| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹4.8 CrAccepted-Finance | ₹4.8 Cr | L-1 | Accepted-Finance L-1 |
| 2 | L-2₹5.1 Cr+₹30.9 L (6.44%)Rejected-Finance | ₹5.1 Cr+₹30.9 L (6.44%) | L-2 | Rejected-Finance L-2 |
| 3 | L-3₹5.5 Cr+₹65.9 L (13.7%)Rejected-Finance | ₹5.5 Cr+₹65.9 L (13.7%) | L-3 | Rejected-Finance L-3 |
| 4 | Not Admitted-Fee/PreQual/Technical JAIN SADAN MAHAL ROAD SHIVPURI DISTT SHIVPURI MP | SHIVPURI | SHIVPURI | MADHYA PRADESH | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| 5 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹5.8 Cr
EMD Value
₹11.6 L
Closing Date
12 May 2026, 5:00 pmClosed
General Manager
Main administrative building, Sector-6, Noida
Strengthening of Road (P/L Interlocking tile, RCC Footpath and drain repairing work in Block-C, Phase-II) Noida
2026_NOIDA_1143282_1
04/GM/SM/WC-7/ET/2026-27
Open Tender
Civil Works
Fixed-rate
270 days
NOIDA
Please refer Tender documents.
3 documents required · 3 mandatory
₹8,260
NOIDA
₹11.6 L
24 Jun 2026
28 Apr 2026
13 May 2026
28 Apr 2026
12 May 2026
28 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exccding 30 cm in depth, 1.5m in width or 10 sqm on plan) including disposal of excavated lead upto 50 mtr. & lift upto 1.5Mtr. dispose earth to be leveled & dressed. : All kinds of soil. The Contractor has to detect Different utilities like sewer line, water Supply line, electric cable, telephone cable, gas pipe line etc. using utility detecting machine before start of excavation and shall start excavation only after getting permission of Engineer-in-Charge | 7,692 | Cum | 136 | ₹10,46,112 |
| 2 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.The contractor has to diffrent utilites like sewer line, water supply line, electric cable, telephone cable, gas pipe line etc. using utility detecting machine before start of excavation and shall start excavation only after getting permission of Engineer-in-charge. all kinds of soil. | 1,793 | Cum | 144.95 | ₹2,59,895.35 |
| 3 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) DSR 18/I.No. 15.2.1/P-248 | 493 | Cum | 923.42 | ₹4,55,246.06 |
| 4 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.In cement mortar | 447 | Cum | 779.76 | ₹3,48,552.72 |
| 5 | Dismantling kerb stone (Dismantling kerb stone by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metre) | 1,741 | Rmt. | 10 | ₹17,410 |
| 6 | Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge | 3,772 | Sqm | 50 | ₹1,88,600 |
| 7 | Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured) : From brick work in cement mortar DSR-18/ I.No: 15.8.3 | 55,204.5 | 1000 Nos. | 2,569.38 | ₹14,18,41,338.21 |
| 8 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 100 in foundation and plinth in: Cement mortar 1:4 (1 cement : 4 coarse sand) (Brick available at site & free of cost) | 112 | Cum | 2,262.51 | ₹2,53,401.12 |
| 9 | Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved. . DSR-18/I.No-15.60 | 10,607 | Cum | 120.55 | ₹12,78,673.85 |
| 10 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering- All work up to plinth 1:4:8 ( 1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) | 67 | Cum | 5,746.88 | ₹3,85,040.96 |
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.25 MB
Capability.xls
Additional Documents • 0.04 MB
TD.pdf
Tender Documents • 13.10 MB
BOQ_2135446.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .