| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.8 CrAccepted-Finance AT GUALIGAN PO TARASA PS RAJKANIKA DIST BHADRAK PIN 754220 | GUALIGAN | BHADRAK | ODISHA | 754220 | ₹1.8 Cr | L1 | Accepted-Finance Winner through opening of the Financial Bid (Cover-II) |
| 2 | L2₹1.8 Cr+₹4.3 L (2.39%)Rejected-Finance | ₹1.8 Cr+₹4.3 L (2.39%) | L2 | Rejected-Finance Loss through opening of the Financial Bid (Cover-II) |
| 3 | L3₹1.8 Cr+₹4.5 L (2.55%)Rejected-Finance AT BARIMAL PO HATIBARI PS SUKINDA DIST JAJPUR PIN 755018 | JAJAPUR | ODISHA | 755018 | ₹1.8 Cr+₹4.5 L (2.55%) | L3 | Rejected-Finance Loss through opening of the Financial Bid (Cover-II) |
| 4 | Rejected-Technical | - | - | Rejected-Technical As per DTCN |
Tender Value
₹2.2 Cr
EMD Value
₹2.2 L
Closing Date
30 Mar 2026, 5:00 pmClosed
CCE, Eastern (R and B) Circle, Balasore
O/o CCE, Eastern (R and B) Circle, Balasore
Building
2026_EICCL_127118_8
CCEEC-20/2025-26
National Competitive Bid
Civil Works - Buildings
Percentage
270 days
Bhadrak
Please refer Tender documents.
4 documents required · 4 mandatory
₹10,000
₹2.2 L
Yes
3 Aug 2026
11 Mar 2026
31 Mar 2026
11 Mar 2026
30 Mar 2026
11 Mar 2026
11 Mar 2026 - 25 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | CIVIL PORTION WORK:-Earth work in excavation in all kinds of soil within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge | 396.45 | cum | 276.89 | ₹1,09,773.04 |
| 2Sand filling in foundation and plinth including cost of all material, labour, conveyance, loading and unloading, taxes, royalties, sundries, tools and plants etc. complete as per the driection of the Engineer in Charge. (linear measurement will be taken and quantity will be calculated on standard weight for all heights). | |||||
| 2.01 | i)Ground | 343.73 | cum | 1,615.37 | ₹5,55,251.13 |
| 2.02 | ii)Compound Wall | 19.54 | cum | 1,615.37 | ₹31,564.33 |
| 3Filling area with excavated earth materials including labour, conveyance, loading and unloading, taxes, royalties, sundries, tools and plants etc. complete as per the driection of the Engineer in Charge. | |||||
| 3.01 | i)Ground | 153.83 | cum | 153.83 | ₹23,663.67 |
| 3.02 | ii)Compound Wall | 45.6 | cum | 153.83 | ₹7,014.65 |
| 4Conveyance of excavated earth materials by mechanical means including 5km lead complete including all labour, materials & royality etc. complete as per direction of EIC. | |||||
| 4.01 | i)Ground | 278.77 | cum | 278.77 | ₹77,712.71 |
| 5Providing & laying plain cement concrete (1:3:6) using 4cm size metal etc. complete including all labour, materials & royality etc. complete as per direction of EIC. | |||||
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.42 MB
dtcn8.pdf
Tender Documents • 1.93 MB
BOQ_584688.xls
BOQ • 0.53 MB
2ndcorrigendum.pdf
PDF • 0.48 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .