| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹2.9 LAccepted-Finance | L-1 | Accepted-Finance Admitted | |
| 2 | L-2₹3.2 L+₹26,901.20 (9.16%)Accepted-Finance | L-2 | Accepted-Finance Admitted | |
| 3 | L-3₹4.4 L+₹1.5 L (51.3%)Accepted-Finance | L-3 | Accepted-Finance Admitted |
Tender Value
₹6.0 L
EMD Value
₹7,000
Closing Date
11 Jan 2021, 4:00 pmClosed
Superintending Engineer
Electricity Transmission Circle Pathrahiya Road Mirzapur
Construction of 132 KV Bay (02 Nos) at 132 KV Sub-station Chauri under ETD-IV, Varanasi
2020_UPTCL_536591_1
19/2020-21/ETC/Mzp
Open Tender
Electrical Works
Fixed-rate
45 days
Chauri
as per tender specification
2 documents required · 2 mandatory
₹826
Executive Engineer, ETD, Mirzapur
₹7,000
15 Jul 2021
9 Dec 2020
12 Jan 2021
9 Dec 2020
11 Jan 2021
9 Dec 2020
Amount
Construction of 02 No. 132 KV Bay and separation of 132 KV Bus with splitting work at 132 KV Sub Station Chauri under Electricity Transmission Division-IV, Varanasi. The job includes the following-
Sorting counting & shifting to loading point and loading of Galv. S/S structures on vehicle (to be provided by the contractor) at EFU-Naini, Prayagraj. Carriage of above structures (12.764 MT) for EFU Naini, Prayagraj to 132 KV S/S Chauri (Approx distance 100 Km). Unloading of Galv. S/S structures from contractor’s vehicle and proper stacking at the store of 132 KV S/S Chauri. Vehicle, labour, and T&P will be provided by the contractor. i. ATM-02 Set @1.413 MT/Set=2.826 MT ii. AXM-03 Set @0.812 MT/Set=2.436 MT iii. XPM-03 Set @ 0.084 MT/Set=0.252 MT iv. YMM-03 Set @ 0.21 MT/Set= 0.063 MT v. BBL-05 Set @ 0.50 MT/Set=2.5 MT vi. BCT-15 Set @ 0.179 MT/Set=2.685 MT vii. BTM-02 Set @ 0.750 MT/Set=1.50 MT viii. BXM-01 Set @ 0.517 MT/Set=0.517 MT ix. ALP-08 Set@ 0.121 MT/Set= 0.968 MT Total =13.747 MT
Erection of structure consisting of columns, beams peak mast etc. and installation structures for other equipments. The job consists to shifting of structure parts, nut, bolts washer etc. from store to work site, erection of structure as per relevant drawing and practices. All materials shall be provided by UPPTCL free of cost. The labour and required T&P shall be arranged by contractor at his own cost i. ATM-02 Set @1.413 MT/Set=2.826 MT ii. AXM-03 Set @0.812 MT/Set=2.436 MT iii. XPM-03 Set @ 0.084 MT/Set=0.252 MT iv. YMM-03 Set @ 0.21 MT/Set= 0.063 MT v. BBL-05 Set @ 0.50 MT/Set=2.5 MT vi. BCT-15 Set @ 0.179 MT/Set=2.685 MT vii. BTM-02 Set @ 0.750 MT/Set=1.50 MT viii. BXM-01 Set @ 0.517 MT/Set=0.517 MT ix. ALP-08 Set@ 0.121 MT/Set= 0.968 MT Total =13.747 MT
132 KV PT Junction box
132 KV CT Junction box
132 KV LI with E/S
132 KV Double Feeder Panel
132 KV Under Frequency Relay
132 KV Distance Protection Panel
Energy Meter 0.2 acc. Class (ABT)
Jumpering of equipment by ACSR Panther conductor including shifting of conductor from store to the site its straightening bending and cutting as per site requirement
Earthing of structure and equipment by suitable (75x10/50x6/25x6mm) size MS flat (to be provided by contractor on his own cost) including cutting straightening bending laying 800 mm below inside the ground with main earth MT including painting of joints with non corrosive paint on flat. Painting at the flat on structure with the green paint after one coat of red oxide primer and back filling of excavated trench along with proper ramming and all associated work.
Laying of following size unarmoured control cable in the cable trench from the control relay panel to the various equipment junction box etc in switchyard as per cable schedule, its saddling proper distance with AL Saddle of size 25x3 mm including carriage of cable drums from the store to the laying site and other associated work to complete the job satisfactory
Termination of following size control cables as laid above as per cable schedule including making necessary holes in glands plate of box wherever required supply and fixing of cable glands ferrule of appropriate size and no. respectively for each core of cable and its termination with crimping type lugs and all associated work to complete the job satisfactory.
Stringing of 132 KV Jack Bus (R,Y,B) with ACSR panther conductor of span length 24 Mtr. At the job include shifting of ACSR panther conductor form store to work place, fitting of all tension clamp, hosting of insulators and proper clamping jointing jumpering etc. (Rates includes all labour and T&P charges but excluding cost of all material such as conductor, isolator, clamps hardware fitting etc. Which shall be provided by UPPTCL)
U K S ENTERPRISES
TARUN ENGINEERING WORKS
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .