Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.7 CrAdmitted-Finance | ₹2.7 Cr | L1 | Admitted-Finance |
| 2 | L2₹2.7 Cr+₹2.2 L (0.82%)Admitted-Finance DISTRICT MAGISTRATE HARIDWAR UTTARAKHAND | HARIDWAR | UTTARAKHAND | 247656 | ₹2.7 Cr+₹2.2 L (0.82%) | L2 | Admitted-Finance |
| 3 | L3₹2.8 Cr+₹4.0 L (1.48%)Admitted-Finance 250 SARTHI VIHAR DEHRADUN | DEHRADUN | DEHRADUN | UTTARAKHAND | ₹2.8 Cr+₹4.0 L (1.48%) | L3 | Admitted-Finance |
| 4 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Others-Bidder did not submitted required documents in hard copy. |
| 5 | Not Admitted-Fee/PreQual/Technical 5 A WEST REST CAMP DEHRADUN | - | - | Not Admitted-Fee/PreQual/Technical Others-Bidder did not submitted required documents in hard copy. |
| Sl No | Description | Qty | Unit | Devbhoomi construction L2 | M/S HimalayanConstruction L3 | MS HILLSTONE INFRA L1 |
|---|---|---|---|---|---|---|
| 1.00 | Excavation for Structures
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of ides and bottom and backfilling in trenches with excavated suitable material | 1,815.61 | Cum | 370 ₹6,71,775.7 | 389 ₹7,06,272.29 | 337 ₹6,11,860.57 Lowest |
| 2.00 | Providing concrete for plain/ reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 PCC Grade M 15 | 534.36 | Cum | 5,650 ₹30,19,134 | 5,678 ₹30,34,096.08 | 5,627 ₹30,06,843.72 Lowest |
| 3.00 | Reinforced cement concrete in substructure complete as per drawings and technical bspecification Clauses 802, 804, 805, 806, 807, 1202 ans 1204 R.C.C. grade M 25 | 776.42 | Cum | 7,634 ₹59,27,190.28 | 7,665 ₹59,51,259.3 | 7,607 ₹59,06,226.94 Lowest |
| 4.00 | Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 (The reinforcement steel shall be procured from original (primary) steel producers as per clause no. 2011.3.1 of MORD specifications (First revision'2014) and IS 1786:2008 clause no. 1.6) | 85.23 | MT | 64,650 ₹55,10,119.5 | 64,981 ₹55,38,330.63 | 64,647 ₹55,09,863.81 Lowest |
| 5.00 | Plain cement concrete in open foundation complete as per drawing and technical specifications PCC Grade M 20 Using Concrete Mixer | 1,782.34 | Cum | 6,341 ₹1,13,01,817.94 | 6,373 ₹1,13,58,852.82 | 6,307 ₹1,12,41,218.38 Lowest |
| 6.00 | Hand Packed stone filling in back of wallls including cost of all materials, royality, T&P etc. complete as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications) | 656.53 | Cum | 1,000 ₹6,56,530 | 1,024 ₹6,72,286.72 | 937 ₹6,15,168.61 Lowest |
| 7.00 | Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7 | 2,094.42 | Rmt | 150 ₹3,14,163 | 152 ₹3,18,351.84 | 137 ₹2,86,935.54 Lowest |
Tender Value
₹3.3 Cr
EMD Value
₹6.5 L
Closing Date
25 Feb 2025, 3:00 pmClosed
Superintending Engineer, 9th Circle, PWD, Dehradun
Superintending Engineer, 9th Circle, PWD, Dehradun
Protection works of the road from Raipur to Iron Bridge via Khairi Mansingh under the State Disaster Mitigation Fund (SDMF) under Raipur constituency of Dehradun district.
2025_pwd_80163_1
813/1C-9/2025, Dated 04/02/2025
Open Tender
Civil Works - Roads
Item Rate
270 days
Khairi Mansingh Road
Please refer Tender documents.
3 documents required · 3 mandatory
₹5,900
Executive Engineer, Temp. Div., PWD, Rishikesh
₹6.5 L
Superintending Engineer, 9th Circle, PWD, Dehradun
4 Apr 2025
10 Feb 2025
25 Feb 2025
10 Feb 2025
25 Feb 2025
17 Feb 2025
17 Feb 2025
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation for Structures
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of ides and bottom and backfilling in trenches with excavated suitable material | 1,815.61 | Cum | - | - |
| 2 | Providing concrete for plain/ reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 PCC Grade M 15 | 534.36 | Cum | - | - |
| 3 | Reinforced cement concrete in substructure complete as per drawings and technical bspecification Clauses 802, 804, 805, 806, 807, 1202 ans 1204 R.C.C. grade M 25 | 776.42 | Cum | - | - |
| 4 | Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 (The reinforcement steel shall be procured from original (primary) steel producers as per clause no. 2011.3.1 of MORD specifications (First revision'2014) and IS 1786:2008 clause no. 1.6) | 85.23 | MT | - | - |
| 5 | Plain cement concrete in open foundation complete as per drawing and technical specifications PCC Grade M 20 Using Concrete Mixer | 1,782.34 | Cum | - | - |
| 6 | Hand Packed stone filling in back of wallls including cost of all materials, royality, T&P etc. complete as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications) | 656.53 | Cum | - | - |
| 7 | Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7 | 2,094.42 | Rmt | - | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.99 MB
BOQ_95583.xls
BOQ • 0.39 MB
SBD.pdf
Tender Documents • 2.14 MB
BOQ.xls
BOQ • 0.39 MB
Tenderdocument.pdf
Tender Documents • 2.14 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .