GEMC-511687712197296
Awarded to BL PANDEY CONTRACTOR
₹37.5 L
Products
| Product | Brand / Model | HSN | Quantity | Unit Price | Amount |
|---|---|---|---|---|---|
| Dismantling existing wall | Dismantling Existing Wall / 9018863 | 8897 | 290 M3 | 1,180 | 342,200 |
| Excavation upto 1.5 | Excavation Upto 1.5 / 9018729 | 9987 | 454 M3 | 542.8 | 246,431.2 |
| Excavation below 1.5 | Excavation Below 1.5 / 9018731 | 9987 | 71 M3 | 649 | 46,079 |
| PCC for footing base 1 IS TO 4 IS TO 8 | PCC For Footing Base 1 IS TO 4 IS TO 8 / 9018780 | 9987 | 24 M3 | 5,900 | 141,600 |
| RCC below plinth footing AND pillar AND beam | RCC Below Plinth Footing AND Pillar AND Beam / 9018793 | 9987 | 68 M3 | 8,106.6 | 551,248.8 |
| RCC above plinth pillar | RCC Above Plinth Pillar / 9018794 | 9987 | 23 M3 | 8,460.6 | 194,593.8 |
| Brick mason wall av plinth | Brick Mason Wall Av Plinth / 9018830 | 9987 | 106 M3 | 6,608 | 700,448 |
| PCC on top of BW | PCC On Top Of BW / 9018786 | 9987 | 3 M3 | 6,313 | 18,939 |
| Plaster 18mm thick | Plaster 18mm Thick / 9018942 | 9987 | 740 M2 | 271.4 | 200,836 |
| Two coat cement primer | Two Coat Cement Primer / 9018942 | 9987 | 886 M2 | 54.28 | 48,092.08 |
| Two coat cement paint | Two Coat Cement Paint / 9018943 | 9987 | 886 M2 | 70.8 | 62,728.8 |
| Slogan writing letters 300 mm | Slogan Writing Letters 300 Mm / 9018963 | 9987 | 900 EA | 79.06 | 71,154 |
| Steel Reinforcement for RCC | Steel Reinforcement For RCC / 9018813 | 9987 | 4,665 KG | 76.7 | 357,805.5 |
| Concertina fencing removal and refixing | Concertina Fencing Removal And Refixing / 7006824 | 9987 | 143 RM | 413 | 59,059 |
| JCB related work | JCB Related Work / 9023699 | 9987 | 18 HR | 1,003 | 18,054 |
| Brick masonry drain | Brick Masonry Drain / 9018820 | 9987 | 106 M3 | 5,728.9 | 607,263.4 |
| Plaster 12 mm thick | Plaster 12 Mm Thick / 9018853 | 9987 | 440 M2 | 200.6 | 88,264 |