Superintending Engineer
Office of the 8th Circle, PWD, New Tehri.
Renewal work by SDBC on 1-Uttarkashi lambgaon Ghansali Tilwara Motor Road road, 2-Budhakedar anyarakhal Motor Road, 3- Chatiyara Khawara Motor Road in Ghansali Constituency of distt. Tehri Garhwal under Annual Repair Year 2022-23.
2022_pwd_43622_1
1699/08Cash-Tender-8/2021 Date 21-04-2022
Open Tender
Civil Works - Roads
Item Rate
270 days
Ghansali (Tehri Garhwal)
As Per NIT, Technical Bid and BOQ
2 documents required · 2 mandatory
₹5,900
EE TD PWD Ghansali
₹4 L
8th Circle, PWD, New Tehri.
7 Sept 2023
23 Apr 2022
6 May 2022
23 Apr 2022
6 May 2022
23 Apr 2022
26 Apr 2022
Amount
1-Uttarkashi lambgaon Ghansali Tilwara Motor Road road (Equivalent length 5.89 km.)
WBM Grading 3Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405..[Grading of no-3] (22.4 -53 mm size)
Tack Coat providing and applying tack coat with Bitumen emlsion RS-1 using emlsion distributer @ of 0.20 to 0.25 kg/sqm,on the prepared bituminous surface cleaned with hydraulic broom as per TS clase 503
BM:- Bituminous MacadamProviding and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per Table 500.4 premixed with bituminous binder,transported to site upto a lead of 1000 m laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per Technical Specification Clause 504.(Bitumen VG-10 @ 3.3% of the weight of mix has been used for analysis purpose.The choice of bitumen will depend upon the prevailing site conditions and shall be in accordance with Clause 504 of MORD)
Providing and laying Semi Dense Bituminous Concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5% of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 508 complete in all respects for Grading II-10 mm VG-10
Providing and laying of hot applied thermoplastic compound of ISI Mark Approved Quality of 2.5 mm thick including reflectorising glass beads @250 gms per sqm area, as per IRC:35 .The finished surface to be level,uniform and free from streaks and holes.
2-Budhakedar anyarakhal Motor Road (Equivalent length 5.35 km.)
WBM Grading 3Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405..[Grading of no-3] (22.4 -53 mm size)
Tack Coat providing and applying tack coat with Bitumen emlsion RS-1 using emlsion distributer @ of 0.20 to 0.25 kg/sqm,on the prepared bituminous surface cleaned with hydraulic broom as per TS clase 503
BM:- Bituminous MacadamProviding and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per Table 500.4 premixed with bituminous binder,transported to site upto a lead of 1000 m laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per Technical Specification Clause 504.(Bitumen VG-10 @ 3.3% of the weight of mix has been used for analysis purpose.The choice of bitumen will depend upon the prevailing site conditions and shall be in accordance with Clause 504 of MORD)
Providing and laying Semi Dense Bituminous Concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5% of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 508 complete in all respects for Grading II-10 mm VG-10
Providing and laying of hot applied thermoplastic compound of ISI Mark Approved Quality of 2.5 mm thick including reflectorising glass beads @250 gms per sqm area, as per IRC:35 .The finished surface to be level,uniform and free from streaks and holes.
3-Chatiyara khawara Motor Road (Equivalent length 2.14 km.)
WBM Grading 3Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405..[Grading of no-3] (22.4 -53 mm size)
Tack Coat providing and applying tack coat with Bitumen emlsion RS-1 using emlsion distributer @ of 0.20 to 0.25 kg/sqm,on the prepared bituminous surface cleaned with hydraulic broom as per TS clase 503
BM:- Bituminous MacadamProviding and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per Table 500.4 premixed with bituminous binder,transported to site upto a lead of 1000 m laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per Technical Specification Clause 504.(Bitumen VG-10 @ 3.3% of the weight of mix has been used for analysis purpose.The choice of bitumen will depend upon the prevailing site conditions and shall be in accordance with Clause 504 of MORD)
Providing and laying Semi Dense Bituminous Concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5% of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 508 complete in all respects for Grading II-10 mm VG-10
Providing and laying of hot applied thermoplastic compound of ISI Mark Approved Quality of 2.5 mm thick including reflectorising glass beads @250 gms per sqm area, as per IRC:35 .The finished surface to be level,uniform and free from streaks and holes.
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .