| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.2 LAccepted-AOC BAGHMARA BAZAR DHANBAD DHANBAD JHARKHAND INDIA 828306 | DHANBAD | DHANBAD | JHARKHAND | 828306 | L1 | Accepted-AOC L1 Firm | |
| 2 | L2₹1.1 L+₹5,125.25 (5.00%)Rejected-Finance RAM CHARAN SINGH S O BRIJMOHAN SINGH VILL DUMRA THANA BAGHMARA NAWAGADH DHANBAD DHANBAD 828306 JHARKHAND INDIA | DHANBAD | JHARKHAND | 828306 | L2 | Rejected-Finance Not L1 Firm | |
| 3 | L3₹1.3 L+₹25,626.25 (25.0%)Rejected-Finance | L3 | Rejected-Finance Not L1 Firm |
Tender Value
₹1.2 L
EMD Value
₹1,600
Closing Date
10 Feb 2023, 9:00 amClosed
Area Manager (EnM), Block-II Area
Office of the General Manager, Block-II Area, P.O.-Nawagarh Distt-Dhanbad 828306
Shifting of 4000 GPM and 2000 GPM pump in the lower side of the D/L face sump long with diversion of its 10in/8in dia delivery pipeline from D/L face to Box cut-III Deco cutting zone sump of BOCP Mine
2023_BCCL_269378_1
GM/B-II/AM (ENM)/E-TENDER/2022-23/271 dt 28.01.23
Open Tender
Electrical and Maintenance Works
Percentage
7 days
ABOCP Mine, BII Area
Please refer Tender documents.
11 documents required · 11 mandatory
₹1,600
18 Apr 2023
30 Jan 2023
11 Feb 2023
31 Jan 2023
10 Feb 2023
31 Jan 2023
31 Jan 2023 - 3 Feb 2023
eProcurement System of Coal India Limited Created By: GAURAV GAURAV Created Date/Time: 11-Feb-2023 11:18 AM Tender Title: Shifting of 4000 GPM and 2000 GPM pump in the lower side of the D/L face sump long with diversion of its 10in/8in dia delivery pipeline from D/L face to Box cut-III Deco cutting zone sump of BOCP Mine Tender ID: 2023_BCCL_269378_1
Tender Inviting Authority: Area Manager (E&M), Block-II Area
Name of Work : Shifting of 4000 GPM and 2000 GPM pump in the lower side of the D/L face sump long with diversion of its 10"/8" dia delivery pipeline from D/L face to Box cut-III Deco cutting zone sump of BOCP Mine.
SCHEDULE OF WORK / ITEM(S)
Sl.No Bidder Name Estimated Rate Quoted Percentage Quoted Rate in Figures and Words
1.00 DHANBAD EARTH MOVERS(GSTN-20AMUPA3449F1ZB) 102505.00 0.00 102505.00 One Lakh Two Thousand Five Hundred and Five
2.00 M/S. SEEMA ENGINEERING WORKS(GSTN-20BCWPS5468P1ZJ) 102505.00 5.00 107630.25 One Lakh Seven Thousand Six Hundred and Thirty
3.00 RIYA ENGINEERING WORKS(GSTN-NA) 102505.00 25.00 128131.25 One Lakh Twenty Eight Thousand One Hundred and Thirty One
Lowest Amount Quoted BY: DHANBAD EARTH MOVERS(102505.00)
BOQ Summary Details Tender Title: Shifting of 4000 GPM and 2000 GPM pump in the lower side of the D/L face sump long with diversion of its 10in/8in dia delivery pipeline from D/L face to Box cut-III Deco cutting zone sump of BOCP Mine Tender ID: 2023_BCCL_269378_1
Sheet Name Sl.No Bidder Name Amount Bid Rank
BoQ1 1 DHANBAD EARTH MOVERS 102505.00 L1
2 M/S. SEEMA ENGINEERING WORKS 107630.25 L2
3 RIYA ENGINEERING WORKS 128131.25 L3
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .