| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹17.4 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹18.9 L+₹1.5 L (8.85%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | L3₹19.0 L+₹1.6 L (9.11%)Rejected-AOC | L3 | Rejected-AOC L3 | |
| 4 | L4₹19.5 L+₹2.1 L (11.9%)Rejected-AOC | L4 | Rejected-AOC L4 | |
| 5 | L5₹19.5 L+₹2.1 L (12.2%)Rejected-AOC | L5 | Rejected-AOC L5 |
Tender Value
₹22.3 L
EMD Value
₹33,500
Closing Date
4 Oct 2021, 5:00 pmClosed
Executive Engineer
Executive Engineer Irrigation Division, Kollam
SDRF - FLOOD DAMAGES 2018- Restoration of erroded embankment on the left bank of achankovil river near ambazhavelil bhagam in ward no . 19 of pramadam panchayath
2021_Irrig_441661_1
17/EEI/KLM/2021-22
Open Tender
Civil Works - Others
Item Wise
120 days
KONNI
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,800
Yes
₹33,500
Yes
1 Dec 2021
25 Sept 2021
8 Oct 2021
25 Sept 2021
4 Oct 2021
25 Sept 2021
Amount
Appendix A Rectifcation of Kadavu and retaining wall
60.7.3 : DISMANTLING DR - Dismanling , clearing away and carefully stacking materials useful for reuse for any thickness of walls in DR masonry including disposal of debris within a distance of 150m.
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
60.2.2 : Bailing out water Using 5HP Pump- Bailing out water with 5HP engine and pump set including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete
60.7.2 : DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site.
60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
60.7.8 : DR with Departmental. Stone - DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course using departmental rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site
7.1.1 : Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
Appendix B Rectification of embankment
60.7.6 : Supplying and stacking granite stone 20 to 45 dm3 for dumping works- Supplying at site of work granite stone 20 to 45 dm3 in size (60% 45m3,30%30 to 40dm3 and 10% 20 to 30dm3 stones) for measurement ( deducting not less than 15% for voids as fixed by the departmental officer at site) including all cost, conveyance, loading and unloading charges all other incidental charges all leads and lifts etc. complete as per the direction of the departmental officers at site.
60.7.7 : Conveyance and dumping of departmental granite stones-Conveyance of departmental granite stone 20 to 45 dm3 in size from stack at site and dumping in position (60% 45m3,30%30 to 40dm3 and 10% 20 to 30dm3 stones) to lines and levels to from the core of the sea wall as per approved design including all leads and lifts etc. complete as per the direction of the departmental officers at site.
60.7.2 : DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site.
16.95 : Providing & making Gabion structure with Mechanically Woven Double Twisted Hexagonal Shaped Wire mesh Gabion Boxes as per IS 16014:2012,MORTH Clause 2500, of required size, Mesh Type 10x12(D=100 mm with tolerance of ± 2%) Zinic+PVC coated, Mesh wire diameter2.7/3.7mm, mechanically edged/selvedged with partitions at every 1m interval and shall have minimum 10 numbers of openings per meter of mesh perpendicular to twist, tying with lacing wire of diameter 2.2/3.2mm(ID/OD), supplied @3% by weight of Gabion boxes, filled with boulders with least dimension of 200 mm, as per drawing, all complete as per directions of Engineer-in-charge.
5.1.3 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.9.1 : Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
Rectification of top landing
60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
50.10.1 : Steel work in built up G I tubular ( round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting,fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete
KUNJUMON DANIEL
BIJI K THOMAS
Mon Joseph
K.V.SUDIN
Bidder Name
Mon Joseph
V G RAJU
KUNJUMON DANIEL
BIJI K THOMAS
K.V.SUDIN
stage.html
html • 0.05 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_628357.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .