Tender Value
₹70 L
EMD Value
₹1.4 L
Closing Date
30 Jun 2026, 4:00 pmClosed
Executive Engineer REW Kargil
Executive Engineer REW Kargil
Construction of Earthen Pond at Barchay
2026_RDD_19097_1
e-Tender- 09 of REW Kargil UTL of 2026-27
Open Tender
Civil Works - Others
Percentage
Sodth
Please refer Tender documents.
3 documents required · 3 mandatory
₹700
Executive Engineer REW Kargil
₹1.4 L
22 Jun 2026
22 Jun 2026
1 Jul 2026
22 Jun 2026
30 Jun 2026
23 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in bulk excavation by mechanical means (Hydraulic excavator) over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil at the rate 60% | 5,241.69 | Cum | 245.94 | ₹12,89,141.24 |
| 2 | Ordinary rock at the rate 30% | 2,620.85 | Cum | 452.99 | ₹11,87,218.84 |
| 3 | Hard rock (Blasting Prohibited) at the rate 10 % | 873.62 | Cum | 1,292.6 | ₹11,29,241.21 |
| 4 | Removal of Surface Boulder by mechinical means inc disposal of usual lead and lift | 248.2 | Cum | 300 | ₹74,460 |
| 5 | Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm depth, dressing to camber and consolidating with road roller including making good the undulations etc. and re-rolling the sub grade and disposal of surplus earthwith lead upto 50
metres. | 1,517.8 | sqm | 183.34 | ₹2,78,273.45 |
| 6 | Providing and laying Good earth mixed with Lime 12%and ramming compacting manually complete job | 240.66 | Cum | 1,200 | ₹2,88,792 |
| 7 | Banking excavated earth in layers not exceeding 20 cm in depth, breaking clods, watering, rolling each layer with ½ tonne roller, or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up, in embankments for roads, flood banks, marginal banks, and guide banks etc., lead upto 50 m and lift upto 1.5 m :(excl. ramming with PRR and watering)
All kinds of soil | 636 | Cum | 491.27 | ₹3,12,447.72 |
| 8 | Providing and Laying HDPE Sheet Pond Linner 300-500 micron incl. carriage and fixing joints and overlap etc Complete job | 1,847 | sqm | 550 | ₹10,15,850 |
| 9 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement- All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 6.48 | Cum | 11,277.66 | ₹73,079.24 |
| 10 | RCC Thermo-Mechanically Treated bars of grade Fe-500D or more | 324 | kg | 129.01 | ₹41,799.24 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.08 MB
BOQ_45513.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .