Tender Value
₹79.0 L
EMD Value
₹79,500
Closing Date
12 Mar 2026, 6:00 pmClosed
Superintending Engineer, Project Implementation Unit, Health & Family Welfare Department.
New construction Compound Wall of MPC Building At.Arkati, Khabda, Nararnpur, Bhitkhurd, Sakarda, Jamli, (6 Nos), Ta.Uchchhal, & At. Kherva, Laxmikheda, (2 Nos), Ta.Nizar, Di.Tapi
283027
2025-26/159/06
Open
Civil Works - Buildings
Tapi
1 document required · 1 mandatory
₹2,400
Yes
PIU-General Fund A/c 11-114
₹79,500
Yes
5 Mar 2026
5 Mar 2026
5 Mar 2026
12 Mar 2026
5 Mar 2026
Quantitiy Estimated Rates Total Amount
Quantitiy Estimated Rates Total Amount
Estimated Item Of Work Unit may be more or
may be more In Figure In word less
Excavation for foundation up to 1.5 M. Depth including sorting out
and stacking of useful materials and disposing of the excavated Rupees One Hundred Seventeen and
stuff up to 50 meter lead (A) Loose or soft soil Paisa Seven Only
Boring holes 3.5m deep in lordinary soil (for cast in situ piles) and
getting out the soil and disposal of the surplus excaated soil as Rupees One Hundred Forty Nine and
directed within a lead of 50 metre follwoing diameter of pilses.(iii) Paisa Sixty Seven Only
Providing and laying cement concrete 1:2:4 (1 cement : 2 coarse
sand : 4 graded stone aggregate 20mm nominal size) and curing Rupees Four Hundred Sixty and Paisa
complete including cost of form work in (A) Foundation and plinth Eighteen Only
Providing and laying ordinary cement concrete 1:2:4 (1 Cement 2-
coarse sand : 4- graded stone aggregates 20 mm nominal size) and
Rupees Three Thousand Six Hundred
finishing smooth with,curing etc. complete including the cost of
4 9.60 12249.23 Ninety Seven and Paisa Ninety One Cu.m.
formwork but excluding the cost of reinforcement for R.C.C work
in (B) COLUMNS: (i) Having cross-sectional area 0.05 to 0.08 Sq.M
Providing and laying ordinary cement concrete 1:2:4 (1 Cement 2-
coarse sand : 4- graded stone aggregates 20 mm nominal size) and
Rupees Three Thousand Six Hundred
finishing smooth with,curing etc. complete including the cost of
5 94.00 12249.23 Ninety Seven and Paisa Ninety One Cum
formwork but excluding the cost of reinforcement for R.C.C work
in (B) COLUMNS: (i) Having
cross-sectional area 0.05 to 0.08 Sq.M
Quantitiy Estimated Rates Total Amount
Quantitiy Estimated Rates Total Amount
Estimated Item Of Work Unit may be more or
may be more In Figure In word less
Providing and laying ordinary cement concrete 1:2:4 (1 Cement 2-
coarse sand : 4- graded stone aggregates 20 mm nominal size) and
finishing smooth with,curing etc. complete including the cost of Rupees Seventy Six and Paisa Twenty
formwork but excluding the cost of reinforcement for R.C.C work One Only
in (A) BEAMS :(i) Having cross
sectional area 0.05 to 0.08 Sq.M
Provdg & laying ordinary cement concerete 1:2:4 (1 cement:
coarse sand : 4 graded stone aggregate 20 mm nominal size) for
RCC lintel incl. finishing smooth with curing etc. complete including Rupees Four Thousand Five Hundred
the cost of form work but excluding the cost of reinforcement up Twenty Four and Paisa Eighty Only
to floor two level Lintel/ Coping
Providing T M T. bar FE 500 D reinforcement for R.C.C. work
Rupees Seven Thousand Six Hundred
8 31839.00 including bending binding and placing in position complete up to 77.29 Cu.Mt.
Seventy Eight and Paisa Two Only
floor two level.
Half brick masonry in common burnt clay building bricks having
crushing strength not less than 35 Kg/ Cm2 in cement mortar 1:4 (1
Rupees One Hundred Thirty and Paisa
9 1609.00 cement : 4- Coarse sand) with 2 Nos. of 6 mm dia mild steeld round 656.34 Cum
Thirty Nine Only
bar after every three coarse embeded in cement mortar super
structure (for G.F) Conventional.
Steel work, riveted in built up sections framed work including
cutting, hoisting, fixing in position and applying a priming coat of Rupees Six Thousand Two Hundred
red lead paint. (D) In trussses and trussed purlins, upto 25 M. span Eighty One and Paisa Nineteen Only
and 15 M ovarall height.
20mm thick sand faced cement plaster on wall upto height
metres above ground level consisting of 12mm thick backing coat Rupees Four Thousand Fifty One and
of c.m. 1:3 (1 cement : 3 sand) and 8 mm thick finishing coat of Paisa Seventy Seven Only
c.m. 1:1 (1 cement : 1 sand) etc. complete
Quantitiy Estimated Rates Total Amount
Quantitiy Estimated Rates Total Amount
Estimated Item Of Work Unit may be more or
may be more In Figure In word less
Finishing wall with weather proof exterior emulsion paint on wall
surface (two coats) to give an required shape even shade after
Rupees Two Hundred Eighty Nine and
12 3216.00 thoroughly brushing the surface to remove all dirt, and remains of 117.40 Cu.Mt.
loose powdered materials.etc complete
Total:- Total:-
In Words :- Rupees Seventy Nine Lakhs Three Thousand Four Hundred Sixty Eight Only.
I/we am/are willing to carry out the work at………………………………………………….% above/below percent (should be written in figures and words) of the
estimated rates mentioned above. Amount of my/our tender works out as under :
Estimated amount put to tender
Add / deduct…………….% above / below
In words (Rupees………………………………..
All works shall be carried out as per Public Work Department Handbook and other specification of Division or as directed.
All the columns in Schedules should be filled in ink and the total of the entries ink last column should be struck by the contractor under his signature.
Rates quoted include clearance of site ( prior commencement of work and at its close ). In all respect and hold good for work under all condition, site,
Serviceable material available ( if any ) after Demolishing / Dismentalling any item should be hand over to the concerned PIU Site Engineer In Charge
The Contractor shall exhibit a board with detailed specification and details of work as directed by the Engineer-In-Charge
for which no extra payment shall be made.
2 The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3 GST and Income tax TDS will be deducted at a source while making payments of bills
In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R.: PRC-10/2017 Cement
Consumption/16/C Date:11/05/2017 as stated in S.O.R. therefore in R.C.C. items where there is a change as per actual
mix design the costof difference of cement consumption have been deducted from the rate of original item at the rate of
input rate mentioned in all the tender. Input rate is Rs. _____________ MT.
5 GST extra applicable in case of work based on SOR 2024-25 only.
Dy. Executive Engineer Divisional Accountant Executive Engineer
PIU Zone-7 Tapi PIU Zone-7 Surat PIU Zone-7 Tapi
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Condition for cement.pdf
GR RnB Revise.pdf
GR-TMT-Lap Length.pdf
INSTRUCTIONS TO PERSON TENDERING.jpg
JPG
Performance Bond and SD-Paripatra-2023.pdf
PIU SPECIAL CONDITIONS.pdf
Inclusion of Insurance clause as per new SBD.pdf
6372 Make List HO 15.10.2025.pdf
Specification.pdf
Schedule B.pdf
SBD.pdf
Tender Document.pdf
Download all tender documents and submit your bid