Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Tender Value
₹1.3 Cr
EMD Value
₹1.3 L
Closing Date
23 Nov 2026, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
The Chief Officer, Dahod Nagarpalika, Dahod
DEVELOPMENT WORK AT GOVIND NAGAR NAVJIVAN UDYAN GARDEN OF DAHOD NAGARAPLIKA UNDER 15TH FINANCE SCHEME (FIRST INSTALLMENT) UNTIED GRANT.YEAR 2025-26.
361414
UNDER 15TH FINANCE SCHEME (FIRST INSTALLMENT) UNTIED 2025-26.
Open
Civil - All
Works
Dahod
14 documents required · 14 mandatory
₹4,248
The Chief Officer, Dahod Municipality, Dahod
₹1.3 L
30 Oct 2026
30 Oct 2026
30 Oct 2026
23 Nov 2026
30 Oct 2026
120 days
Total Amount Rs.
SBD SECTION-7 BILL OF QUANTITIES-286
Note :2 Rates quoted include clearance of site (prior commencement of work and its close) in all respects
and hold good for work under.
Note : 3 I/ We have read the conditions mentioned in this tender and agree to abide by the same.
Note : 4 In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R.:
PRC-10/2017 Cement Consumption/16/C Date:11/05/2017 as stated in S.O.R. therefore in
R.C.C. items where there is a change as per actual mix design the cost of difference of cement
consumption have been deducted from the rate of original item at the rate of input rate mentioned in
all the tender.
Signature of Contractor President Chief Officer
Dahod Nagarpalika Dahod Nagarpalika
SBD SECTION-7 BILL OF QUANTITIES-287
DAHOD NAGARPALIKA DAHOD
ESTIMATE FOR CONSTRUCTION WORK OF PAVER BLOCK & KERBING AT GOVIND NAGAR GARDEN , AT
Qty. Description Unit Amount
1 55.00 Excavation for foundation in Loose or soft soil 1:5 mt. Depth
Cmt. including sorting out and stacking of useful materials and
depositing of the excavated stuff for all the leads and lift etc.
complete as directed by Engineer-in-charge.
a) 0.00 to 1.50 M. depth 125.86 Cmt.
2 28.00 Providing and laying cement concrete 1:4:8 (1- Cement : 4-
Cmt. coarse sand : 8- hand broken stone aggregates 40 mm
nominal size) and curing complete excluding cost of
formwork in (A) Foundation and Plinth 2679.92 Cmt.
3 273.00 Providing and fixing pre-cast Rubber Dye inter locking
Smt concrete block 60mm thick with grade of concrete M300
pnumatic compressed by mechanically pressed and as per
approved design including 75mm Sand layer for levelling and
filling the joint with sand in proper line and level etc
complete. 702.02 Smt
Add : 18% GST, Charges Rs.
Add : 2% Contingency Charges Rs.
Add : 1% Quality Controll Rs.
SBD SECTION-7 BILL OF QUANTITIES-288
DAHOD NAGARPALIKA DAHOD
NAME OF WORK :- ESTIMATE FOR 3D WALL PAINTING , PLANTATION & C.C.T.V CAMERA AT GOVIND
NAGAR GARDEN, AT DAHOD.
Item Qty. Description Total Unit Amount
1 1250.00 Providing Artistic 3D wall Painting on Godi road Bridge location up
Smt. to 10 Mtr Height 1484.70 Smt.
2 50.00 Providing Loam or Clay soil of approval quality on site.
3 250.00 Laying out Lawn: After excavating soil upto 30 cm depth,
Smt. preparing soil for planting by supplying and mixing pepairing soil
for planting by supplying and mixing Farm Yard Manure at the rate
of 5 cu. m. per 100 Sq. Mt. area, providing and planting suckers of
pure dharo ( doob ) grass roughly at 10 cm x 10 cm distance and
maintaining till well established etc complete ( about 45 days ).
4 42.00 PLANTING TREES AND SHURBS After excavating pit of the size
Nos. cm X 60 cm X 60 cm refilling with the same by providing and
mixing farm yard manure at the rate of 0.06 cum per pit providing
and planting well grown sapling of specified variety and
maintaining till well established (about 45 days) complete. 121.45 Nos.
5 375.00 STREET LIGHT BRACKET - Providing, Supplying & Installation
PER SQ.FT Decorative Bracket With Lighting
Length 2.5 ft PER
6 1.00 DAHUA 2MP IP PTZ CAMERA 25X ZOOM UPTO 100 MTR. AS PER
Job DIRECTED BY EIC. 377437.00 Job
Add : 18% GST Rs.
Add : 2% Contingency Charges Rs.
Add : 1% Quality Controll Rs.
SBD SECTION-7 BILL OF QUANTITIES-289
SBD SECTION-7 BILL OF QUANTITIES-290
DAHOD NAGARPALIKA, DAHOD
NAME OF WORK :- ESTIMATION CONSTRUCTION WORK OF TOILET BLOCK AT GOVIND NAGAR GARDEN , AT
Item Qty. Description Total Unit Amount
1 33.00 Excavation for base footings upto depth 1.5 m. including sorting out
Cmt. and disposing of the excavated material upto 50 m lead (loose or soft
soil) 125.86 Cmt.
2 5.83 Excavation for foundation for depth from 1.5 m to 3.0 m including
Cmt. sorting out and stacking of useful materials and disposing of fthe
excavated stuff upto 50 Meter lead.(A) Loose or soft soil
3 7.50 Filling in foundation and plinth with murrum or selected soil in layers
Cmt. of 20cm thickness including watering, ramming and consolidating etc.
4 21.00 Carring out plinth treatment to post construction /
Smt. existing structure by spraying chemical solution for termite control
treatment including labour and material consistment with I.S.I
specification. Using Chlordene and Chiorpurfiles 20 EC. As Per
6131_paret-II Consentration Weight one percent is recommended i.e
one litre 20 EC chemical emulsion with 19 liter give 1 %
concrentration inclusive of one litre chemical emulsion appication at
the rate of 5 Litre chemical / Sqm of surface is recommended as per
5 8.00 Providing and laying cement concrete 1:3:6 (1- Cement : 3- Coarse
Cmt. sand : 6- Graded brick bat aggregate 40mm normal size) and curing
complete excluding cost of formwork in (A) Foundation and Plinth
6 Providing and laying controlled cement concrete M-250 and curing
complete excluding the cost of formwork and reinforcement of
reinforced concrete work in
a. 5.90 -- do -- for R.C.C. Column Footing 4744.98 Cmt.
b. 1.60 -- do -- for R.C.C. Column Up to pl 4744.98 Cmt.
c. 1.70 -- do -- for R.C.C. Column Super Structure 9263.72 Cmt.
SBD SECTION-7 BILL OF QUANTITIES-290
d 2.30 -- do -- for Ground Beam 7008.39 Cmt.
e 0.50 -- do -- for Coping 6375.12 Cmt.
f 0.70 -- do -- for Plinth Beam 7008.39 Cmt.
g 1.00 -- do -- for R.C.C. Lintel 8037.58 Cmt.
h 0.50 -- do -- for R.C.C. Chhajja 8037.58 Cmt.
i 2.00 -- do -- for R.C.C. Beam 6864.97 Cmt.
j 4.00 -- do -- for R.C.C. Slab 7053.84 Cmt.
2660.00 Providing and supplying TMT Fe-500 bar steel reinforcment for R.C.C
Kgs. work including bending, binding and placing in position etc. complete
8 2.50 Brick work using common burnt building bricks having crushing
Cmt. strngth not less than 35 Kg./cm2 in C.M. (1:6) (1 Cement, 6 fine sand)
racking out joints curring etc. complete directed by Engineer-in-
charge. 3853.23 Cmt.
9 13.00 Brick work using common burnt building bricks having crushing
Cmt. strngth not less than 35 Kg./cm2 in super structure for Ground Floor
in C.M. (1:6) (1 Cement, 6 fine sand) racking out joints curring etc.
complete directed by Engineer-in-charge. 4141.66 Cmt.
10 17.10 Providing, laying and constructing half brick masonry work with
Smt. conventional building bricks having crushing strength not less that
Kg./Cm2 for super structure for G.F. in cement mortar (1:4) (1
Cement, 4 fine sand) including ranking out joints, curing scaffolding
11 2.20 Providing and fixing glazed louverd glass windows and ventilators
Smt. with teakwood frame 10cm x 7cm size including the cost of oil
painting to wood work etc. complete.
SBD SECTION-7 BILL OF QUANTITIES-291
12 5.10 Provoding and fixing flush door shutters, solid core construction with
Smt. frame of first class hardwood with cross board and face veneer or
plywood face panels, including anodised alluminium butt hinges with
necessary screws. (B) Non-decorative type and block board core
anodised alluminium butt hinges in flush door shutters (2) 35 mm
thick. 1829.74 Smt.
13 24.70 Providing and fixing FRP frame size 100x50 mm and 28mm thick FRP
Smt. depress panel shutter having extra reinforcement on sides & edges in
Gel coat finish. The core of the shutter & frame is to be filed up with
injected fire retardant grade polyurethene foam done in situ alongwith
embedded wooden pieces for stiffening & also taking hinges &
fintures. The whole FRP frame & shutter is to be water proof weather
proof, termite proof & resistance to mild acid/alkali. Rates are to be
inclusive of S.S hinges with necessary screws & alluminium fixtures &
fastenings & fastener sleeve.
14 116.80 Providing 15mm thick cement plaster in single coat on Rough
Smt. (Similar)side of single or half brick walls for interior plastering upto
floor two level and finished even and smooth in (i) Cement mortar 1:3
(1-cement :4-sand) finishing with a floating coat of neat cement slurry.
15 30.90 Providing 10mm thick cement plaster in single coat on brick/concrete
Smt. walls for interior plastering upto floor two level and finished even and
smooth in (ii) Cement mortar 1:4 (1-cement :4-sand) finishing with a
floating coat of neat cement slurry.
16 73.10 Providing and Laying 20 mm thick sand face cement plaster on Walls
Smt. upto height of 10 mts. Above ground level consisting of 12mm thicjk
backing coat of C.M 1:3 (1 Cement, 3 Sand ) and 8 mm thick finishing
coat of C.M 1:1 (1 Cement, 1 Sand) etc. complete.
17 148.00 Applying two coats of putty & two coats of primer of approved brand
Smt. and manufacture on new wall surface to give an even shade including
throughly brushing the surface free from mortar dropping and other
foreign matter and sand papered smooth.
18 148.00 Distempering (Three Coat) with oil bound washable distemper of
Smt. approved brand and manufacture and of required shade on wall
surfaces to give and even shade over and including a primer coat
with alkali resistance primer of approved brand after throughly
brushing the surface to give and even shade free from foreign matter
and also including preparing the surface even and smooth.
SBD SECTION-7 BILL OF QUANTITIES-292
19 73.50 Finishing wall with Weather Proof Acrylic Emulsion Exterior Paint on
Smt. wall surface (two coat) to give and even shade and of approved
brand and manufacture including throughly brooming and brushing
the surface to remove all dirts, and remians of loose powdered
material. 62.43 Smt.
20 18.90 Providing and laying white glazed tiles 6 mm thick in flooring, treads
Smt. of steps and landing laid on bed of 12 mm thick cement mortar 1:3 (1
Cement : 3 Coarse Sand) finished with flush pointing in white cement.
21 54.60 Providing and laying white glazed tiles 6 mm thick in skirting risers of
Smt. steps and dado on 10 mm cement plaster 1:3 (1 Cement : 3 Coarse
Sand) and pointing in white cement jointed with white cement slurry.
22 3.30 Providing and laying polished kota stone slab 25mm thick in risers of
Smt steps, dado and pillars laid on 10 mm thick cement mortar 1:3 (1
Cement, 3 Coarse Sand) and jointed with grey cement slurry including
rubbing and polishing etc. complete.
23 26.50 Providing and laying broken chine mosaic flooring for terrace
Smt. using 12 mm to 20 mm broken pieces of glazed tiles to be laid over
cement mortar 1:3 to plain or slope and to be tempered to bring
mortar creme out upto surface using white cement including
rounding off junctions and extending them upto 15 cm along the
wall,clearing with water and oxalic acid etc. as directed.
24 14.80 Providing and fixing to wall ceiling and floor 10.0 Kg. F/Cm2working
Rmt. pressure poluthene pipes of the following outside Dia.Low densidy,
complete with special falnge compression typefittings, wall clipsetc.
including making good the wall ceiling andfloor. (110mm)
25 2000.00 Providing erecting and fixing double coated ISI water tank of required
Ltr. capacity each with all necessary fitting sand connection etc. complete
on terrace 3.95 Ltr.
26 2.00 Providing and fixing wash down water closet (Indian Type W.C. Pan)
Each size 580mm with Viterous China 100mm size integral P or S trap
including jointing the trap with soil pipe in cement mortar 1:1 (
cement : 1 fine sand). Rates including Providing and fixing in cement
mortar 1:3 (1 cement : 3 fine sand) a pair of white viterous china
250mm x 130mm x 30mm footrest to long pattern squatting pan water
closet and 25mm dia chromium plates brass half turn flush cock of
approved quality etc. complete as directed.
SBD SECTION-7 BILL OF QUANTITIES-293
27 2.00 Providing and fixing wash down water closet (European type W.C.
Each Pan) with integral P or S trap including jointing the trap with soil pipe
in cement mortar 1:1 ( 1 cement : 1 fine sand). Rates including
providing and fixing plastic seat cover with C.P. brass hinges and
rubber buffers, Jet spray heavy duty with S.S. braided hose 60 cm
long and 25mm dia chromium plates brass half turn flush cock of
approved quality etc. complete as directed. 2220.99 Each
28 4.00 Providing and fixing 430mm x 260mm x 350mm size white earthen
Each ware flat back or corner type urinal of approved quality including.
15mm Dia Stop Tap and Necessary Connections the urinal with
waste pipe etc. complete. 1281.69 Each
29 4.00 Providing and fixing white viterous china flat back wash basin of
Each 550mm x 400mm size with single hole for pillar tape with C.I. or M.S.
brackets painted white including cutting holes and making good the
same. Rates including providing and fixing 32mm dia C.P. Brass
waste couplin, 32mm dia M.I. Fisher unit, Brass screw down stop tap
of 15mm dia pillar tap capstan head, screw down high pressure with
screws, shanks, back nuts, PVC pipe & 32mm dia flexible waste pipe
up to Nani Trap etc. complete as directed by engineer in charge.
30 10.00 Providing and fixing screw down bib taps of following size.(A)Brass
Each screw down bib tap polished bright.(i)15mm dia..
31 5.00 Providing and fixing screw down bib taps of following size.(B) Brass
Each chromium plated screws down Bib Tap .(i) 15mm dia.
32 3.00 Providing and fixing gun metal chek or non return fullway wheel valve.
Each (A) 15 mm Dia. 186.83 Each
33 3.00 Providing and fixing C.P. brass towel rail complete with C.P. brass
Each brackets fixed to wooden pluges with C.P. brass screws (B) 600 mm x
34 5.00 Providing and fixing toilet paper holder (A) C.P. brass.
35 9.00 Providing and fixing 100 mm dia sand cast iron grating for gully, floor
Each or nanhi trap.
36 9.00 Providing and fixing cast iron (Spun) Nahni trap of the following
Each nominal diameter of self cleaning design with C.I. screaed down or
higned grating including cost of cutting and making good the walls
and floor 100mm inlet and 50mm outlet.(C) 100mm dia.
SBD SECTION-7 BILL OF QUANTITIES-294
37 6.00 Providing and fixing S.W. gully trap with C.I. grating brick masonry
Each chamber and water tight C.I. cover with frame of 300mm x 300mm
size (inside) with standard weight.(i) Square mouth traps.(B) 150mm x
100mm size P or R type
38 3.00 Constructing brick masonry chamber for underground C.I. Inspection
Each chamber and bends with bricks having crushing strength not less than
35Kg/ Cm2 in C.M. 1:5 C.I. cover with frame (Light duty) 455mm x
610mm intenal dimensions total weight of cover with frame to be not
less than 38Kg. (Wt. of cover 23 Kg.) and Wt. of frame 15Kg. )
(R.C.C. top slabe with 1:2:4 mix (1-cement :2- coarse sand :4-graded
stone aggregate 20mm size) foundation concrete 1:5:10 inside
plaster 15mm thick with cement mortar 1:3 finished smooth with a
floating coat of neat cement on walls and bed concrete etc.
complete.(iii) Inside dimensions 600mm x 850 mm and 450mm deep
for pipe lines with three or more inlets. 7180.44 Each
39 50.00 Providing and laying (To level or slopes) and jointing with stiff mixture
Rmt. of cement mortar in proportion 1:1 salt glazed stone ware pipes
including testing of pipes and joint complete. (B) 150 mm Dia
40 3.00 Providing and fixing 600 mm x 450 mm bevelled edge mirror of
Each superior glass mounted on 6 mm thick A.C Sheets or plywood sheet
and fixing to wooden pluge with c.p brass screws and wasers.
41 30.00 Providing, laying and jointing in true line and level 32 mm dia U.P.V.C.
Rmt. Pipe (SCH-40) including fittings make as approved by Engineer In
Charge. Pipe shall be fixed on the wall with the help of clamp at every
two meter c/c. or shall be concealed as directed including necessary
fittings etc. including testing of pipe and joints and fixing the same
with adhesive solvent, including cost of all materials.
42 25.00 Providing, laying and jointing in true line and level 25 mm dia U.P.V.C.
Rmt. Pipe (SCH-40) including fittings make as approved by Engineer In
Charge. Pipe shall be fixed on the wall with the help of clamp at every
two meter c/c. or shall be concealed as directed including necessary
fittings etc. including testing of pipe and joints and fixing the same
with adhesive solvent, including cost of all materials.
43 50.00 Providing, laying and jointing in true line and level 15 mm dia U.P.V.C.
Rmt. Pipe (SCH-40) including fittings make as approved by Engineer In
Charge. Pipe shall be fixed on the wall with the help of clamp at every
two meter c/c. or shall be concealed as directed including necessary
fittings etc. including testing of pipe and joints and fixing the same
with adhesive solvent, including cost of all materials.
SBD SECTION-7 BILL OF QUANTITIES-295
44 10.00 Providing and fixing screw down bib taps of following size.(A) Brass
Nos. screw down bib tap polished bright. (i) 15mm dia.
45 8.00 Providing and fixing brass screw down stop tap.(A) 15mm dia.
Nos. 205.83 Nos.
46 3.00 Providing and fixing gun metal chek or non return fullway wheel valve.
Nos. (A) 25 mm Dia. 420.63 Nos.
Add :- 18% of GST Rs.
Add :- 2% of Contingency Charges Rs.
Add :- 1% of Qaulity Controll Rs.
SBD SECTION-7 BILL OF QUANTITIES-296
DAHOD MUNICIPALITY, DAHOD
NAME OF WORK :- ESTIMATE FOR CONSTRUCTION WORK OF P.C.C & C.C. WORK AT CHAKALIYA
ROAD SAK MARKET AT DAHOD
Item Qty. Description Total Unit Amount
1 52.60 Providing and laying cement concrete (1:3:6) (1 Cement,
Cmt Coarse sand, 6 Hand broken Stone agreegate 40 mm
nominal size ) and curing complete excluding cost of
formwork in (A) foundation and plinth.
2 52.60 Providing and laying controlled cement concrete M.250 and
Cmt curing complete excluding the cost of formwork and
reinforcement for reinforced concrete work in (A) Foundations,
footings, Base of columns and Mass concrete.
Add :- 18% GST Rs.
Add :- 2% of Contingency Charges Rs.
Add :- 1% of Qaulity Controll Rs.
SBD SECTION-7 BILL OF QUANTITIES-297
DAHOD NAGARPALIKA, DAHOD
NAME OF WORK :-CONSTRUCTION WORK OF ENTRY GATE , FENCING AT WALL & GRANITE AT
COMPOUND WALL AT GOVIND NAGAR GARDEN AT DAHOD
Item Qty. Description Total Unit Amount
1 1350.00 Providing and fixing M.S. grills of required pattern to wooden
Kgs. frames of windows etc. with M.S. flats at required spacings
and frame alround, square or round bars with round headed
bolts and nuts or by screws (A) Plain Grill.
FOR MAIN GATE 110.31 Kgs.
2 25.20 Painting two coats (excluding priming coat) on new steel and
Sqm. other metal surface with enamel paint, brushing,interior to
give an even shade including cleaning the surface an even
shade including cleanicn the surface of all dirt, dust and other
foreign matter.
3 0.88 Steel work, riveted in built up sections framed work including
Qtl. cutting, hoisting, fixing in position and applying a priming coat
of red lead paint. (A) In beams and joists, channels angles Tees,
flats, with connecting plates or angle cleats as in main and
cross beams. Hip and jack rafters, purlins conneted to common
rafters and the like. 5889.50 Qtl.
4 0.16 16G Make Tata
Qtl. Double twisted barbed wire, gauge 16, barb spacing 4". four
horizontal lines and two diagonals of galvanised steel barbed
wire weighting 9.38 K.G. per 100 metre strained and fixed to
posts with G.I. staples, including fixing the posts in coping of
SBD SECTION-7 BILL OF QUANTITIES-298
5 480.00 Providing and laying polished Granite tiles with Moulding
Smt. to 25mm thick black thick in risers of steps, skirting Dedo and
pillars laid on 10 mm thick cement mortar 1 : 3 (1 cement :
course sand) and jointed with gray cement slurry mixed with
pigment to match the shade of slab including rubbing,
polishing, Moulding etc. complete. For Flooring, Doors &
Windows Edges. 2974.45 Smt.
Total Amount, Rs.
Total Amount, Rs.
Add :- 18% of GST, Rs.
Add :- 1% of Qaulity Controll Rs.
Add :- 2% of Contingency Charges Rs.
SBD SECTION-7 BILL OF QUANTITIES-299
DAHOD NAGARPALIKA DAHOD
ESTIMATE FOR PROPOSED GARDENING, HOLTICULTURAL & PLANTATION WORK AT GOVIND NAGAR
GARDDEN AT DAHOD.
Sr No Item Description Qty Unit Rate Total Amount
Sr No Item Description Qty Unit Rate Total Amount
Development of lawn including excavation of area up to
to 200 mm depth as per requirement and disposal of same
outside premises, removing of weeds, cleaning, spreading
garden soil, organic fertilizer and mixing same, applying anti
termite insecticides, supplying and laying of carpet lawn,
1 watering. And maintain up to two month.(supplying of 300.00 Smt 450.00
required quantity of carpet lawn shall be in the scope of
contractor).(With Two Years of Maintenance including
Replacement of Damage Plant, lawn Etc With Required
insecticides, pesticides, Fertilizer etc Complete as Directed
Development of shrubs and flower bed at the location
directed by officer in charge including required pit size up to
2*2*2 feet as per required disposal of same out sidepremises
,removing of weed cleaning , filling garden soil ,organic
fertilizer mixing the same applying anti termite treatment and
planting plants as required ,watering and maintaining the
2 fiower beds for period of two months.(supply required 75.00 Smt 300.00
quantity of plants and shrubs shall be in scope of
contractor).variety of shrubs as per index. (With Two Years
of Maintenance including Replacement of Damage Plant,
lawn Etc With Required insecticides, pesticides, Fertilizer etc
Complete as Directed By EIC.)
Plantation of various hedge plants, saplings including
excavation trench of 9 inch depth an width, filling with garden
soil and organic fertilizer, applying anti termite insecticides as
required, plantation of different variety hedge plants at
distance of 8 inch to 2 feet between plants (supply of
required hedge plants and sapling shall be in the scope of
contractor). (With Two Years of Maintanance including
Replacement of Damage Plant,laWN Etc With Required
insectisides, pestisides, Fertilizer etc Complete as Directed
Supply and plantation of palm and exotic plants and focus
variety for including 2*2*2 pit filling with garden soil, mix with
organic fertilizer and termite pesticides ,watering and
maintain up to two months.(supply of require quantity of
4 palm, exotic plants and focus variety in the scope of 25.00 Nos 2000.00
contractor).plants list as per Index (With Two Years of
Maintenance including Replacement of Damage Plant, lawn
Etc With Required insecticides, pesticides, Fertilizer etc
Complete as Directed By EIC.)
SBD SECTION-7 BILL OF QUANTITIES-300
Supply and plantation of trees at various garden and places
including 2*2*2 pit filling with garden soil, mix with organic
fertilizer and termite pesticides, watering and maintain up to
two months (supply of require quantity of trees in the scope
5 of contractor). Trees lists as per index(Bamboo) (With Two 25.00 Nos 1500.00
Years of Maintenance including Replacement of Damage
Plant, lawn Etc With Required insecticides, pesticides,
Fertilizer etc Complete as Directed By EIC.).
Add :- 18% of GST, Rs.
Add :- 1% of Qaulity Controll Rs.
Add :- 2% of Contingency Charges Rs.
SBD SECTION-7 BILL OF QUANTITIES-301
DAHOD NAGARPALIKA, DAHOD
NAME OF WORK :- ESTIMATE FOR CONSTRUCTION WORK OF SECURITY CABIN AT GOVIND NAGAR GARDEN
Item Qty. Description Total Unit Amount
1 8.23 Excavation for base footings upto depth 1.5 m. including
Cmt. sorting out and disposing of the excavated material upto 50 m
lead (loose or soft soil) 125.86 Cmt.
2 3.12 Filling available excavated earth (excluding rock) in trenches.
Cmt. plinth, sides of foundations etc. in layers not exceeding 20 cm.
in depth consolidating each disposited layer by ramming and
watering 137.47 Cmt.
3 0.81 Filling in foundation and plinth with murrum or selected soil in
Cmt. layers of 20cm thickness including watering, ramming and
consolidating etc. complete.
4 2.70 Carrying out plinth treatment to post construction/existing
Smt. structure by spraying chemical solution for termite control
treatment including labour and material consistment with I.S.I
specification. Using Chlordene and chiorpurfiles 20 EC. As per
6131_paret-II consteration weight one percent is
recommended i.e. one litre 20 EC chemical emulsion with
liter give 1% concrentration inclusive of one litre chemical
emulsion application at the rate of 5 litre chemical/sqm of
surface as recommended as per I.S.
5 2.02 Providing and laying cement concrete 1:3:6 (1 Cement,
Cmt. coarse sand, 6 hand broken stone aggregates 40mm. Nominal
size) and curing ecomplete excluding cost of formwork in (A)
Foundation and Plinth.
6 Providing and laying controlled cement concrete M-200 and
curing complete including the cost of formwork and excluding
the cost of reinforcement of reinforced concrete work in
a 0.17 -- do -- for Coping 5803.97 Cmt.
b 0.26 -- do -- for R.C.C. Lintel 8689.03 Cmt.
SBD SECTION-7 BILL OF QUANTITIES-302
c 0.17 -- do -- for Chhajja 7950.72 Cmt.
e 1.02 -- do -- for Beam 6252.91 Cmt.
f 0.66 -- do -- for R.C.C. Slab 6508.44 Cmt.
284.02 Providing T.M.T. Bar Fe 500 / 500-D reinforcement for
Kgs. R.C.C.work including bending, binding and placing in position
complete upto floor two level.(upto 10 ton)
8 4.31 Brick work using common burnt building bricks having crushing
Cmt. strngth not less than 35 Kg./cm2 in super structure for Ground
Floor in C.M. (1:6) (1 Cement, 6 fine sand) racking out joints
curring etc. complete directed by Engineer-in-charge.
9 2.09 Brick work using common burnt building bricks having crushing
Cmt. strngth not less than 35 Kg./cm2 in super structure for Ground
Floor in C.M. (1:6) (1 Cement, 6 fine sand) racking out joints
curring etc. complete directed by Engineer-in-charge.
10 1.58 Providing and fixing flush door shutters, soild core construction
Smt. with frame of first class hardwood with crossboard and face
veneer or plywood face panels, including anodised aluminium
butt hinges with necessary screws. (B) Non-decorative type
and block board core anodised alluminium butt hinges in flush
door shutters. (2) 35 mm thick.
11 1.44 Providing and fixing glazed louverd glass windows and
Smt. ventilators with teakwood frame 10cm x 7cm size including the
cost of oil painting to wood work etc. complete.(A)C.M 1:3
12 221.40 Providing and fixing M. S. grills of requried pattern to wooden
Kgs. frames of window etc. with M. S. flats at requried spacings and
frame alround square or round bars with round headed bolts
and nuts or by screws. (B) Plain Grills 110.31 Kg.
SBD SECTION-7 BILL OF QUANTITIES-303
13 15.33 Providing 15 mm. thick cement plaster in single coat on Rough
Smt. (similar) side of single or half brick walls for interior plastering
upto floor two level and finished even and smooth in. (II)
cement mortar 1 : 4 (1 cement : 4 sand) Extra over item 58 to
64 for finishing with a floating coat of neat cement slurry. (upto
10 ton) 231.38 Smt.
14 8.65 Providing 10 mm. thick cement plaster in single coat on
Smt. brick/concrete walls for interior plastering up to floor two level
and finished even and smooth in. (II) cement mortar 1 : 4 (1
cement:4 sand) Extra over item 58 to 64 for finishing with a
floating coat of neat cement slurry. (upto 10 ton) Extra over
items 58 to 71 for plastering on cellings and sofits of stairs upto
floor two level instead of plastering on walls.
15 23.57 Providing and Laying 20 mm thick sand face cement plaster on
Smt. Walls upto height of 10 mts. Above ground level consisting of
12mm thicjk backing coat of C.M 1:3 (1 Cement, 3 Sand ) and
8 mm thick finishing coat of C.M 1:1 (1 Cement, 1 Sand) etc.
complete. 353.98 Smt.
16 23.98 Distempering (Three Coat) with oil bound washable distemper
Smt. of approved brand and manufacture and of required shade on
wall surfaces to give and even shade over and including a
primer coat with alkali resistance primer of approved brand
after throughly brushing the surface to give and even shade
free from foreign matter and also including preparing the
surface even and smooth.
17 23.57 Finishing wall with Weather Proof Acrylic Emulsion Exterior
Smt. Paint on wall surface (three coat) to give and even shade and
of approved brand and manufacture including throughly
brooming and brushing the surface to remove all dirts, and
remians of loose powdered material.
18 4.17 Providing & Laying 24 "x 24" vitrified 8 mm thick tile flooring
Smt. over 20 mm ( average) base of cement mortar 1:6 (1: cement :
6 coarse sand ) on new surface or fixing on existing flooring by
adhesive material including dismentaling of existing flooring
and jointed with color cement slurry including finised with flush
pointing & cleaning the surface etc. complete for antiskit . (upto
SBD SECTION-7 BILL OF QUANTITIES-304
19 2.52 Providing and laying polished Granite tiles 18 mm thick in
Smt risers of steps, skirting Dedo and pillars laid on 10 mm thick
cement mortar 1 : 3 (1 cement : 3 course sand) and jointed
with gray cement slurry mixed with pigment to match the shade
of slab including rubbing, polishing, Moulding etc. complete.
For Flooring, Doors & Windows Edges.
20 2.70 Providing and laying broken china mosaic flooring for terrace
Smt using 12mm to 20mm broken pieces of glazed tiles to be laid
over cement mortar 1:3 to plain or slope and to be tempered to
bring mortar crème out upto surface using white cement
including rounding off junctions and extending them upto 15cm
along the wall, clearing with water and oxalic acid. etc. as
21 4.00 Providing, Supplying, Lowering and Laying in standard length
Rmt. ISI mark rigid unplasticised PVC pipes suitable for potable
water with ring fit joint including cost of rings, as per IS
Specification no. 4985/1988 including all local and central
taxes, transportation, freight charges, octroi, inspection
charges, loading, unloading, conveyance to the departmental
stores and including cost of jointing material etc. complete.75
Add : 5% for Electrical Installation Rs.
Add 18 % For GST
Add 2% For Contingecies Charges Rs.
Add 1% For Quality Control Rs.
SBD SECTION-7 BILL OF QUANTITIES-305
DAHOD NAGARPALIKA DAHOD
ESTIMATE FOR OUTDOOR GYM EQUIPMENTS AT GOVIND NAGAR GARDEN , AT DAHOD.
Sr. Item Qauntity Total Rate Per Amount
1 Outdoor GYM Equipments . As Per Directed
Engi. In Charge excluding Labour,
Transpotation & All Taxes. Etc complete.
Chest Press 1.00 627250.00 No.
Leg Press 1.00 57750.00 No.
Stair Stepper & Twister 1.00 58050.00 No.
Pull Chair 1.00 65850.00 No.
Cross Trainer 1.00 57750.00 No.
Add : 5% of Transportation Charge Rs.
Add : 18% of GST Rs.
SBD SECTION-7 BILL OF QUANTITIES-306
DAHOD NAGARPALIKA DAHOD
ESTIMATE FOR CHILDREN PLAY AREA EQUIPMENT & RUBBERIZED FLOORING AT GOVIND
NAGAR GARDEN , AT DAHOD.
Sr. Item Qauntity Total Rate Per Amount
1 Children play area Equipment &
Rubberized flooring . As Per Directed Engi.
In Charge excluding Labour, Transpotation &
All Taxes. Etc complete.
With 5’ Platform, 2 Swings, 2 slides 1.00 227250.00 No.
Double Swings 1.00 23750.00 No.
Marry Go Round 5' 1.00 29750.00 No.
SeeSaw Single 2.00 19750.00 No.
Spring Rider 2.00 11050.00 No.
Rock Climber 1.00 35750.00 No.
Monkey Bar 2.00 25750.00 No.
2 Safety outdoor Rubberized flooring Application
:- Children play area. Thickness:-
Base layer :- SBR - 19mm
Top Layer :- EPDM – 6mm
Note:- Rubberized flooring rates is including
Supply of material & Installation charges. 8000.00 250.00 Sq.ft
Add : 5% of Transportation Charge Rs.
Add : 18% of GST Rs.
SBD SECTION-7 BILL OF QUANTITIES-307
DAHOD NAGARPALIKA DAHOD
ESTIMATE FOR PRE-CAST R.C.C. BENCHES AT GOVIND NAGAR GARDEN , AT DAHOD.
(Rate Taken From Market Quotation)
Sr. Item Qauntity Total Rate Per Amount
1 Precast Concrete Reinforced Bench . As Per Directed Engi.
In Charge excluding Labour, Transpotation & All Taxes. Etc
2 Dustbins for children's play areas and gardens (typically
shaped like animals or cartoon characters) As Per Directed
Engi. In Charge excluding Labour, Transpotation & All Taxes.
Add : 5% of Transportation Charge Rs.
Add : 18% of GST Rs.
SBD SECTION-7 BILL OF QUANTITIES-308
DAHOD NAGARPALIKA DAHOD
ESTIMATE FOR WATER COOLER & LED SOLAR STREET LIGHT AT GOVIND NAGAR GARDEN , AT DAHOD.
Sr. Item Qauntity Total Rate Per Amount
1 Providing & Erecting full SS Body (SS 304) Split type water cooler
having storage capacity 160 to 175 Ltr.(Tank SS 304) & Cooling
capacity 150 ltr. Per hour @ an ambient temp of 350 C.The outlet
temp. of the water should drop by 150C within a hour,The water
cooler should be comprising of hermetically sealed Reciprocating
compressor with R134A, fan motor, Copper Condensing unit with
company fabricated Outdoor Unit water tank surrounded by
evaporating coil, thermostats, relay etc.complete with necessary
copper tube & Insulation, M.S Chanel Stand with Painting for water
tank & M.S. Powder Coated Stand for Outdoor unit with Installation.
With DPELCB and 4 Way DB Box with accessory Three core Cord
for connection.
2 Supplying and erecting LED Solar street lights with High power
White LEDs wattage of 1Watt and above assembled on single
MCPCB, efficiency more than 130 lm/w and corrosion free High
pressure die cast aluminum housing with smooth finish powder
coated and heat sink extruded aluminium with diffuser and
Polycarbonate optics/ lenses with company mark/name engraved
or embossed with 36 hours battery backup & MPPT 24V,7.5 A
charge controller with 12 hours automatic switch on/off with wind
speed resistance
lumens, as per PV
61215. – 2x100W and 6 mtr
poles complete erected.
Add : 18% of GST Rs.
Add : 1% Q.C Rs.
Add : 2% of Contiguncy Charges. Rs.
SBD SECTION-7 BILL OF QUANTITIES-309
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
BOQ.pdf
Notes.pdf
SBD_Part1.pdf
SBD_Part2.pdf
Others Important 1.pdf
Others Important 2.pdf
Others Important 3.pdf
Others Important 4.pdf
Others Important 5.pdf
Others Important 6.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .