| 1 | L1₹11.5 LAdmitted-Fee/PreQual/Technical/Finance | ₹11.5 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| Sl No | Description | Qty | Unit | V V ELECTRICALS L1 |
|---|---|---|---|---|
| 1.00Fabrication and replacement of damaged cable trays in Ammonia Complex 2025-26 | ||||
| 1.01 | Fabrication, erection and fixing of cable trays and supporting structures of different dimensions using MS angles, channels, flats etc. of different sizes at various locations of Ammonia Complex. The work includes dismantling the existing damaged cable trays and supporting structures and fixing new trays/ structures by welding/ grouting to steel structures/ pillars/ walls etc. as per the instruction of Engineer in-charge.
MS structural materials, electric power for welding and cutting and lifting/transport facilities such as cranes, forklifts, trailers, etc., subject to availability, shall be provided by FACT free of cost. All other tools, tackles, consumables, manpower, safety equipment and materials required for execution of the work shall be arranged by the contractor.Disposal of dismantled materials and scrap shall be carried out as directed by the Engineer-in-Charge.
The vendor scope shall also include:
1. Surface preparation:
New MS structural materials shall be mechanically cleaned, including manual chipping and wire brushing to remove rust, mill scale, and contaminants, ensuring a clean, dry surface for coating. 2.Primer coating:
Painting two coats (in two different colours) of surface tolerant self priming high build epoxy primer "Protectomastic" of Berger paints or equivalent approved quality of epoxy priming coat with minimum volume of solid of 80% on new steel structural work, after cleaning the surface, at all heights. Supply of paint, labour, scaffolding charges etc. shall be under vendor scope. 3.Finish coating:
Painting two coats (in two different colours) of finished paint with Acrylic Aliphatic Polyurathane coating, "BR PU High Gloss Enamel" of Berger paints or equivalent approved quality of PU finish paint with minimum volume of solid of 52% over steel structure (already applied with two coats of primer) at all heights. Supply of paint,labour,scaffolding charges etc. shall be under vendor scope. | 17,000 | KG | 9,77,500 ₹11,53,450 Lowest |
Tender Value
Refer Docs
EMD Value
₹12,000
Closing Date
5 May 2026, 2:00 pmClosed
AGM P and P
ASSISTANT GENERAL MANAGER PROJECTS AND PLANNING PD ADMINISTRATION
Fabrication and replacement of damaged cable trays in Ammonia Complex2025 26
2026_FACT_905227_1
3017/2026-2027/E33381
Limited
Miscellaneous Works
Item Rate
365 days
UDYOGAMANDAL
5 documents required · 5 mandatory
₹0
₹12,000
Yes
11 May 2026
13 Apr 2026
6 May 2026
13 Apr 2026
5 May 2026
13 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Fabrication and replacement of damaged cable trays in Ammonia Complex 2025-26 | |||||
| 1.01 | Fabrication, erection and fixing of cable trays and supporting structures of different dimensions using MS angles, channels, flats etc. of different sizes at various locations of Ammonia Complex. The work includes dismantling the existing damaged cable trays and supporting structures and fixing new trays/ structures by welding/ grouting to steel structures/ pillars/ walls etc. as per the instruction of Engineer in-charge.
MS structural materials, electric power for welding and cutting and lifting/transport facilities such as cranes, forklifts, trailers, etc., subject to availability, shall be provided by FACT free of cost. All other tools, tackles, consumables, manpower, safety equipment and materials required for execution of the work shall be arranged by the contractor.Disposal of dismantled materials and scrap shall be carried out as directed by the Engineer-in-Charge.
The vendor scope shall also include:
1. Surface preparation:
New MS structural materials shall be mechanically cleaned, including manual chipping and wire brushing to remove rust, mill scale, and contaminants, ensuring a clean, dry surface for coating. 2.Primer coating:
Painting two coats (in two different colours) of surface tolerant self priming high build epoxy primer "Protectomastic" of Berger paints or equivalent approved quality of epoxy priming coat with minimum volume of solid of 80% on new steel structural work, after cleaning the surface, at all heights. Supply of paint, labour, scaffolding charges etc. shall be under vendor scope. 3.Finish coating:
Painting two coats (in two different colours) of finished paint with Acrylic Aliphatic Polyurathane coating, "BR PU High Gloss Enamel" of Berger paints or equivalent approved quality of PU finish paint with minimum volume of solid of 52% over steel structure (already applied with two coats of primer) at all heights. Supply of paint,labour,scaffolding charges etc. shall be under vendor scope. | - | KG | - | - |
stage.html
html • 0.01 MB
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.12 MB
BOQ_951473.xls
BOQ • 0.23 MB
STC33381.pdf
Tender Documents • 13.97 MB
comp33381.pdf
Additional Documents • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].