| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.7 LAdmitted-Finance | ₹1.7 L | L1 | Admitted-Finance |
| 2 | L2₹1.7 L+₹680.75 (0.40%)Admitted-Finance | ₹1.7 L+₹680.75 (0.40%) | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | Nota Ram Contractor L2 | kesar singh contractor L1 |
|---|---|---|---|---|---|
| 1.00 | Demolition of RCC work by mechanical means and stock piling at designated locations and disposal of dismentled materials upto a lead of 1 km, stacking servicable and unservicable material separately including cutting reinforcement bars complete in all respect with in all leads and lifts as per the direction and direction and satisfactionof Engineer-in-charge. | 1.52 | Cum | 2,300 ₹3,496 | 2,200 ₹3,344 Lowest |
| 2.00Providing form work with steel plates 3.15mm thick welded with angle iron in frame 30x30x5mm so as to give a fair finish I/c centring , shuttering , strutting and proping etc.with wooden battens and ballies, height of propping and centring below supporting floor to ceiling not exceeding 4m and removal of the same for insitu- reinforced concrete &plain concrete work in :- | |||||
| 2.01 | suspended floors, roofs,landings and shelves and their supports, balconies, beams, girders, bressumers and cantilivers up to floor two level complete in all respect with in all leads and lifts as per the direction and direction and satisfactionof Engineer-in-charge. | 13.85 | Sqm | 775 ₹10,733.75 | 750 ₹10,387.5 Lowest |
| 3.00 | Providing and laying cement concrete 1:2:4 ( 1cement:2 sand: 4graded stone aggregate 20 mm nominal size )and curing complete excluding the cost of form work and reinforcement in:- Slab complete in all respect with in all leads and lifts as per the direction and direction and satisfactionof Engineer-in-charge. | 1.61 | Cum | 9,250 ₹14,892.5 | 9,200 ₹14,812 Lowest |
| 4.00 | Prov. Tor steel reinforcement for RCC work @52 Kg / Cum complete in all respect with in all leads and lifts as per the direction and direction and satisfactionof Engineer-in-charge. | 222.05 | Kg | 95 ₹21,094.75 Lowest | 95 ₹21,094.75 Lowest |
| 5.00 | Fixing . 500 mm dia man hole cover with frame complete in all respect with in all leads and lifts as per the direction and direction and satisfactionof Engineer-in-charge. | 1 | No. | 2,500 ₹2,500 Lowest | 2,500 ₹2,500 Lowest |
| 6.00 | 20 mm cement plaster in single coat on rough side of brick/concrete/ stone walls for interior plastering up to floor two levels including arrises, internal rounded angles, chamfers and/or rounded angles not exceeding 80 mm in girth and finished even and smooth in cement mortar 1:4 (1 cement:4 sand) in all leads and lifts as per the direction and direction and satisfactionof Engineer-in-charge. | 67.82 | Sqm | 400 ₹27,128 Lowest | 400 ₹27,128 Lowest |
| 7.00 | White washing with lime on undecorated wall surfaces two coats to give an even shade including thoroughly brooming the surface to remove all dirt , dust and other foreign matters in all leads and lifts as per the direction and direction and satisfactionof Engineer-in-charge. | 35.61 | Sqm | 22 ₹783.42 Lowest | 22 ₹783.42 Lowest |
| 8.00 | Excavation in earth work and disposal of excavated earth upto a lead of 20 metres and lift upto 1.50 metres, disposed earth to be levelled and neatly dressed in Pick-Jumper work. | 2.04 | Cum | 560 ₹1,142.4 Lowest | 560 ₹1,142.4 Lowest |
| 9.00 | Providing and laying cement concrete 1:3:6 (1 cement: 3 sand: 6 graded stone aggregate 40mm nominal size) excluding cost of centring & shuttering in. | 0.65 | Cum | 8,500 ₹5,525 Lowest | 8,500 ₹5,525 Lowest |
Tender Value
₹1.5 L
EMD Value
₹3,000
Closing Date
9 Sept 2026, 5:00 pmClosed
EE
Executive Engineer JS Division Baggi Distt. Mandi H.P.
as per BOQ
2026_HPIPH_142096_1
EE-JSD-BGI-TA-Tender/2026- 15166-215 dt. 26/8/2026
Open Tender
Civil Works - Bridges
Item Rate
90 days
Baggi
as per NiT
6 documents required · 6 mandatory
₹350
₹3,000
15 Sept 2026
28 Aug 2026
10 Sept 2026
28 Aug 2026
9 Sept 2026
28 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolition of RCC work by mechanical means and stock piling at designated locations and disposal of dismentled materials upto a lead of 1 km, stacking servicable and unservicable material separately including cutting reinforcement bars complete in all respect with in all leads and lifts as per the direction and direction and satisfactionof Engineer-in-charge. | 1.52 | Cum | - | - |
| 2Providing form work with steel plates 3.15mm thick welded with angle iron in frame 30x30x5mm so as to give a fair finish I/c centring , shuttering , strutting and proping etc.with wooden battens and ballies, height of propping and centring below supporting floor to ceiling not exceeding 4m and removal of the same for insitu- reinforced concrete &plain concrete work in :- | |||||
| 2.01 | suspended floors, roofs,landings and shelves and their supports, balconies, beams, girders, bressumers and cantilivers up to floor two level complete in all respect with in all leads and lifts as per the direction and direction and satisfactionof Engineer-in-charge. | 13.85 | Sqm | - | - |
| 3 | Providing and laying cement concrete 1:2:4 ( 1cement:2 sand: 4graded stone aggregate 20 mm nominal size )and curing complete excluding the cost of form work and reinforcement in:- Slab complete in all respect with in all leads and lifts as per the direction and direction and satisfactionof Engineer-in-charge. | 1.61 | Cum | - | - |
| 4 | Prov. Tor steel reinforcement for RCC work @52 Kg / Cum complete in all respect with in all leads and lifts as per the direction and direction and satisfactionof Engineer-in-charge. | 222.05 | Kg | - | - |
| 5 | Fixing . 500 mm dia man hole cover with frame complete in all respect with in all leads and lifts as per the direction and direction and satisfactionof Engineer-in-charge. | 1 | No. | - | - |
| 6 | 20 mm cement plaster in single coat on rough side of brick/concrete/ stone walls for interior plastering up to floor two levels including arrises, internal rounded angles, chamfers and/or rounded angles not exceeding 80 mm in girth and finished even and smooth in cement mortar 1:4 (1 cement:4 sand) in all leads and lifts as per the direction and direction and satisfactionof Engineer-in-charge. | 67.82 | Sqm | - | - |
| 7 | White washing with lime on undecorated wall surfaces two coats to give an even shade including thoroughly brooming the surface to remove all dirt , dust and other foreign matters in all leads and lifts as per the direction and direction and satisfactionof Engineer-in-charge. | 35.61 | Sqm | - | - |
| 8 | Excavation in earth work and disposal of excavated earth upto a lead of 20 metres and lift upto 1.50 metres, disposed earth to be levelled and neatly dressed in Pick-Jumper work. | 2.04 | Cum | - | - |
| 9 | Providing and laying cement concrete 1:3:6 (1 cement: 3 sand: 6 graded stone aggregate 40mm nominal size) excluding cost of centring & shuttering in. | 0.65 | Cum | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.67 MB
TC.pdf
Tender Documents • 0.14 MB
BOQ_210971.xls
BOQ • 3.76 MB
FORM6_3.pdf
Tender Documents • 0.63 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .