Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹9.4 LAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹9.5 L+₹9,126 (0.97%)Admitted-Finance 13 1 THAKUR DAS BANERJEE ROAD KOL 700056 | KOLKATA | KOLKATA | WEST BENGAL | 700056 | L2 | Admitted-Finance | ||
| 3 | L3₹9.5 L+₹9,506 (1.01%)Admitted-Finance 118 DHAMAITALA LANE JAGADDAL KOLKATA SONARPUR 700151 | KOLKATA | SOUTH 24 PARGANAS | WEST BENGAL | 700151 | L3 | Admitted-Finance |
Tender Value
₹9.5 L
EMD Value
₹19,012
Closing Date
21 Sept 2026, 2:00 pmClosed
EE,BNWD
Room No.124 1ST FLOOR PURTA BHAVAN D.F. BLOCK SECTOR I SALT LAKE KOLKATA 700 091.
Providing floor mounted AC machine room beside the Cafeteria, 4th Floor, Institute Block at National University of Juridical Science, Salt Lake, Kolkata, during the year 2026-2027.
2026_WBPWD_5023604_1
WBPWD/EE/BNWD/NIT08e/2026-27
Open Tender
CIVIL WORKS
Percentage
30 days
Salt Lake
Please refer Tender documents.
5 documents required · 5 mandatory
₹19,012
Yes
30 Sept 2026
10 Sept 2026
23 Sept 2026
10 Sept 2026
21 Sept 2026
11 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing brick work manually/ by mechanical means includingstacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. | 7.21 | Cu.M | 2,060.2 | ₹14,849.92 |
| 2 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer -in - charge.
Nominal concrete 1:3:6 or richer mix (including equivalent design mix) | 4.13 | Cu.M | 2,434.25 | ₹10,053.45 |
| 3 | Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. | 1.46 | Cu.M | 3,551.25 | ₹5,185.18 |
| 4 | Centering and shuttering including strutting, propping etc. and removal of form for Columns, Pillars, Piers, Abutments, Posts and Struts Column
4th floor | 5.4 | Sq.M | 961.3 | ₹5,191.02 |
| 4.01 | Beam | 9.84 | Sq.M | 736.4 | ₹7,246.18 |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
1:1½:3 (1 Cement: 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
4th floor | 6.27 | Cu.M | 8,340.85 | ₹52,297.13 |
| 6 | Brick work with common burnt clay selected F.P.S. (non modular) bricks of class designation 7.5 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand)
Above plinth level upto floor V level | 2.81 | Cu.M | 9,439.75 | ₹26,525.7 |
| 7 | Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc. complete.
40 mm thick with 20 mm nominal size stone aggregate | 41.9 | Sq.M | 614.2 | ₹25,734.98 |
| 8 | Providing and fixing double scaffolding system (cup lock type) on the exterior side, up to seven story height made with 40 mm dia M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing
it there after. The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required locations with essential safety features for the workmen etc. complete as per directions and approval of Engineer-in-charge. The elevational area of the scaffolding shall be measured for payment purpose. The payment will be made once irrespective of duration of scaffolding.
Note: - This item to be used for maintenance work judicially, necessary
deduction for scaffolding in the existing item to be done. | 159.08 | Sq.M | 338.25 | ₹53,808.81 |
| 9 | 12 mm cement plaster of mix :
1:6 (1 cement: 6 coarse sand)
Ground Floor | 44.25 | Sq.M | 343.65 | ₹15,206.51 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.87 MB
BOQ_5107760.xls
BOQ • 0.30 MB
Form_2911.pdf
Tender Documents • 0.54 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .