| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹40.9 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹41.0 L+₹15,951.13 (0.39%)Rejected-AOC | L2 | Rejected-AOC L2 |
Tender Value
₹40.9 L
EMD Value
₹50,000
Closing Date
2 Nov 2020, 1:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Manager Subcontract
KEL Kochi
ADS-MLA(2019-20) - THRITHALA CONSTITUENCY -CONSTRUCTION OF VARIOUS ROAD UNDER THIRUMITTAKODU GRAMA PANCHAYATH
2020_KEL_394856_1
KRO/ BDC/718/2020
Open Tender
Civil Works - Roads
Item Rate
150 days
KEL Kochi
As per NIT
6 documents required · 6 mandatory
₹2,950
online
₹50,000
Yes
7 Jan 2021
26 Oct 2020
3 Nov 2020
26 Oct 2020
2 Nov 2020
26 Oct 2020
26 Oct 2020 - 2 Nov 2020
120 days
Amount
APPENDIX 1- CONSTRUCTION OF CHERAPPARAMBU SMASHANAM ROAD
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
2.1.1 : Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil
51.2.3 : Filling with Quarry Muck Filling up low lying and water logged areas with local material/ quarry muck, spreading in layers, leveling the top at site and consolidation by ramming, etc complete for improving the CBR value of subgrade
16.42 : Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) in pavements, laid to required slope and camber in panels as required including consolidation finishing and tamping complete. Cement make: Use Malabar cement only as per Govt. direction and in case of non availabilty of Malabar cement use Ultra Tech, Dalmia, Ramco or eq. brand in the order of preference.
APPENDIX 2- CONSTRUCTION OF EARATHUNJALIL ROAD
4.9 : Wet Mix Macadam: Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406.By Mechanical Means with 1 km lead.(Quantity by level calculation )
5.1.1a : Prime Coat :-Low porosityProviding and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
5.2.2a : Tack Coat : Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
5.9.1.2a : 20mm thick Open-Graded Premix Carpet using Bituminous (penetration grade/modified bitumen) Binder - Bitumen S-65Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either Type A or Type B or Type C as per Technical Specification Clause 508.Case - I By Manual Means(II)Bitumen (S-65)
5.12.A.3.2a : Seal Coat - Manual Means - Type C - Bitumen S-65Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A, Type B and Type C as per Technical Specification Clause 510A.By Manual Means:-Case - III : Type C(II)Bitumen (S-65)
4.11.2 : Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place method normal. Construction of granular sub-base by providing local material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408. (ii)Using Gravel mix soil.
APPENDIX 2- CONSTRUCTION OF EARATHUNJALIL ROAD- CIVIL WORKS
2.1.1 : Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil
16.42 : Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) in pavements, laid to required slope and camber in panels as required including consolidation finishing and tamping complete. Cement make: Use Malabar cement only as per Govt. direction and in case of non availabilty of Malabar cement use Ultra Tech, Dalmia, Ramco or eq. brand in the order of preference.
APPENDIX 3- CONSTRUCTION OF AARAMGOTTUKARA AMBALAM LINK ROAD
4.11.2 : Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place method normal. Construction of granular sub-base by providing local material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408. (ii)Using Gravel mix soil.
APPENDIX 3- CONSTRUCTION OF AARAMGOTTUKARA AMBALAM LINK ROAD- CIVIL WORKS
2.1.1 : Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil
16.42 : Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) in pavements, laid to required slope and camber in panels as required including consolidation finishing and tamping complete. Cement make: Use Malabar cement only as per Govt. direction and in case of non availabilty of Malabar cement use Ultra Tech, Dalmia, Ramco or eq. brand in the order of preference.
APPENDIX 4- CONSTRUCTION OF AYCHUVEEDU VADAKKE VELLIKUNNU ROAD
4.11.2 : Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place method normal. Construction of granular sub-base by providing local material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408. (ii)Using Gravel mix soil.
APPENDIX 4- CONSTRUCTION OF AYCHUVEEDU VADAKKE VELLIKUNNU ROAD-CIVIL WORKS
2.1.1 : Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil
16.42 : Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) in pavements, laid to required slope and camber in panels as required including consolidation finishing and tamping complete. Cement make: Use Malabar cement only as per Govt. direction and in case of non availabilty of Malabar cement use Ultra Tech, Dalmia, Ramco or eq. brand in the order of preference.
APPENDIX 5- CONSTRUCTION OF AMMATTI ETTONAM ROAD
4.11.2 : Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place method normal. Construction of granular sub-base by providing local material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408. (ii)Using Gravel mix soil.
APPENDIX 5- CONSTRUCTION OF AMMATTI ETTONAM ROAD- CIVIL WORKS
2.1.1 : Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil
16.42 : Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) in pavements, laid to required slope and camber in panels as required including consolidation finishing and tamping complete. Cement make: Use Malabar cement only as per Govt. direction and in case of non availabilty of Malabar cement use Ultra Tech, Dalmia, Ramco or eq. brand in the order of preference.
APPENDIX 6 -CONSTRUCTION OF KAIPENCHERY- ERADIYAM AMBALAM ROAD
4.1.A.2 : Granular Sub-base with Well Graded Material (Table 400.1)(A)By Mix in Place Method Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401.(ii) For Grading II Material.
4.9 : Wet Mix Macadam :Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406.By Mechanical Means with 1 km lead. (Quantity by level calculation )
5.1.1a : Prime Coat :-Low porosityProviding and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
5.2.2a : Tack Coat :Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
5.9.1.2a : 20mm thick Open-Graded Premix Carpet using Bituminous (penetration grade/modified bitumen) Binder - Bitumen S-65Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either Type A or Type B or Type C as per Technical Specification Clause 508.Case - I By Manual Means(II)Bitumen (S-65)
5.12.A.3.2a : Seal Coat - Manual Means - Type C - Bitumen S-65Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A, Type B and Type C as per Technical Specification Clause 510A.By Manual Means:-Case - III : Type C(II)Bitumen (S-65)
APPENDIX 6 - CONSTRUCTION OF KAIPENCHERY- ERADIYAM AMBALAM ROAD- CIVIL WORKS
2.1.1 : Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil
51.2.3 : Filling with Quarry Muck Filling up low lying and water logged areas with local material/ quarry muck, spreading in layers, leveling the top at site and consolidation by ramming, etc complete for improving the CBR value of subgrade
APPENDIX 1- CONSTRUCTION OF CHERAPPARAMBU SMASHANAM ROAD- SUPPLYING AND FIXING GRANITE NAME BOARD including lettering etc as per LSGD norms and direction of engineer in charge.
APPENDIX 2- CONSTRUCTION OF EARATHUNJALIL ROAD-SUPPLYING AND FIXING GRANITE NAME BOARD including lettering etc as per LSGD norms and direction of engineer in charge.
APPENDIX 3- CONSTRUCTION OF AARAMGOTTUKARA AMBALAM LINK ROAD-SUPPLYING AND FIXING GRANITE NAME BOARD including lettering etc as per LSGD norms and direction of engineer in charge.
APPENDIX 4- CONSTRUCTION OF AYCHUVEEDU VADAKKE VELLIKUNNU ROAD-SUPPLYING AND FIXING GRANITE NAME BOARD including lettering etc as per LSGD norms and direction of engineer in charge.
APPENDIX 5- CONSTRUCTION OF AMMATTI ETTONAM ROAD-SUPPLYING AND FIXING GRANITE NAME BOARD including lettering etc as per LSGD norms and direction of engineer in charge.
APPENDIX 6 -CONSTRUCTION OF KAIPENCHERY- ERADIYAM AMBALAM ROAD -SUPPLYING AND FIXING GRANITE NAME BOARD including lettering etc as per LSGD norms and direction of engineer in charge.
Note :1 All materials, Items, Equipment shall be best branded items with IS and approved by client/KEL
2:Rate should be inclusive of Insurance,Transportation, delivery and installation cost for all items
3.Rate should be Exclusive of GST.
4.Work should be executed as per DSR/PWD specification and direction of Engineer at site.
K.G. Somasundaran
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart shows the information on this page on a best-effort basis and does not guarantee that it is accurate, complete or current. Check it against the buyer's official notice and documents before you act on it; the official record prevails. TenderKart is not liable for any loss or claim arising from the use of this information. If you notice any error or omission, please let us know at .