Loading…
Loading…
Tender Value
₹10.6 L
EMD Value
₹21,183
Closing Date
1 Oct 2026, 3:00 pm3d left
Executive Engineer
Bidhannagar Municipal Corporation
Construction of cover slab along with repairing of interior portion of an old damaged existing manhole chamber in six (06) nos. of different location within Salt Lake area under Bidhannagar Municipal Corporation.
2026_MAD_1042265_1
NIT NO. 548/PWD(BMC), DTD. 15.09.2026
Open Tender
Miscellaneous Works
Percentage
45 days
Bidhannagar Municipal Corporation
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹21,183
15 Sept 2026
15 Sept 2026
5 Oct 2026
15 Sept 2026
1 Oct 2026
15 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling R.C floor, roof beams etc. Including cutting rods and removing rubbish as directed within a lead of 75 m including stacking of steelbars.
(a) In ground floor including roof. | 17.16 | m3 | 1,956 | ₹33,564.96 |
| 2 | M.S structural works in columns beams etc. With simple rolled structural members (e.g joists, angle, channel sections conforming to IS: 226, IS: 808 & SP (6) - 1964 connected to one another with bracket, gussets, cleats as per design, direction of Engineer-in-charge complete including cutting to requisite shape and length, fabrication with necessary bolting, metal arc welding conforming to IS: 816-1969 & IS:1995 using electrodes of approved make and brand conforming to IS:814 - 2004, haulage, hoisting and erection all complete. The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour required for the work including all incidental charge of all tools and plants and labour required for the work including all incidental charges such as electricity charges, labour insurance charges etc.
i) For structural members of specified sections weighing less than 22.5 Kg/m | 6.18 | MT | 59,119 | ₹3,65,355.42 |
| 3 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. | 2.94 | MT | 60,580 | ₹1,78,032.5 |
| 4 | Supplying ready mixed concrete of M 25 Grade with well graded stone chips of 20 mm nominal size containing designed quantity of cement per Cu.m of wet concrete produced in computerised batching plant under controlled condition using approved super plastisizer, designing concrete mix following I.S. 10262 and I.S. 456, transporting the mix with agitation in transit mixer to work site depositing the mix on a platform erected for the purpose at required levels of concreting and then placing the mix in its final location of form work compacting and curing the same complete as per specification & direction of the Engineer-in-charge including computerised batching plant transit mixer with all accessories vibrators etc. inclusive of all other incidental charges in this connection complete but excluding cost of hire charge of platform and its supporting staging which would be paid through separate item. [cement to be supplied by the Manufacturer/ supplier]
In Ground Floor and Foundation
(i) Without approved concrete pump | 18.72 | m3 | 7,617 | ₹1,42,590.24 |
| 5 | Supplying to site empty cement polythene bags (capacity 50kg) in good condition including stacking, incedental charges etc. all complete (capacity 50kg) | 570 | Each | 6 | ₹3,420 |
| 6 | Labour charges for filling empty cement gunny bag/polythene bag (capacity 50 kg) with all kinds of earth (wet or dry), sand or agreegates (stone/brick) and sewing as done in case of cement bags, (tying with a knot after filling will not be accepted) and stacking within a lead of 30metre as per direction of Engr-in-charge (cost is excluding the cost of any types of filling materials.)
N.B Volume of earth/sand filled bags should not be less than 0.028 cum/bag | 570 | Each | 7 | ₹3,990 |
| 7 | Dumping in position earth / sand filled gunny / poly bags (capacity 50 kg) within a lead of 30 metre inclusive of all lifts. | 570 | Each | 3 | ₹1,710 |
| 8 | Bailing out water by pump including all leads and lifts and including making all arrangements for disposal, where continuous flow or seepage of water is encountered and rating of pumps and hours of operation is specifically ascertained as per direction of the Engineer-in-charge. | 480 | Hp-Hr | 23 | ₹11,040 |
| 9 | Artificial stone in floor, dado, staircase etc with cement
concrete (1:2:4)withstonechips, laid inpanelsasdirected
with topping made with ordinary or white cement (as
necessary) andmarble dust in proportion (1:2) including
smooth finishingand roundingoff corners including raking out jointsorrougheningofconcretesurfaceand application of cement slurrybefore flooring works using cement @1.75 kg/sq.m all complete including all materials and labour.
In ground floor.
3mm. thick topping(Highpolishinggrindingonthis itemis
not permitted with ordinary cement).
Using grey cement
(iii) 35 mm. thick | 300 | m2 | 330 | ₹99,000 |
| 10 | Removing earth/sand filled poly bags/gunny bags from the channel bed/slope and initially depositing the same near channel bank at a place as directed by the Engineer-in-Charge for measurement of bag & then disposing off the same at a distance not less than 150 metre from the channel site. | 570 | Each | 6 | ₹3,420 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.11 MB
BOQ_2558307.xls
BOQ • 0.29 MB
Condition.pdf
Additional Documents • 17.40 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .