| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.0 CrAccepted-AOC C 20 GAUR GRACIOUS KANTH ROAD MORADABAD | MORADABAD | UTTAR PRADESH | ₹1.0 Cr | L1 | Accepted-AOC L1 Firm |
| 2 | L2₹1.0 CrRejected-AOC | ₹1.0 Cr | L2 | Rejected-AOC L2 Firm |
Tender Value
₹1.0 Cr
EMD Value
₹2.0 L
Closing Date
22 Jun 2026, 1:00 pmClosed
General Manager Zone-2
General Manager, Zone-2, U.P. Projects Corporation Ltd. 14, Chandra Shekar Nagar Colony, Tulasherpur, Bareilly
DEVELOPMENT WORK OF RAMLEELA PLACE AT MOHALLA SAHUKARA, BILASPUR, DISTT. RAMPR (U.P.)
2026_UPPRC_1157726_1
06 /PCL/GM/ZONE-2/BLY/2026-27
Open Tender
Civil Works
Percentage
365 days
BILASPUR, DISTT. RAMPUR (U.P.)
As per BID Document
2 documents required · 2 mandatory
₹17,700
₹2.0 L
27 Aug 2026
8 Jun 2026
22 Jun 2026
8 Jun 2026
22 Jun 2026
8 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Civil works | - | - | - | - |
| 2 | Excavation in foundation in ordinary soil (loam clay or sand) including lift upto 1.50 meter and lead upto 30 meter and including filling, watering and ramming of excavated earth into the trenches or into the space between the building and sides of foundation trenches or into the plinth and removal and disposal of sur-plus earth as directed by the Engineer incharge up to a distance of 30 meters from the foundation trenches. | - | CUM | 1 | - |
| 3 | Filling of earth in plinth in 20cm layer including leveling, dressing and watering and also including of supply of earth including carted loading & unloading as per direction of Engineer incharge.. | - | CUM | - | - |
| 4 | Sand filling in plinth under floors including watering, ramming, consolidating and dressing complete including lead up to 50m and lift upto 1.5m and including cost of sand. | 1 | CUM | 1 | ₹1 |
| 5 | Providing and laying cement concrete 1:4:8 (1 cement :4 coarse sand :8 graded Stone aggregate 40 mm nominal size) including supply of all materials, labour T & P rtc required for proper completion of the work and curing complete also including cost of formwork in foundation & floors. | - | CUM | 1 | - |
| 6 | Treatment of soil under existing floors using chemical emulsion @ one litre per hole, 300 mm apart including drilling 12 mm diameter holes and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor:With Chlorpyriphos/Lindane E.C. 20% with 1% concentration | 1 | SQM | 1 | ₹1 |
| 7 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) (Plinth beam) , foundation raft , column | 1 | CUM | - | - |
| 8 | RCC WORK ABOVE PLINTH Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). (Slab)/BEAM | - | CUM | - | - |
| 9 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement
:1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) Column | 1 | CUM | - | - |
| 10 | Brick work with common burnt clay F.P.S. (non modular)
bricks of class designation 7.5 in foundation and plinth in:1:4 (1 cement : 4 sand) | - | CUM | 1 | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.18 MB
BID06.pdf
Tender Documents • 17.46 MB
BOQ_2169615.xls
BOQ • 0.53 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].