| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.4 LAccepted-AOC | ₹5.4 L | L1 | Accepted-AOC Quoted 1.5 percentage below estimate rate on negotiation. |
| 2 | L2₹5.7 L+₹35,594.01 (6.60%)Rejected-AOC | ₹5.7 L+₹35,594.01 (6.60%) | L2 | Rejected-AOC Quoted rate is 5 percentage above estimate rate |
| 3 | L3₹5.9 L+₹46,546.01 (8.63%)Rejected-AOC | ₹5.9 L+₹46,546.01 (8.63%) | L3 | Rejected-AOC Quoted rate is 7 percentage above estimate rate |
Tender Value
₹5.5 L
EMD Value
₹14,000
Closing Date
15 May 2026, 4:00 pmClosed
Assistant Executive Engineer
Office of the Assistant Executive Engineer, Electrical Sub Division, Chithirapuram - 685565
Reconductoring LT ABC Kovilkadavu Transformer under Electrical Section, Marayoor.
2026_KSEB_848911_1
03/2026-27/AEE/ESD/CPM
Open Tender
Electrical Works
Percentage
120 days
Marayoor
Please refer Tender documents.
6 documents required · 6 mandatory
₹1,298
₹14,000
6 Jun 2026
27 Apr 2026
22 May 2026
27 Apr 2026
15 May 2026
27 Apr 2026
27 Apr 2026 - 15 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Providing Stay for LT poles including digging & back filling pit in ordinary soil. | 40 | No | 938.82 | ₹37,552.8 |
| 2.01 | Fitting and providing one HT Stay for 11kV pole, including digging and back filling pit in ordinary soil. | 8 | No | 1,373.73 | ₹10,989.84 |
| 3.01 | Dismantling (without damage) one km LT three phase 4 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. | 3 | km | 14,129.32 | ₹42,387.96 |
| 4.01 | Dismantling (without damage) one km LT additional conductor line by dismantling cross arms, insulators and stacking the conductors in rolls properly. | 3 | km | 3,351.73 | ₹10,055.19 |
| 5.01 | Dismantling (without damage) one km LT single phase 2 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. | 1 | km | 7,443.64 | ₹7,443.64 |
| 6.01 | Erecting one LT PSC Pole in position including digging & back filling pit in ordinary soil. | 38 | No | 2,017.73 | ₹76,673.74 |
| 7.01 | Labour charges for loading LT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). | 40 | No | 478.82 | ₹19,152.8 |
| 8.01 | Insertion of one HT PSC pole in existing HT/LT line including digging & back filling of pit in ordinary soil, fitting cross arm, insulator, binding etc. , drawing sufficient length of GI earth leads to the ground for earthing (excluding provision of earthing). | 7 | No | 4,089.82 | ₹28,628.74 |
| 9.01 | Labour charges for loading HT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). | 8 | No | 762.14 | ₹6,097.12 |
| 10.01 | Providing Strut using LT PSC pole including digging and back filling pit in ordinary soil. | 2 | No | 1,887.05 | ₹3,774.1 |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1434534.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.16 MB
Generalconditionsofcontract.pdf
Tender Documents • 1.13 MB
GeneraletenderCondition.pdf
Tender Documents • 0.68 MB
SpecialConditions.pdf
Other Document • 0.49 MB
GSTRegistrationQuestionnaire.pdf
Additional Documents • 0.02 MB
BOQ_1434534.xls
BOQ • 0.26 MB
NIT.pdf
Tender Documents • 0.15 MB
Datecorrigendum_0001.pdf
PDF • 0.18 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .