| 1 | L1₹9.0 LAccepted-AOC | L1 | Accepted-AOC L1 Bidder | |
| 2 | L2₹9.4 L+₹31,391 (3.45%)Rejected-Finance | L2 | Rejected-Finance Unsuccessful Bidder | |
| 3 | L3₹9.5 L+₹38,711 (4.25%)Rejected-Finance | L3 | Rejected-Finance Unsuccessful Bidder | |
| 4 | L4₹9.5 L+₹40,368 (4.44%)Rejected-Finance BHATI ABHOYNAGAR WEST VIVEKANANDA CLUB ROAD NEAR HOUSE OF DOCTOR GOURISHANKAR CHAKRABORTY P O AGARTALA TRIPURA WEST PIN 799001 | AGARTALA | WEST TRIPURA | TRIPURA | 799001 | L4 | Rejected-Finance Unsuccessful Bidder | |
| 5 | L5₹10.0 L+₹86,971 (9.56%)Rejected-Finance ABHAYNAGAR JAGATPUR PO ABHAYNAGAR AGARTALA WEST TRIPURA | AGARTALA | WEST TRIPURA | TRIPURA | L5 | Rejected-Finance Unsuccessful Bidder |
Tender Value
₹9 L
EMD Value
₹18,000
Closing Date
20 Jun 2023, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
AGE (I) AGARTALA
AGE (I) AGARTALA PIN 901184 C/O 99 APO
REPAIR TO PLINTH PROTECTION, BRICK WORK, PLASTERING AND ATT TREATMENT AND ALLIED WORKS AT MIL STN AGARTALA
2023_MES_597787_1
8394/E8
Open Tender
Civil Works
Item Rate
180 days
AGARTALA
Please refer Tender documents.
8 documents required · 8 mandatory
₹500
AGE (I) AGARTALA
₹18,000
Yes
26 Jun 2023
23 May 2023
22 Jun 2023
23 May 2023
20 Jun 2023
6 Jun 2023
Amount
Schedule'A' Part-I: B&R works
Demolition of un-reinforced cement concrete in ground floors and pavings not exceeding 15 cm thickness, (Below or above ground level) and disposal of unsv materials, debris and rubbish to a distance not exceeding 100 M as directed .
M & L 75mm thick PCC 1:3:6 type C-1 ( 20mm graded aggregate) thick as in Path & plinth protection & finishing the surface even & fair without using extra cement complete all as specified .
M&L PCC in surface channels and drains type B1 (1:2:4) using 20 mm graded stone aggregate complete all as specified .
M&L for Hardcore of Broken bricks gauge n exc. 63mm, deposited, spread & levelled in layers n exc. 15 cm thick, watered & rammed to a true surface complete all as specified .
S& F in repair 110mm bore , for PVC (SWR) pipes single socketed, in any length with rubber ring joints, laid in trenches or in floors complete all as specified
Demolition of brick work, built in cement mortar complete all as specified .
M & L brick work with sub class "B" bricks, straight or curved on plan exc 6 m mean radius, built in cement mortar (1:4) using old size bricks complete as specified.
M&L for Brick work with sub-class `B' bricks, straight or curved on plan to any radius in half brick thick walls built in cement mortar 1:4 complete all as specified .
Taking down cement plaster on wall of any description including racking out joints, hacking for key and scrubbing down with water etc complete all as specified .
M & L 15mm thick rendering on fair faces of brick work or concrete surface in cement mortar 1:4 to mixed with WPC @2% by weight of cement (200 ml per bag of cement) be finished fair and even with out using extra cement complete all as specified .
M & L 15mm thick rendering on other than fair faces of brick work or concrete surface in cement mortar 1:6 to be finished fair and even with out using extra cement complete all as specified .
Supply only liquid water proofing compound
M&L for applying two coats of cement base paint, white or tinted on new wall surface including preparation of surface complete all as specified
M & L two coat of Colour wash on new unplastered wall Surface including preparation of new surfaces complete all as specified
M&L for Finishing walls with Acrylic Smooth exterior paint of required shade : New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm)including preparation of new Surface complete all as specified.
M&L for along the external wall below concrete or masonry apron using chemical emulsion@ 2.25 litres per linear metre including drilling and plugging holes etc. in apron. complete all as specified.
M&L for providing & injecting chemical emulsion for Post Constructional Anti-termite Treatment along external wall where the apron is not provided using chemical emulsion @ 7.5 litres / Sqm of the vertical surface of the sub-structure to a depth of 300mm including excavating channel along the wall & rodding etc.complete all as specified
Treatment of soil under existing floors using emulsion @ 01 litre / hole, 300mm apart including drilling & sealing 12mm dia holes with CM(1:2) to match the existing floors complete all as specified .
M&L for post construction Anti termite treatment at point of contact of wood work by chemical emulsion (in oil or Kerosene based solution) @ 0.50 litre / hole by drilling 6 mm dia holes at a downward angle of 45 degree at 150 mm centre to centre and sealing the same complete all as specified .
NOTES :- 1. The amount of schedule of credit shall be deducted from the total of this BOQ for arriving at contract sum. 2. Unless otherwise specified the rates for PCC shall deemed to include the cost of formwork shuttering etc, required for complete and proper execution of the work. Refer Schedule 'A' notes for details.
M/S SANKAR GOPE
Pranjit kar
SUMAN DEB
M/S SWAPAN DEBNATH
M/S PRITAM ENTERPRISES
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.PDF
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .