| 1 | L1₹4.9 LAccepted-AOC | L1 | Accepted-AOC Agreement executed with this contractor |
Tender Value
₹5.1 L
EMD Value
₹12,874
Closing Date
1 Mar 2025, 1:00 pmClosed
Ajayakumar V
Assistant Executive Engineer Office of the AEE,MI Subdivision,Shoranur
GENERAL-Deposit-Construction of field channel from vattakundu check dam in ward No.10 of Ambalappara Grama Panchayath-General Civil Work
2025_Irrig_735617_2
IRR/IA/TR/4995/2024_5_1_1/1
Open Tender
Civil Works - Others
Item Rate
180 days
Ambalappara
Please refer tender documents.
7 documents required · 7 mandatory
₹1,135
₹12,874
15 May 2025
22 Feb 2025
4 Mar 2025
22 Feb 2025
1 Mar 2025
22 Feb 2025
Amount
Appendix A
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
2.7.3:Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.Hard rock (blasting prohibited)
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
60.5.2:DOWEL BARS - Supplying and providing MS dowel bars of size 16 mm dia of 2m long (1m in rock and 1m in concrete ) including drilling holes of 20mm dia to a depth of 1m in rock and filling the gap with cement grout( 0.10kg/each) etc complete.
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
50.13.1:9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
60.63.1:FRP SHUTTERS - Supplying and fixing FRP Channels of "C" profile and sill beam size 100x100x100 mm with flange of 50 to 75mm depth in the grooves already arranged and as per the direction of departmental .officers.
60.63.2:FRP SHUTTERS - Supplying and fixing FRP shutters of suitable size to with stand the design and max water pressure as prescribed by the departmental officer and installing the FRP channels provided in the grooves already arranged and as per the direction of departmental .officers.
60.7.8:DR with Departmental. Stone - DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course using departmental rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site
2.25:Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
OD10016/2024-2025:Engaging man mazdoor DLR labour for removing weeds and other obstruction (blocking materials, debris, fallen down trees etc.) clearing the blocked culverts, dosing leakage of water through shutter portion water distribution etc. complete
Bidder Name
abdul kahdar c
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1193784.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .