| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.1 LAccepted-AOC CHITRANGI KHATAI SINGRAULI DISTT SINGRAULI M P 486882 | SINGRAULI | SINGRAULI | MADHYA PRADESH | 486882 | L1 | Accepted-AOC As per NIT | |
| 2 | L2₹2.2 L+₹43,054.22 (24.6%)Rejected-AOC PARASI PO KAKERI DISTT SONEBHADRA UP 231224 | PARASI | SONEBHADRA | UTTAR PRADESH | 231224 | L2 | Rejected-AOC As per NIT | |
| 3 | L3₹2.4 L+₹66,376 (37.9%)Rejected-AOC RIVER SIDE BHURKUNDA RAMGARH JHARKHAND | RAMGARH | RAMGARH | JHARKHAND | L3 | Rejected-AOC As per NIT |
Tender Value
₹2.6 L
EMD Value
₹3,300
Closing Date
23 Aug 2024, 9:00 amClosed
Project Engineer EnM Bhurkunda colliery
Office of Project Engineer EnM Bhurkunda colliery
Complete Repairing and rewinding of 315KVA, 3.3KV/550V Andrew Yule MakeFLP air cooled Distribution transformer of Bhurkunda project under Barka Sayal Area.
2024_CCL_314909_1
PE(EnM)/BHK/e Tender/24-25/14
Open Tender
Electrical and Maintenance Works
Item Rate
15 days
Office of Project Engineer EnM Bhurkunda colliery
Please refer tender document.
2 documents required · 2 mandatory
₹3,300
5 Feb 2025
12 Aug 2024
24 Aug 2024
13 Aug 2024
23 Aug 2024
13 Aug 2024
13 Aug 2024 - 19 Aug 2024
Amount
Cost of Copper strip (Primary and Secondary) with DGC covering size- 9 SWG
Insulation Cost
Labour Cost
Less scrap @60% of Sl. No. 01
Supply and fixing of HT Bushing Insulator with studs
Contractor's Profit
Total impact of GST for the purpose of CTC
Anupam Enterprises
M/S DK ENTERPRISES
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_326350.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .