| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹10.5 LAccepted-AOC NEAR DOON INSTITUTE BHALLA FARM SHYAMPUR RISHIKESH DEHRADUN UK 249 204 | DEHRADUN | DEHRADUN | UTTARAKHAND | 249204 | L1 | Accepted-AOC Contract Awarded being lowest bidder. | |
| 2 | L2₹14.6 L+₹2.6 L (21.7%)Rejected-AOC 274 210 DAFNALA ROAD SHAHIBAUG AHMEDABAD GUJARAT 380009 | AHMADABAD | GUJARAT | 380009 | L2 | Rejected-AOC Rejected due to higher amount quoted. | |
| 3 | Rejected-Technical A 3 13 SIMANDHAR ENCLAVE NEAR PAVAPURI BUS STOP GHATLODIYA AHMEDABAD GUJARAT 380061 | AHMADABAD | GUJARAT | 380061 | - | Rejected-Technical Not admitted due to firm is not having appropriate category as mentioned in NIT i.e. b (ii) |
| Sl No | Description | Qty | Unit | ALBA AC AND REF SERVICES L2 | BK CONSTRUCTION L1 |
|---|---|---|---|---|---|
| 1.00 | Material and labour for detection of fault in HT line 11 KV , 95 Sqmm 3 core HT cable with the help of special T & P ( HT Fault Locator Machine etc) and marking the fault location complete all as specified and directed by Engr-in-charge. Note:- Cost of T & P of machine shall deemed to be incl in Quoted rate. | 10 | Each | 11,700 ₹1,17,000 | 6,000 ₹60,000 Lowest |
| 2.00 | Material and labour for rectification of fault in HT line 11 KV by manual excavation of faulty HT cable safely and joining of HT cable of size 95 Sqmm 3 core upto 7 RM with the help of two straight through cold shrink joint and returning filling the same after relaying of HV cover, sand cushionong complete all as specified and directed by Engr-in-charge. Note:- Rate of Earthwork, Cable jointing Kit, sand cushionoing and HT cable shall deemed to be incl in quoted rate. | 4 | Each Job | 31,500 ₹1,26,000 | 21,000 ₹84,000 Lowest |
| 3.00 | Material and labour for rectification of fault in HT line 11 KV by manual excavation of faulty HT cable safely and joining of HT cable of size 95 Sqmm 3 core upto 7 RM with the help of one straight through cold shrink joint, one Outdoor end termination cold shrink joint and returning filling the same after relaying of HV cover, sand cushionong complete all as specified and directed by Engr-in-charge. Note:- Rate of Earthwork, Cable jointing Kit, sand cushioning and HT cable shall deemed to be incl in quoted rate. | 3 | Each Job | 27,000 ₹81,000 | 19,000 ₹57,000 Lowest |
| 4.00 | Material and labour for rectification of fault in HT line 11 KV by manual excavation of faulty HT cable safely and joining of HT cable of size 95 Sqmm 3 core upto 7 RM with the help of one straight through cold shrink joint, one indoor end termination cold shrink joint and returning filling the same after relaying of HV cover, sand cushionong complete all as specified and directed by Engr-in-charge. Note:- Rate of Earthwork, Cable jointing Kit, sand cushioning and HT cable shall deemed to be incl in quoted rate. | 3 | Each Job | 24,300 ₹72,900 | 18,000 ₹54,000 Lowest |
| 5.00 | Supply and fix cable jointing kit for 11 KV grade cable for indoor termination Cold Shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured Al conductor cable of size 95 sq mm complete all as specified and directed. | 3 | Each | 6,390 ₹19,170 Lowest | 10,500 ₹31,500 |
| 6.00 | Supply and fix cable jointing kit for 11 KV grade cable for Outdoor termination Cold Shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured Al conductor cable of size 95 sq mm complete all as specified and directed. | 2 | Each | 6,750 ₹13,500 Lowest | 11,500 ₹23,000 |
| 7.00 | Supply and fix cable jointing kit for 11 KV grade cable for straight through Cold Shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured Al conductor cable of size 95 sq mm complete all as specified and directed. | 2 | Each | 13,500 ₹27,000 Lowest | 14,500 ₹29,000 |
| 8.00 | Dismantling cross-arms of M.S. channel or angle sections etc. complete and setting aside for re-use with in 50mbracings supports etc complete all as specified and directed | 3 | Qtl | 450 ₹1,350 Lowest | 500 ₹1,500 |
| 9.00 | Dismantling and taking down ACSR conductor complete all as specified.
Note :- Dismantling of MS work and insulators shall be measured and paid separately. | 2 | Qtl | 550 ₹1,100 | 200 ₹400 Lowest |
| 10.00Dismantling and removing of old HT Pole complete alongwith removing PCC debris from the pole and cleaning and deposit to MES store yard complete all as specified and directed by Engr-in-charge for the following types of poles | |||||
Tender Value
Refer Docs
EMD Value
₹30,000
Closing Date
15 Jul 2025, 6:00 pmClosed
CWE AHMEDABAD
CWE AHMEDABAD
REPAIR / REPLACEMENT AND IMPROVEMENT IN MAINTENANCE OF EXTERNAL ELECTRIC SUPPLY, HT EQUIPMENT , VCB , RMU, GOD / LBS AND HT CABLING UNDER GE (A) GANDHINAGAR AT GANDHINAGAR MIL STN
2025_MES_715206_1
87399/E8
Open Tender
Electrical and Maintenance Works
Item Rate
120 days
ARMY AREA GANDHINAGAR
AS PER TENDER DOCUMENT
6 documents required · 6 mandatory
₹500
GE (A) GANDHINAGAR
₹30,000
Yes
13 Dec 2025
18 Jun 2025
22 Jul 2025
18 Jun 2025
15 Jul 2025
3 Jul 2025
18 Jun 2025 - 2 Jul 2025
Amount
Material and labour for detection of fault in HT line 11 KV , 95 Sqmm 3 core HT cable with the help of special T & P ( HT Fault Locator Machine etc) and marking the fault location complete all as specified and directed by Engr-in-charge. Note:- Cost of T & P of machine shall deemed to be incl in Quoted rate.
Material and labour for rectification of fault in HT line 11 KV by manual excavation of faulty HT cable safely and joining of HT cable of size 95 Sqmm 3 core upto 7 RM with the help of two straight through cold shrink joint and returning filling the same after relaying of HV cover, sand cushionong complete all as specified and directed by Engr-in-charge. Note:- Rate of Earthwork, Cable jointing Kit, sand cushionoing and HT cable shall deemed to be incl in quoted rate.
Material and labour for rectification of fault in HT line 11 KV by manual excavation of faulty HT cable safely and joining of HT cable of size 95 Sqmm 3 core upto 7 RM with the help of one straight through cold shrink joint, one Outdoor end termination cold shrink joint and returning filling the same after relaying of HV cover, sand cushionong complete all as specified and directed by Engr-in-charge. Note:- Rate of Earthwork, Cable jointing Kit, sand cushioning and HT cable shall deemed to be incl in quoted rate.
Material and labour for rectification of fault in HT line 11 KV by manual excavation of faulty HT cable safely and joining of HT cable of size 95 Sqmm 3 core upto 7 RM with the help of one straight through cold shrink joint, one indoor end termination cold shrink joint and returning filling the same after relaying of HV cover, sand cushionong complete all as specified and directed by Engr-in-charge. Note:- Rate of Earthwork, Cable jointing Kit, sand cushioning and HT cable shall deemed to be incl in quoted rate.
Supply and fix cable jointing kit for 11 KV grade cable for indoor termination Cold Shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured Al conductor cable of size 95 sq mm complete all as specified and directed.
Supply and fix cable jointing kit for 11 KV grade cable for Outdoor termination Cold Shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured Al conductor cable of size 95 sq mm complete all as specified and directed.
Supply and fix cable jointing kit for 11 KV grade cable for straight through Cold Shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured Al conductor cable of size 95 sq mm complete all as specified and directed.
Dismantling cross-arms of M.S. channel or angle sections etc. complete and setting aside for re-use with in 50mbracings supports etc complete all as specified and directed
Dismantling and taking down ACSR conductor complete all as specified. Note :- Dismantling of MS work and insulators shall be measured and paid separately.
Dismantling and removing of old HT Pole complete alongwith removing PCC debris from the pole and cleaning and deposit to MES store yard complete all as specified and directed by Engr-in-charge for the following types of poles
Concrete/PCCpoles incl all Spl T &P like crane, JCB etc
Steel Tubular Poles incl all Spl T &P like crane, JCB etc
Dismantling and taking down insulator any type, any size complete all as specified
Dismantling and taking down Stay Assy complete all as specified.
Supply and Laying in trenches GI tubing light grade 100 mm bore protection of cable under road/ drain/ paving/ hard standing, pole.
Material and labour for PCC (1:2:4) type B-1 (Using 20 mm graded crushed stone aggregate) as in coping/benching including wheathing slightly chamfered on edge and finishes exposed surfaces even smooth without using extra cement including necessary form work complete all as specified and directed at site.
Material and labour for PCC (1:4:8) type D-2 (using 40 mm graded crushed stone aggregate) for foundation of pole/ Paving/drain etc complete all as specified and directed.
Disconnecting & taking down 11KV/433 volts unserviceable transformer of capacity upto 100 KVA from two pole structure (From Mily Station Gandhinagar) and transport to civil workshop including opening and dismantling for rewinding / repairing etc and reassemble after repair and reinstall at same location including replacement of unserviceable nuts, bolts and washers, etc and connecting, testing etc complete all as specified and directed. Note: - (i) The quoted rates shall be deemed to include for cost of crane for taking down transformer and cost of transportation of transformer to workshop and vice versa including all arrangement. (ii) Cost of HT / LT winding and other connected spare parts for repair will be measured & paid separately under respective items of schedule.
Disconnecting & taking down 11KV/433 volts unserviceable transformer of capacity upto 500 KVA from two pole structure (From Mily Station Gandhinagar) and transport to civil workshop including opening and dismantling for rewinding / repairing etc and reassemble after repair and reinstall at same location including replacement of unserviceable nuts, bolts and washers, etc and connecting, testing etc complete all as specified and directed. Note: - (i) The quoted rates shall be deemed to include for cost of crane for taking down transformer and cost of transportation of transformer to workshop and vice versa including all arrangement. (ii) Cost of HT / LT winding and other connected spare parts for repair will be measured & paid separately under respective items of schedule.
Material and labour, in repairs, rewinding of the core / coil of transformer with mass impregnated copper winding wire of appropriate gauge with thermal class 'E' insulating material and varnishing incl insulation paper, glass tape, Bamboo clamps etc complete all as per specified and directed.
Supply and fixing, in repair, LT bush insulator suitable for 500/400/315/250/100/63 KVA capacity of transformer.
Supply and fixing, in repair, LT bush (rod) spindle of brass complete with washer and nut suitable for existing size and lengths of 500/400/315/250/100/63 KVA capacity of transformer complete all as per specified and directed.
Supply and fixing, in repair, HT bush insulator of 11 KV rating for outdoor transformer suitable for 500/400/315/250/100/63 KVA capacity transformer complete all as per specified and directed.
Supply and fixing, in repair, HT bush (rod) spindle made out of brass with nut, bolts and washers suitable for 500/400/315/250/100/63 KVA capacity transformer, complete all as per specified and directed.
Supply and fixing, in repair, rubber gasket set 6mm thick for transformer incl top cover gasket of capacity upto 400 KVA complete all as per specified and directed.
Dehydration and filtration of transformer oil of the transformer mounted on floor/ on poles using filtration plant. The process of dehydration and filtration shall be continuous till the dielectric strength does not achieved 50 KV. Note: Contractor shall arrange filtration/dehydration machine and other required T&P at site.
Supply & topping up transformer oil in existing transformer, the di-electric strength not less than 50 KV all as specified and as directed by Engineer-in-Charge.
Material and labour for horizontal boring by using the trenchless technology under the road at least 60 Cm below road top, in any type of soil for insertion of GI pipe of 100 mm bore.
Servicing and overhauling of 11 KV VCB by cleaning and lubrication mechanism, panel checking & cleaning of fix and movable contact including checking of CT ratio and breaker tripping by primary injection and calibration of relay and setting of 11KV HT VCB, relay testing control & power circuit with IR testing report as per required operation all as directed by Engineer-in-charge.
Supply and Fix in repair Transformer accessories such as Horngap, breather assembly with Silica gel, Conservater Tank level indiactor, rubber gaskets etc incl fixing of leakages by fabrication and welding complete all as specified and directed
Servicing and overhauling of medium voltage switchgear Make Siemens, TYPE- 8DJH ST, voltage upto 12 KV, Gas Insulated, Extendable by cleaning and lubrication mechanism, On Off Operation Check, Relay Testing Control & Power Circuit with IR Testing Report in hard copy including setting as per required operation and compatible with GEB (Gujrat Electricity Board) complete all as specified and directed by Engr-in-charge. The following scope of work will be under the scope of work per Circuit breaker under preventive maintainenece which is depicted below:-
(i) CHECKING OF THE OPERATION OF BREAKER THROUGH ELECTRICAL & MECHANICAL MODE (ii) REMOVE ALL THE WORNED OUT O RINGS & GASKETS AND REPLACE THE SAME (iii) APPLYING NECESSAEY ERAMIC ADHESIVES/ EPOXY PASTES/ SILICA SEALANT WHEREVER NECESSARY (iv) CHECKING OF CLOSE , TRIP COILS & INSULATION VALUES, OHMIC VALUES & CHECKING OF THE HEALTHINESS OF COILS (v) REPLACING THE DEFECTIVE DC COILS, LIMIT, TNC, L/R & AUXILIARY SWITCHES (vi) REPLACING THE TRIP BLOCK ASSEMBLY & DEFETCED MECHANISM SHELTER/ CUBICLE (vii) CHECKING THE INTERRUPTER HEALTHINESS FOR THE FIXED CONTACTS FOR BREAKERS (viii) CHECKING OF INSULATION RESISITENCE VALUE WITH 5KV MEGGER (IR VALUE) (ix) CHECKING THE CONTACT RESISTANCE VALUE FOR ALL THREE POLES (x) CARRYOUT THE TIME INTERVAL TEST FOR THE BREAKER POLES (xi) CHECKING & DISMANTLING THE OPERATING MECHANISM IF IT FOUND WITH SETTING DISTURBED AND RE- ASSEMBLING THE SAME ONCE THE OVERHAULING IS OVER (xii) CHECKING OF ALL CONTROL & RELAY CABLES (xiii) CHECKING OF TIGHTNESS FOR MOVING & FIXED ARCHING, MAIN CONTACTS (xiv) CHECKING OF SHUNT TRIP DEVICE & COIL (xv)CHECKING THE SENSITIVENESS OF THE TRIPPING OF THE BREAKER THROUGH RELAY (xvi) CHECKING OF TIGHTNESS OF ALL CONTROL CABLES (xvii) CHECKING OF THE FREEWHEELING OF OPERATING MECHANISM & APPLY THE REQUIRED LUBRICATIONS (xviii) MEASURING & FILLING OF GASES IF BREAKER IS SF6 TYPE (IF GCB) (xix) ENTIRE CLEANING OF BREAKER & FEEDER AND APPLYING GREASING & LUBRICATIONS IN WHEREVER IT REQUIRED TO BE APPLIED
Material and labour including installation, testing and commissioning of Trivector meter 11 KV/110V PT ratio and 75/50/5/5 A CT ratio, A class 0.5 with RS485 for Main incomer VCB type 12VE12, rated voltage 12000 V, current 400 A,, breaking capacity 13.1 kA, Making Capacity -33 kAp, short time current13.1 for 1 sec incl control wiring complete all as specified and directed by Engr-in-charge .
Supply and Fix in repair Master Trip relay 110 V DC comptible to existing VCB 12VE12, rated voltage 12000 V, current 400 A,, breaking capacity 13.1 kA, Making Capacity -33 kAp, short time current13.1 for 1 sec with type AVAJH13, voltage-24-30 VDC, Cont: 40NO + 1 NC HR complete all as specified and directed by Engr-in-charge.
Supply and Fix in repair ON/OFF Butterfly leaf asembly suitable for medium voltage switchgear Make Siemens, TYPE- 8DJH ST, voltage upto 12 KV, complete all as specified and directed by Engr-in-charge.
Supply and Fix in repair 24 volt DC spring charging motor assembly with limit switch suitable for medium voltage switchgear Make Siemens, TYPE- 8DJH ST, voltage upto 12 KV, complete all as specified and directed by Engr-in-charge. The motor assembly shall perform follwing operating mechanism sucessfully:- (i) Operating mechanism for circuit-breaker (ii) Operating mechanism for three-position disconnector (iii) Interlocking between circuit-breaker and disconnector
Supply and Fix in repair medium Voltage 11 KV Insulating right angle boots, Cold applied unscreened elastomeric insulating boots (in Silicon or EPDM) are moulded parts, fitted over the connection between a cable lug and inline or right-angled equipment bushing, to improve phase-to-phase and phase-to-ground insulation having elastomeric housing excellent erosion resistance, dielectric properties, and environmental resistance, giving superb performance in areas of high humidity and electrical stresses,Tool free application, High-performance insulation material,excellent track and erosion resistance complete all as specified and directed by Engr-in-charge.
Supply and Fix Danger notice plate of 25 cm x 20 cm size, 1.6mm thick mild steel sheet, vitreous enamelled white, with letters, figures and conventional skull and bones in signal red colour and fixed with M.S. clamps, bolts and nuts complete all as specified and directed by Engr-in-charge.
ALBA AC AND REF SERVICES (BID ID -3348431)
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .