THE EXECUTIVE ENGINEER MALDA DIVISION, P.H. ENGINE
DOULATPUR PHE COMPLEX, MALIHA MALDA-732102
Additional laying of Pipe line for improvement of FHTC functionality by different dia UPVC pipe and Providing FHTC for DUBA KHOSKAN piped Water Supply Scheme at Gazole Block in the District of Malda under Malda Division, P.H.E.Dte. (3rd Call)
2026_PHED_5021812_3
WBPHED/EE/MD/NIeT_15 (3rd Call) of 2026-2027
Open Tender
CIVIL WORKS
Item Rate
30 days
DOULATPUR PHE COMPLEX, MALIHA MALDA-732102
Please refer Tender documents.
5 documents required · 5 mandatory
₹1.3 L
Yes
9 Oct 2026
3 Sept 2026
12 Oct 2026
3 Sept 2026
9 Oct 2026
3 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Supplying, laying, fiting, fixing and jointing of UPVC pipes conforming to IS:4985-2000 with latest revision and amendments, if any, including labour charges for earth work in excavation in any kind of soil including mixed soil with boulder ,road sub-grade and its flanks but excluding moorum and laterite or sand stonehard arock including cutting of brick pavement without damaging the existing telephone/electrical cable line etc.(in case of damage of any type of cable line during excavation, necessary damaged charges as applicable by the respaective authority will be borne by the agency in his own cost. Loading, unloading, carrying of pipes, specials, valves from the local store to work site and lowering laying of pipes specials valves carefully in trenches maintaining proper levels and alignment ,jointing the pipe , specials and valves including supplying of good quality/approved brand solvent cement (as per IS:14182-1994 including cost of all fabricated PVC fitting i.e. tees,bend, reducers, adopter etc.as per IS:101-1988 and making flange joints including supplying required quantity of nuts, bolts and rubber insertion (CIDF sluice valves will be supplied by the department free of cost) as required at site by adopting suitable method so as to facilate the maintenance of pipe line locally as per conventional method including back filling the trenches with good earth obtained from excavation of trenches including consolidation with watering in layer not exceeding 150mm thk. with maintaining an average depth of . [Ref. PHED Schedule Page No : L-3, Item No: 2/ii]
N.B. i) Manufacturer’s test certificate for UPVC pipe & specials to be produced before laying of pipe line.
ii) 3rd party inspection of UPVC pipe & specials to be done by CEPET or as per direction of EIC as per approved vender list.
iii)No part payment at any stage on account of supply of materials shall be entertained.
iv)Payment will be made on actual consumption of materials. | - | - | - | - |
| 2 | N.B. i) Manufacturer’s test certificate for UPVC pipe & specials to be produced before laying of pipe line. ii) 3rd party inspection of UPVC pipe & specials to be done by CEPET or (India) SGS/NTH Kolkata or as per direction of EIC as per approved vender list. iii) No part payment at any stage on account of supply of materials shall be entertained. iv) Payment will be made on actual consumption of materials. v) UPVC pipes for the works to be supplied as per approved vendor list and as per direction & satisfaction of EIC. No pipes will be allowed beyond recommendated vendor list.
vi) Submission of drawing of pipe line with statement of materials consumed between node to node points against each R.A. & final bill.if so. vii) Any deviation from required clear cover of 1.10mtr.due to site adverse condition, prior permission is to be obtained from EIC and payment for such work will be made on prorate basis over the rate of entire item. viii) All pipe connection shall be completed in all respect and as per directionof EIC. Decision of EIC in this respect is final & binding. In case of any deviation/or any left out pipe connections an amount of Rs.10,000.00 for each pipe connection will be realized/recovered from the bill.
v)UPVC pipes for the works to be supplied as per approved vendor list and as per direction & satisfaction of EIC. No pipes will be allowed beyond recommendated vendor list.
vi)Submission of completion drawing of pipe line showing all specials,valves, etc with final bill is mandatory.(Cost of drawing will be paid seperately).
vii) Any deviation from required clear cover of 1.10mtr.due to site adverse condition, prior permission is to be obtained from EIC and deduction for such work will be made accordingly.
viii)All pipe connection shall be completed in all respect and as per directionof EIC. Decision of EIC in this respect is final & binding. In case of any deviation/or any left out pipe connections an amount of Rs.10,000.00 for each pipe connection will be realized/recovered from the bill. | - | - | - | - |
| 3 | (i) Laying of pipe line including cost of pipe & fittings /fitting but excluding cost of valves. | - | - | - | - |
| 4 | a) 90 mm O.D Dia | 8,805 | /Mtr. | 342 | ₹30,11,310 |
| 5 | b) 110 mm O.D Dia | 664 | /Mtr. | 471 | ₹3,12,744 |
| 6 | c) 125 mm O.D Dia | 175 | /Mtr. | 643 | ₹1,12,525 |
| 7 | d) 140 mm O.D Dia | 112 | /Mtr. | 785 | ₹87,920 |
| 8 | e) 160 mm O.D Dia | 135 | /Mtr. | 974 | ₹1,31,490 |
| 9 | f) 180 mm O.D Dia | 145 | /Mtr. | 1,544 | ₹2,23,880 |
| 10 | Construction of different dia Sluice valve /Air valve /Washout chamber in different sizes for village road where light traffic run and for main road where heavy traffic run as deptt.approved drawing with 25cm thick brick work (1:6) over cement concrete (4:2:1) over a single B/F soling over150mm.thick sand filling in foundation including earth work in excavation and disposal of excess earth from work site with RCC (1:1.5:3) cover slab 100mm / 150mm thick slab on top of chamber with 1% reinforcement in RCC cover slab with necessary opening for operation of valve all complete including cost of labour & materials as per Departmental Dwg. [Reinforcement type:- Other manufactuerers not specified] (PHE Schedule of Rate Civil Work P-L 21, Item-14 ) | - | - | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.76 MB
Tendernotice_2.pdf
PDF • 1.08 MB
Tendernotice_3.pdf
PDF • 0.51 MB
Tendernotice_4.pdf
PDF • 7.23 MB
BOQ_5101186.xls
BOQ • 0.39 MB
Corrigendum-Iniet15.pdf
PDF • 0.49 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .