NP-3 60.00 R.Mt. 202.00
casing for a borewell involves strategically
drilling openings in the casing pipe to allow water
to enter the well from the desired water-bearing
strata. With all Neccessery Machnery And
Materials. As Per Directed By Engineer Incharge
16 filling in foundation and plinth with brick Bats 5.20 Cu.M. 621.46
Chhara in layers of 20cm. thickness including
watering, remming and consolidating etc.
Total FOR 1 NOS:-
Total FOR 8 NOS:-
Total ( B1 ) :-
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
1.Invitation TENDER DOCUMENT-292144.pdf
2.SBD-2025 TENDER DOCUMENT-292144.pdf
3.Volume I-Technical Specifications TENDER DOCUMENT-292144.pdf
4. Special condition TENDER DOCUMENT-292144.pdf
5. GR TENDER DOCUMENT-292144.pdf
6.Schedual B TENDER DOCUMENT-292144.pdf
Download all tender documents and submit your bid