| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.4 LAccepted-AOC | ₹8.4 L | L1 | Accepted-AOC AGREEMENT EXECUTED |
| 2 | Rejected-Technical | - | - | Rejected-Technical L3 |
| 3 | Rejected-Technical | - | - | Rejected-Technical L2 |
| Sl No | Description | Qty | Unit | MPM CONSTRUCTIONS L3 | K K MAJEED L1 | NOUSHAD K B L2 |
|---|---|---|---|---|---|---|
| 1.00building | ||||||
| 1.00 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | 27 | cum | 750 ₹20,250 | 359.72 ₹9,712.44 | 363.32 ₹9,809.64 |
| 1.00 | 4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) | 6.63 | cum | 7,000 ₹46,417 | 7,932.89 ₹52,602.99 | 8,012.22 ₹53,129.03 |
| 1.00 | 5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete | 18.56 | sqm | 450 ₹8,352 | 386.16 ₹7,167.13 | 390.02 ₹7,238.77 |
| 1.00 | 5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources) | 9.71 | cum | 11,000 ₹1.1 L | 10,488.77 ₹1.0 L | 10,593.66 ₹1.0 L |
| 1.00 | 5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers | 62.8 | sqm | 700 ₹43,960 | 762.88 ₹47,908.86 | 770.51 ₹48,388.03 |
| 1.01 | 5.9.19:Centering and shuttering including strutting, etc. and removal of form for:Weather shade, Chajjas, corbels etc., including edges | 17.29 | sqm | 750 ₹12,967.50 | 1,021.94 ₹17,669.34 | 1,032.16 ₹17,846.05 |
| 1.01 | 5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform | 54.42 | sqm | 700 ₹38,094 | 961.24 ₹52,310.68 | 970.85 ₹52,833.66 |
| 1.01 | 5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts | 32.4 | sqm | 650 ₹21,060 | 1,008.55 ₹32,677.02 | 1,018.64 ₹33,003.94 |
| 1.01 | 5.2.2:Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 2.92 | cum | 15,000 ₹43,740 | 12,772.18 ₹37,243.68 | 12,899.9 ₹37,616.11 |
Tender Value
₹8.4 L
EMD Value
₹21,073
Closing Date
7 Mar 2026, 3:00 pmClosed
Executive Engineer
O/o the Executive Engineer, LSGD Division, Kakkanad, Ernakulam
refer tender work
2026_LSGD_834052_2
ET181/MLA-ADS/EE/LSGD/25-26
Open Tender
Civil Works - Others
365 days
O/o The Executive Engineer
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,860
Yes
₹21,073
Yes
9 Jun 2026
27 Feb 2026
9 Mar 2026
27 Feb 2026
7 Mar 2026
27 Feb 2026
building
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources)
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources)
5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.9.19:Centering and shuttering including strutting, etc. and removal of form for:Weather shade, Chajjas, corbels etc., including edges
5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts
5.2.2:Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
5.3:Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) derived from natural sources: 3 graded stone aggregate 20 mm nominal size derived from natural sources).
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5.22A.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
50.6.1.8:Solid block masonry using pre cast solid blocks (Factory made) of size 40x20x15cm or nearest available size confirming to IS 2185 part I of 1979 for super structure up to floor two level with thickness 15cm in: CM 1:6 ( 1 cement : 6 coarse sand etc complete
13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
13.16.1:6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)
OD430118/2025-2026:supplying and fixing in place granite name board of slab area less than 0.9 sq.m including engraving and painting letters etc complete as per direction of engineer incharge at site
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1419140.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.06 MB
viewnit.pdf
Tender Documents • 0.04 MB
BOQ_1419140.xls
BOQ • 0.26 MB
Requisitionfore-payment.pdf
Tender Documents • 0.17 MB
viewsbd.pdf
Tender Documents • 1.67 MB
Download all tender documents and submit your bid