| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹21.9 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹24.1 L+₹2.2 L (10.2%)Rejected-AOC | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | GINSON GT L2 | SANTHOSHKUMAR K K L1 |
|---|---|---|---|---|---|
| 1.00APPENDIX A - Reactive Maintenanace | |||||
| 1.00 | 2.2:Clearing grass and removal of rubbish up to a distance of 50 metres outside the periphery of the area | 7.25 | Hectare | 61,382.7 ₹4,45,024.58 | 55,820 ₹4,04,695 Lowest |
| 1.00 | 3.24.B:Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil by Manual Means to specified lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in embankment within a lead of 50 metres (average lead 25 metres) | 940 | metre | 245.52 ₹2,30,788.8 | 220 ₹2,06,800 Lowest |
| 1.00 | 12.8.1.C.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications RCC Grade M20 - Using Concrete Mixer | 1.51 | cum | 9,616.59 ₹14,540.28 | 8,750 ₹13,230 Lowest |
| 1.00 | 12.40:Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications | 0.1 | MT | 1,04,990.19 ₹10,289.04 | 95,600 ₹9,368.8 Lowest |
| 1.00 | 3.6:Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m | 153 | cum | 51.91 ₹7,942.23 | 47 ₹7,191 Lowest |
| 1.01 | OD281904/2024-2025:Supplying and spreading quarry rubbish in the eroded portions of BT
edge, deep pot holes and low level berms as per the direction of the departmental officers at site
including cost of materials, conveyance and labour charges for spreading, ramming etc
complete. | 97.5 | cum | 1,235.93 ₹1,20,503.18 | 1,125 ₹1,09,687.5 Lowest |
| 1.01 | 55.4:Supplying and stacking 36mm size hard broken stone in standard heaps for measurement. | 15 | cum | 2,668.2 ₹40,023 | 2,400 ₹36,000 Lowest |
| 1.01 | OD281902/2024-2025:Engaging Coolie for petty works | 80 | each | 1,175.59 ₹94,047.2 | 1,070 ₹85,600 Lowest |
| 1.01 | OD281901/2024-2025:Engaging wood cutter | 75 | each | 1,198.68 ₹89,901 | 1,090 ₹81,750 Lowest |
Tender Value
₹23.1 L
EMD Value
₹50,000
Closing Date
21 Jul 2025, 3:00 pmClosed
EXECUTIVE ENGINEER
EXECUTIVE ENGINEER PWD ROADS DIVISION THRISSUR
GENERAL RM 2025 26 RC2 Phase1 under Wadakkanchery Section in Thrissur District One year Running Maintenance contract for various roads 6 number of roads for a total length of 27.615 km General Civil Work
2025_PWD_775948_1
PWD/RB/5390/2025-2026
Open Tender
Civil Works - Roads
Item Rate
365 days
Thrissur
Please refer Tender documents.
9 documents required · 9 mandatory
₹2,760
Yes
₹50,000
Yes
11 Sept 2025
10 Jul 2025
23 Jul 2025
10 Jul 2025
21 Jul 2025
10 Jul 2025
Amount
APPENDIX A - Reactive Maintenanace
2.2:Clearing grass and removal of rubbish up to a distance of 50 metres outside the periphery of the area
3.24.B:Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil by Manual Means to specified lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in embankment within a lead of 50 metres (average lead 25 metres)
12.8.1.C.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications RCC Grade M20 - Using Concrete Mixer
12.40:Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications
3.6:Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m
OD281904/2024-2025:Supplying and spreading quarry rubbish in the eroded portions of BT edge, deep pot holes and low level berms as per the direction of the departmental officers at site including cost of materials, conveyance and labour charges for spreading, ramming etc complete.
55.4:Supplying and stacking 36mm size hard broken stone in standard heaps for measurement.
OD281902/2024-2025:Engaging Coolie for petty works
OD281901/2024-2025:Engaging wood cutter
OD281907/2024-2025:Lifting the existing precast RCC covering slabs from drain and culvert for removal of silt and placing the same slab on position after completion of clearing work including all labour charges and miscellaneous expenses etc. complete
OD281905/2024-2025:Hire charges of Tipper including operation charges and fuel charges for cleaning and removing dumped stones waste materials etc. as per the direction of departmental officers at site etc. complete
OD281906/2024-2025:Hire charges of Hydraulic excavator including operation charges and fuel charges for clearing and removing waste materials clearing grass etc. along the sides of roads as per the direction of departmental officers at site.
OD282584/2024-2025:Filling up potholes with bituminous ready mix compound (25kg bag) and compacting by ramming to get a compact surface including cost of materials, laying charges, transportation to site, etc. complete. Rate is arrived for a bag of 25Kg
OD28489/2025-2026:Providing and fixing of non retro-reflectorised DLP board manufactured as per IRC:67 made of Type IV microprismatic grade sheeting fixed over aluminium sheeting 2mm thick/aluminium composite material sheeting 4mm thickwith area not exceeding 0.9 sqmwith suitable back supporting frame of MS Angle 40x40x6 and supported on GI pipe pole50mm NB confirming to IS 1239 firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete min size 45x45x60cm, 60cm below ground level including painting all exposed surface with 2 coats of epoxy painting over epoxy primer and as per approved drawing and clause 801 including lettering symbols, etc.
OD28535/2025-2026:Providing and fixing vinyl sticker in existing DLP board including lettering and printing Removal of existing sticker plate from the DLP board by removing the rivet and accessories, transportation from site to factory, Removal of existing sticker from Sticker Plate, installation of new sticker, transporting back to site. installation of new sticker plate to the DLP board using rivets and accessories.
APPENDIX B Premonsoon Work
3.11:Removal of unserviceable soil including excavation, loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per clause 305.
OD28480/2025-2026:Engaging Coolie for petty works
OD28481/2025-2026:Engaging wood cutter for cutting the branches of trees.
OD28487/2025-2026:Hire charges of Tipper including operation charges and fuel charges for cleaning and removing dumped stones waste materials etc. as per the direction of departmental officers at site etc. complete
OD28556/2025-2026:Hire charges of Hydraulic excavator including operation charges and fuel charges for clearing and removing waste materials clearing grass etc. along the sides of roads as per the direction of departmental officers at site.
55.15:Refurbishment of existing signboardsRefurbishment of existing signboards of all size except gantry mounted ones to their original reflectivity & position by removing obstructions like overgrowth vegitation etc ,if any,washing the signboards with water & soap solution to remove all dirt, oil etc. , correcting any dislocations including minor repairs, replacement of lost nut and bolts etc complete.
OD28518/2025-2026:Lifting the existing precast RCC covering slabs from drain and culvert for removal of silt and placing the same slab on position after completion of clearing work including all labour charges and miscellaneous expenses etc. complete
OD28557/2025-2026:Filling up potholes with bituminous ready mix compound (25kg bag) and compacting by ramming to get a compact surface including cost of materials, laying charges, transportation to site, etc. complete. Rate is arrived for a bag of 25Kg
APPENDIX C - Preventive Maintenance
4.12:Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.
10.5.1a:Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm. Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 504, compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - For grading I Material
APPENDIX D - Emergency Work
OD29607/2025-2026:Hire charges of Hydraulic excavator including operation charges and fuel charges for clearing and removing waste materials clearing grass etc. along the sides of roads as per the direction of departmental officers at site.
OD29609/2025-2026:Hire charges of Tipper including operation charges and fuel charges for cleaning and removing dumped stones waste materials etc. as per the direction of departmental officers at site etc. complete
OD29613/2025-2026:Supplying and spreading quarry rubbish in the eroded portions of BT edge, deep pot holes and low level berms as per the direction of the departmental officers at site including cost of materials, conveyance and labour charges for spreading, ramming etc complete.
GINSON GT (BID ID -2255895)
Bidder Name
SANTHOSHKUMAR K K
GINSON GT
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1268363.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .