| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.2 LAccepted-AOC | L1 | Accepted-AOC First Lowest | |
| 2 | L2₹8.0 L−₹27,580.54 (3.35%)Rejected-AOC | L2 | Rejected-AOC Second Lowest | |
| 3 | Rejected-Technical | - | Rejected-Technical tender documents are perfect | |
| 4 | Rejected-Technical | - | Rejected-Technical tender documents are perfect |
Tender Value
₹9.7 L
EMD Value
₹24,364
Closing Date
30 Nov 2023, 3:00 pmClosed
Assistant Executive Engineer
O/o The Assistant Executive Engineer,Spl Buildings Subdivision, Ayurveda College, Tvpm
DEPOSIT-Compound wall construction and wire mesh works in Government Ayurveda College Mens Hostel Poojapura, Thiruvananthapuram.-Construction of compound wall and wire mesh works
2023_PWD_624710_1
PWD/BLDG/TR/3237/2023_5_1_1/1
Open Tender
Civil Works - Buildings
Item Rate
120 days
Thiruvananthapuram
Please refer Tender documents.
9 documents required · 9 mandatory
₹2,150
Yes
₹24,364
Yes
21 Jun 2024
23 Nov 2023
2 Dec 2023
23 Nov 2023
30 Nov 2023
23 Nov 2023
Amount
compound wall
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
2.28.1:Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m.All kinds of soil
15.18:Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates,boltd, nuts, cutting rivets, welding etc. including dismembering and stacking within 50 metres lead.
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
15.9.2:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:In cement mortar
OD172397/2023-2024:Random rubble masonry with hard stone(departmental supply) in foundation and up to plinth level with Cement mortar 1:6 (1 cement : 6 coarse sand)
7.1.1:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
50.6.1.1:Solid block masonry using pre cast solid blocks ( factory made) of size 40x20x20cm or nearest available size confirming to IS 2185 part 1 of 1979 for foundation and plinth with thickness 20 cm and above in: CM 1:6 ( 1 cement : 6 coarse sand) etc complete
14.72:Providing and fixing double scaffolding system (cup lock type) on the exterior side, upto seven story hight made with 40 mm dia. M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staricase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after. The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required location with essential safety features for the workmen etc. complete as per directions and approval of Engineer- in Charge. The elevational area of the scaffolding shall be measured for payment purpose. The payment will be made once irrespective of duration of scaffolding. Note:- This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done .
13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
13.46.1:Finishing walls with Acrylic Smooth exterior paint of required shade:New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm)
OD172331/2023-2024:Providing and fixing GI Weld Mesh(opening size 25x25mm and having wire diameter of at least 3.8 mm) on frames (paid separately) including all cost of materials and labour charges etc complete as per the direction of Engineer-in -Charge
10.2:Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.
50.10.1:Steel work in built up G I tubular ( round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting,fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete
13.52.1:Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer's specifications including appropriate priming coat, preparation of surface, etc. complete.On steel work
OD173433/2023-2024:Labour engaged for cleaning , etc
CHANDRAN.S
TVM TALUK ITI CERTIFICATE HOLDERS CO-OP SOCIETY Ltd
V.HARIKUMAR
Bidder Name
V.HARIKUMAR
TVM TALUK ITI CERTIFICATE HOLDERS CO-OP SOCIETY Ltd
CHANDRAN.S
RAJESH S R
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_941313.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .