| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹80.1 LAccepted-AOC | ₹80.1 L | L1 | Accepted-AOC L1 bidder |
| 2 | L2₹81.7 LRejected-Finance MAYURAM PAYANCHERY IRITTY KANNUR PIN 670001 | IRITTY | KANNUR | KERALA | 670001 | ₹81.7 L | L2 | Rejected-Finance L2 bidder |
| 3 | L3₹82.9 LRejected-Finance | ₹82.9 L | L3 | Rejected-Finance L3 bidder |
| 4 | L4₹85.5 LRejected-Finance KUPPOL PERINGOME PO 670353 | PERINGOME | KANNUR | KERALA | 670353 | ₹85.5 L | L4 | Rejected-Finance L4 bidder |
| Sl No | Description | Qty | Unit | MOHANAN P L4 | PRAVAH INFRATECH LLP L2 | BIJU E P L1 | L&M INFRA BUILDERS L3 |
|---|---|---|---|---|---|---|---|
| 1.00Ground Development Work - Construction of Mud Football Court | |||||||
| 1.01 | OD140779/2025-2026Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 30 cm depth, dressing to camber and consolidating with road roller including making good the undulations etc. and re-rolling the sub grade and disposal of surplus earth including all lifts and leads, hire charges of machineries, labour charges etc complete as per the direction of engineer in charge.All kinds of soil.(Based on CPWD-2.6.1, 16.1,30.2.8 & MoRTH-3.6 & 3.16) | 5,900 | sqm | 98 ₹5.8 L | 95.93 ₹5.7 L | 94 ₹5.5 L | 200 ₹11.8 L |
| 1.02 | OD60158/2025-2026Supplying and stacking sieved red earth at site for measurement including royalty and carriage upto 5 k.m. lead,all labour charges for stacking, loading and unloading etc complete.(Based on CPWD 30.2.2 & 30.2.4.3) | 944 | cum | 887 ₹8.4 L | 818.62 ₹7.7 L | 802.35 ₹7.6 L | 700 ₹6.6 L |
| 1.03 | OD140774/2025-2026Supplying and stacking sieved sand at site for measurement including cost of sand, carriage upto 5 k.m. lead,all labour charges for stacking,loading and unloading etc complete.(Based on CPWD 30.2.2 & 30.2.4.3). | 236 | cum | 2,622 ₹6.2 L | 2,532.52 ₹6.0 L | 2,482.17 ₹5.9 L | 2,400 ₹5.7 L |
| 1.04 | OD140775/2025-2026Mixing departmentally supplied earth and sand in the required proportion specified or directed by the officer - in- charge including all cost of labour charges, hire charges of machineries etc. complete.(Based on CPWD 30.2.9) | 1,180 | cum | 46.5 ₹54,870 | 45.34 ₹53,501.20 | 44.44 ₹52,439.20 | 70 ₹82,600 |
| 1.05 | OD140776/2025-2026Spreading of departmentally supplied earth and sand in the required thickness as per direction of officer - in- charge including all cost of labour charges, hire charges of machineries etc. complete.(cost of earth and sand to be paid separately).(Based on CPWD 30.2.8) | 1,180 | cum | 66.96 ₹79,012.80 | 65.03 ₹76,735.40 | 63.73 ₹75,201.40 | 75 ₹88,500 |
| 1.06 | OD60163/2025-2026Consolidation of subgrade with power road roller of 8 to 12 tonne capacity with road roller including making good the undulations etc.including all cost of labour charges, hire charges ,fuel,oil etc. complete.(Based on CPWD 16.1) | 5,900 | sqm | 3.07 ₹18,107.10 | 2.96 ₹17,464 | 2.9 ₹17,110 | 4 ₹23,600 |
| 1.07 | OD140778/2025-2026Supply and installing Movable type premium quality outdoor Football Goal Post of size 24x8 feet made with heavy duty MS Pipe of size 4" dia for main frame with supports Back frame with PU finishing including all fittings such as premium quality Nylon net, Hooks, solid wheels etc. for elevens court. | 1 | pair | 41,803 ₹41,803 | 40,358.36 ₹40,358.36 | 39,556 ₹39,556 | 40,000 ₹40,000 |
| 2.00Retaining Wall cum Step Gallery | |||||||
| 2.01 | 2.7.1Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.Ordinary rock | 190 | cum | 632 ₹1.2 L | 433.97 ₹82,454.30 | 425.34 ₹80,814.60 | 325 ₹61,750 |
Tender Value
₹91.0 L
EMD Value
₹50,000
Closing Date
27 Oct 2025, 3:00 pmClosed
The Chief Engineer, Sports Kerala Foundation
Jimmy George Indoor Stadium, Vellayambalam, Thiruvananthapuram
Ground Development work - Construction of Mud Football Court, Retaining wall cum Step Gallery, Fencing and Drain
2025_SKF_811961_1
243/SKF/CE/2025-26
Open Tender
Civil Works - Others
180 days
Kannur
Please refer tender document
6 documents required · 6 mandatory
₹2,950
₹50,000
28 Feb 2026
18 Oct 2025
29 Oct 2025
18 Oct 2025
27 Oct 2025
18 Oct 2025
Amount
Ground Development Work - Construction of Mud Football Court
OD140779/2025-2026Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 30 cm depth, dressing to camber and consolidating with road roller including making good the undulations etc. and re-rolling the sub grade and disposal of surplus earth including all lifts and leads, hire charges of machineries, labour charges etc complete as per the direction of engineer in charge.All kinds of soil.(Based on CPWD-2.6.1, 16.1,30.2.8 & MoRTH-3.6 & 3.16)
OD60158/2025-2026Supplying and stacking sieved red earth at site for measurement including royalty and carriage upto 5 k.m. lead,all labour charges for stacking, loading and unloading etc complete.(Based on CPWD 30.2.2 & 30.2.4.3)
OD140774/2025-2026Supplying and stacking sieved sand at site for measurement including cost of sand, carriage upto 5 k.m. lead,all labour charges for stacking,loading and unloading etc complete.(Based on CPWD 30.2.2 & 30.2.4.3).
OD140775/2025-2026Mixing departmentally supplied earth and sand in the required proportion specified or directed by the officer - in- charge including all cost of labour charges, hire charges of machineries etc. complete.(Based on CPWD 30.2.9)
OD140776/2025-2026Spreading of departmentally supplied earth and sand in the required thickness as per direction of officer - in- charge including all cost of labour charges, hire charges of machineries etc. complete.(cost of earth and sand to be paid separately).(Based on CPWD 30.2.8)
OD60163/2025-2026Consolidation of subgrade with power road roller of 8 to 12 tonne capacity with road roller including making good the undulations etc.including all cost of labour charges, hire charges ,fuel,oil etc. complete.(Based on CPWD 16.1)
OD140778/2025-2026Supply and installing Movable type premium quality outdoor Football Goal Post of size 24x8 feet made with heavy duty MS Pipe of size 4" dia for main frame with supports Back frame with PU finishing including all fittings such as premium quality Nylon net, Hooks, solid wheels etc. for elevens court.
Retaining Wall cum Step Gallery
2.7.1Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.Ordinary rock
4.1.8Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources)
60.7.1DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
7.1.1Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
5.1.2Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources)
5.9.5Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.22.6Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
13.7.112 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1 cement : 3 fine sand)
13.48.1Finishing with Deluxe Multi surface paint system for interiors and exteriors using primer as per manufacturers specifications:Two or more coats applied on walls @ 1.25 ltr/10 sqm over and including one coat of special primer applied @ 0.75 ltr /10 sqm
Fencing and Drain
2.9.1Excavation work by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m.Ordinary rock
4.1.3Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
4.3.1Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
4.1.8Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources)
5.1.2Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources)
5.9.1Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.9.2Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
5.22.6Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
OD140782/2025-2026Steel work for fencing with G I pipes including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including all cost of materials, labour charges, hire charges of machineries, charges for welding and bolted with special shaped washers etc. complete.(Rate based on CPWD 50.10.2)
16.70.1Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50 mm including strengthening with 2 mm dia wire or nuts , bolts and washers as required complete as per the direction of Engineer-in- charge.Made of G.I. wire of dia 4 mm
OD140791/2025-2026Supply and Installation of approved quality 2mm thick UV Stabilized Nylon net of Mesh size not greater than 50mm in existing GI poles including all cost of materials, conveyance, labour charges, etc. as per the direction of Engineer in charge.(Rate based on CPWD 26.81)
13.61.1Painting with synthetic enamel paint of approved brand and manufacture to give an even shade:Two or more coats on new work
OD60233/2025-2026Lifting, conveying and fixing the newly casted RCC covering slabs of any thickness on top of drain in position including all labour charges and miscellaneous expenses etc complete (Based on MoRTH 55.25 )
PRAVAH INFRATECH LLP (BID ID -2411776)
L&M INFRA BUILDERS (BID ID -2411780)
MOHANAN P (BID ID -2411455)
Bidder Name
MOHANAN P
BIJU E P
L&M INFRA BUILDERS
PRAVAH INFRATECH LLP
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1356401.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.59 MB
Tenderdocmathamangalam.pdf
Tender Documents • 1.37 MB
BOQ_1356401.xls
BOQ • 0.29 MB
DWG.pdf
Other Document • 0.81 MB
Download all tender documents and submit your bid