Tender Value
₹44.3 L
EMD Value
₹45,000
Closing Date
3 Oct 2026, 6:00 pm6d left
Executive Engineer, N.P. Main Canal Division No. 19, Harij
Providing, Supplying, Laying & Fixing RCC NP-3 Pipeline for connecting existing well syphon @ ch.3878 mt to well syphon @ ch.4955 mt. of Loteshwar Minor-2 Canal.
344560
05 of 2026-27
Open
Civil Works - Canal
Works
Patan
8 documents required · 7 mandatory · 1 optional
₹1,770
Executive Engineer, N.P.Main Canal Division No. 19, Harij
₹45,000
11 Sept 2026
11 Sept 2026
11 Sept 2026
3 Oct 2026
11 Sept 2026
Providing, Supplying, Laying & Fixing RCC NP-3 Pipeline for connecting existing well syphon @ ch.3878 mt to well syphon @ ch.4955 mt. of
Loteshwar Minor-2 Canal.
It. Rate in Rs.
Qty Description Per Amount in Rs.
No. In Fig. In Words
1 4456.000 Excavation in all sorts of soil (including wet and slushy condition of soil)
with yellow, sandy, gravelly soil including soft murrum & H.M. including
sorting & stacking and depositing the excavated stuff in uniform layers
as and where directed upto lead of 30 m and lift as shown below
including clearing the site etc. compute (including dewatering). (B) For
foundation trenches of C.D. work (a) 0 to 3 Mt. depth Rupees Seventy Nine
2 52.110 Dismentalling of RCC work viz. slab, beam,lintel,barrel,staircase etc.
including removing the steel from the dismentelled portion without
damage to reinforcement sorting & stacking of useful and unuseful Rupees One Thousand
material from the dismentalled materials as directed under detailed Five Hundred Fourteen
specifications etc. complete. 1514.90 And Paise Ninety Only Cmt
3 71.000 Providing and laying foundation concrete of proportion as under by using Rupees Three
cement, sand and machine crushed course aggregate laid in situ Thousand Four
including necessary temping, smooth finishing, watering and curing as Hundred Twenty Four
directed with all leads and lifts etc complete. (a) PCC 1:3:6 3424.30 And Paise Thirty Only Cmt
4 700.000 Providing, Supplying, Laying & Fixing in position under ground R.C.C.
hume pipes of NP 3 class as per I.S. specification of prescribed
diameter incl. filling the joints & providing & fixing necessary collars with
cement mortar 1:1 inclusive of testing for leakage & working pressure as Rupees One Thousand
directed with all cost of materials & labour for all leads & lifts etc Nine Hundred Eleven
complete.(c) 600 mm dia. 1911.90 And Paise Ninety Only Rmt
Schedule-B Page 1 of 4 Schedule-B
It. Rate in Rs.
Qty Description Per Amount in Rs.
No. In Fig. In Words
5 315.300 Providing and laying CC 1:2:4 grade using cement, sand & crushed Rupees Four Thousand
metal incuding providing & erecting necessary form work, centering, Eight Hundred Seventy
vibrating, smooth finishing, watering & curing as directed with all leads & Three And Paise Forty
lifts etc. complete. (a) Sub structures 4873.40 Only Cmt
6 83.000 Providing and laying RCC 1:1.5:3 grade by using cement, sand and
crushed metal for different items like copping work, pier cap, abutment
cap, Wearing coat, Skin concrete, Solid slab upto 60 cm. thick, Barrel of
canal syphons, barrel of R.C.C. through, & beams for foundation and
super structure as per approved design incl. providing necessary
centering, shuttering and form work, vibrating, smooth finishing, Rupees Five Thousand
watering and curing as directed with all leads and lifts etc. comp. One Hundred One And
5101.40 Paise Forty Only Cmt
7 2175.000 Backfill with selected earth including ramming consolidation including Rupees Sixty Seven
watering with lead as under and all lifts etc. complete. (a) 0 to 30m. 67.00 Only Cmt
8 3.550 Providing and laying HYSD/TMT Fe 500 steel bar reinforcement for
R.C.C. works and anchor bar with providing binding wires including
cutting, bending, welding, binding in position hooking, placing in position Rupees Seventy One
with all leads & lifts etc. complete.(B) TMT Fe 500 steel bars Thousand Three
71366.00 Hundred Sixty Six Only MT
9 20.000 Providing and placing steel steps of 25 mm dia M.S. bar including Rupees Two Hundred
cutting bending and fixing in the wall of H.R. well etc comp. Forty Nine And Paise
249.73 Seventy Three Only No.
10 23.040 Providing laying and fixing 20 mm dia Grill 22 cms c/c including
necessary openings support, oil painting with 1 coat primer and two Rupees Two Thousand
coats of approved oil paint etc. completed. One Hundred Ninety
2198.00 Eight Only SMT.
Rupees Forty Four Lakh(s) Twenty Seven Thousand One Hundred Thirty And Paise Seventy Seven Only Total Amount Rs.
Rupees Forty Four Lakh(s) Twenty Seven Thousand One Hundred Thirty And Paise Seventy Seven Only Total Amount Rs.
N.P.M.C.Division No.19,Unit-2
Schedule-B Page 2 of 4 Schedule-B
Providing, Supplying, Laying & Fixing RCC NP-3 Pipeline for connecting existing well syphon @ ch.3878 mt to well syphon @ ch.4955
mt. of Loteshwar Minor-2 Canal.
CEMENT CONSUMPTION STATEMENT
Description Qty Rate in Bags Per
3 Providing and laying foundation concrete of proportion as under by using cement, sand
and machine crushed course aggregate laid in situ including necessary temping, smooth
finishing, watering and curing as directed with all leads and lifts etc complete. (a) PCC
4 Providing, Supplying, Laying & Fixing in position under ground R.C.C. hume pipes of NP
3 class as per I.S. specification of prescribed diameter incl. filling the joints & providing &
fixing necessary collars with cement mortar 1:1 inclusive of testing for leakage & working 700.00 0.062 Rmt
pressure as directed with all cost of materials & labour for all leads & lifts etc complete.(c)
5 Providing and laying CC 1:2:4 grade using cement, sand & crushed metal incuding
providing & erecting necessary form work, centering, vibrating, smooth finishing, watering 315.30 6.400 Cmt
& curing as directed with all leads & lifts etc. complete. (a) Sub structures
6 Providing and laying RCC 1:1.5:3 grade by using cement, sand and crushed metal for
different items like copping work, pier cap, abutment cap, Wearing coat, Skin concrete,
Solid slab upto 60 cm. thick, Barrel of canal syphons, barrel of R.C.C. through, & beams
for foundation and super structure as per approved design incl. providing necessary
centering, shuttering and form work, vibrating, smooth finishing, watering and curing as
directed with all leads and lifts etc. comp.
Dy.Ex.Engineer Executive Engineer
N.P.M.C.Division No.19,Unit-2 N.P.M.C.Division No.19
Schedule-B Page 3 of 4 Cement Consumption
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
1 SBD.pdf
2 Schedule B.pdf
3 SPECIFICATION.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .