Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.7 CrAccepted-AOC | ₹1.7 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹1.7 CrRejected-AOC C O LT MAAHANTA NARZARY W NO 5 TENGAPARA P O P S KOKRAJHAR DIST KOKRAJHAR BTC ASSAM PIN 783370 | KOKRAJHAR | KOKRAJHAR | ASSAM | 783370 | ₹1.7 Cr | L2 | Rejected-AOC L2 |
| 3 | L3₹1.7 CrRejected-AOC | ₹1.7 Cr | L3 | Rejected-AOC L3 |
| Sl No | Description | Qty | Unit | AMIT BRAHMA L1 | DHARAMSING NARZARY L2 | LAXMI SHARMA L3 |
|---|---|---|---|---|---|---|
| 1.00 | 2.2 Clearing and grubbing road land including uprooting wild vegetation, grass, buses, shrubs, saplings and trees of girth up to 300mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000m including removal and disposal of top organic soil not exceeding 250mm in thickness as per Technical Specification Clauses 201.
(I) By Manual Means. :: (A) In area of non thorny jungle. | 1.25 | Hect | 52,995.09 ₹66,243.86 | 52,995.08 ₹66,243.85 | 52,995.1 ₹66,243.88 |
| 2.00 | 3.2 Scarifying the existing bituminous road surface to a depth of 150 mm and disposal of scarified material with a lift upto 3.0m and lead upto 1000 m as per Technical Specification Clause 301.4. | 9,562.5 | Cum | 7.35 ₹70,284.38 | 7.34 ₹70,236.56 | 9 ₹86,062.50 |
| 3.00 | 3.4 Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting p g to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 :: (i) Private Land | 8,163.6 | Cum | 258.21 ₹21.1 L | 258.2 ₹21.1 L | 265 ₹21.6 L |
| 4.00 | 15.2 Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. :: (i) Private Land | 946.69 | Cum | 339.68 ₹3.2 L | 339.68 ₹3.2 L | 342 ₹3.2 L |
| 5.00 | Analysis /4.7.III(B) WBM Grading 3 . Using stone screening Type B 11.2 mm for Gr. II . Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405 :: (B) By Mechanial Means. | 1,104.47 | Cum | 4,600.9 ₹50.8 L | 4,600.9 ₹50.8 L | 4,600.9 ₹50.8 L |
| 6.00 | 5.1.(ii) PRIME COAT ii) Medium porosity
Providing and applying primer coat with Bitumen emulsion (CSS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.90- 1.2 kg/ sqm using mechanical means as per Technical Specification Clause 502. | 9,562.5 | Sqm | 48.93 ₹4.7 L | 48.93 ₹4.7 L | 50 ₹4.8 L |
| 7.00 | 5.2 Tack Coat (ii) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503. | 19,125 | Sqm | 13.33 ₹2.5 L | 13.33 ₹2.5 L | 13.33 ₹2.5 L |
| 8.00 | 17.1,III,A,ii Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5% by weight of total mix and filler transporting the hot miox to work site,laying with a hydrostatic paver finisher with sensor control to the reqd. grade, lavel and alignment,rolling with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoSRT&H cl. no. 507. complete in all respect. (including carriage of mixed materials up to 10.0 Km initial lead from mixing plant )( Including cost of testing of materials at site and laboratory as directed by the deptt.) :: With hydrated lime / cement as filler (refer table 500-9 of MoSRT&H specification) & anti stripping agent as per IS:14982 (Refer Appendix-5 of MoSRT&H specification) :: With 60/70 or VG-30 grade bitumen :: for Grading II (19 mm nominal size) | 478.12 | Sqm | 10,485.26 ₹50.1 L | 10,485.26 ₹50.1 L | 10,485.26 ₹50.1 L |
| 9.00 | 17.3, III,A,i Bituminous Concrete: Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of
75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 % of mix and filler transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the reqd. grade, lavel and alignment,rolling with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoSRT&H cl. no.509. complete in all respect. (including carriage of mixed materials up to 10.0 Km initial lead from mixing plant )( Including cost of testing of materials at site and laboratory as directed by the deptt.) :: III) With hydrated lime / cement as filler (refer table 500-9 of MoSRT&H specification) & anti stripping agent as per IS:14982 (Refer Appendix-5 of MoSRT&H specification) :: A) With 60/70 or VG-30 grade bitumen :: i) for Grading I (19 mm nominal size) | 251.02 | Cum | 12,404.39 ₹31.1 L | 12,404.39 ₹31.1 L | 12,404.39 ₹31.1 L |
| 10.00 | 16.60 Planting of Trees and their Maintenance for three Year (Planting of trees by the road side (Avenue trees) in 0.60 m dia holes, 1 m deep dug in the ground, mixing the soil with decayed farm yard/sludge mannure, planting the saplings, backfilling the trenches, watering , fixing the tree guatrd and maintaining the plants for three year. | 30 | Each | 760.72 ₹22,821.60 | 760.72 ₹22,821.60 | 760.72 ₹22,821.60 |
Tender Value
₹1.7 Cr
EMD Value
₹3.4 L
Closing Date
6 Jan 2026, 12:30 pmClosed
Sri J.M. Basumatary
O/o the Addl. Chief Engineer-cum-Director, PWD, BTC, Kokrajhar.
Construction of road from Dahalapara to Shyamgaon village From Ch.0.00m to Ch.2550.00m by providing DBM BC under RIDF-XXXI of NABARD for the year 2025-26. TN_67KOK_RIDF-XXXI-06
2025_BTC_49288_1
No.ACE-22/PWD/NIT/GW/25-26/19
Open Tender
Civil Works – Roads
180 days
Kokrajhar
Refer to Tender Documents
4 documents required · 4 mandatory
₹3,400
₹3.4 L
Yes
25 Mar 2026
15 Dec 2025
7 Jan 2026
15 Dec 2025
6 Jan 2026
15 Dec 2025
15 Dec 2025 - 6 Jan 2026
2.2 Clearing and grubbing road land including uprooting wild vegetation, grass, buses, shrubs, saplings and trees of girth up to 300mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000m including removal and disposal of top organic soil not exceeding 250mm in thickness as per Technical Specification Clauses 201. (I) By Manual Means. :: (A) In area of non thorny jungle.
3.2 Scarifying the existing bituminous road surface to a depth of 150 mm and disposal of scarified material with a lift upto 3.0m and lead upto 1000 m as per Technical Specification Clause 301.4.
3.4 Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting p g to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 :: (i) Private Land
15.2 Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. :: (i) Private Land
Analysis /4.7.III(B) WBM Grading 3 . Using stone screening Type B 11.2 mm for Gr. II . Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405 :: (B) By Mechanial Means.
5.1.(ii) PRIME COAT ii) Medium porosity Providing and applying primer coat with Bitumen emulsion (CSS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.90- 1.2 kg/ sqm using mechanical means as per Technical Specification Clause 502.
5.2 Tack Coat (ii) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
17.1,III,A,ii Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5% by weight of total mix and filler transporting the hot miox to work site,laying with a hydrostatic paver finisher with sensor control to the reqd. grade, lavel and alignment,rolling with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoSRT&H cl. no. 507. complete in all respect. (including carriage of mixed materials up to 10.0 Km initial lead from mixing plant )( Including cost of testing of materials at site and laboratory as directed by the deptt.) :: With hydrated lime / cement as filler (refer table 500-9 of MoSRT&H specification) & anti stripping agent as per IS:14982 (Refer Appendix-5 of MoSRT&H specification) :: With 60/70 or VG-30 grade bitumen :: for Grading II (19 mm nominal size)
17.3, III,A,i Bituminous Concrete: Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 % of mix and filler transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the reqd. grade, lavel and alignment,rolling with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoSRT&H cl. no.509. complete in all respect. (including carriage of mixed materials up to 10.0 Km initial lead from mixing plant )( Including cost of testing of materials at site and laboratory as directed by the deptt.) :: III) With hydrated lime / cement as filler (refer table 500-9 of MoSRT&H specification) & anti stripping agent as per IS:14982 (Refer Appendix-5 of MoSRT&H specification) :: A) With 60/70 or VG-30 grade bitumen :: i) for Grading I (19 mm nominal size)
16.60 Planting of Trees and their Maintenance for three Year (Planting of trees by the road side (Avenue trees) in 0.60 m dia holes, 1 m deep dug in the ground, mixing the soil with decayed farm yard/sludge mannure, planting the saplings, backfilling the trenches, watering , fixing the tree guatrd and maintaining the plants for three year.
10.2 (A). I Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3 fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per drawings and Technical Specification Clause 801 (ii) 600mm equilateral triangle
(iv) 800mm x 600 mm rectangular
16.38 Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes and conforming to the MoSrt&H specifications
10.10 Reiforced cement concrete M15 grade kilometre stone/local stone of standard design as per IRC:8 fixing in position including painting and printing, etc. as per drawing and Technical Specification Clause 1703. ii) Ordinary kilometre Stone (Precast)
iii) 200m Stone (precast)
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.16 MB
SBDRIDF.pdf
Tender Documents • 13.74 MB
BOQ_78259.xls
BOQ • 0.26 MB
FOBRIDF.pdf
Additional Documents • 0.25 MB
Download all tender documents and submit your bid