Tender Value
₹12.3 L
EMD Value
₹14,522
Closing Date
17 Aug 2026, 6:00 pmClosed
The Chief officer Valsad Municipality valsad
BID DOCUMENTS FOR CONSTRUCTION WORK OF STORM WATER (BOX DRAIN) FROM NEAR HANUMAN MANDIR TO GANGLI KHADI JOINT MAIN GUTTER WARD NO-5 AT VALSAD NAGARPALIKA UNDER: VIKENDRIT JILLA AYOJAN YOJANA YEAR 2026-27
331964
VIKENDRIT JILLA AYOJAN YOJANA YEAR 2026 27
Open
Civil - All
Works
Valsad
14 documents required · 14 mandatory
₹1,062
The Chief Officer, Valsad Municipality, Valsad
₹14,522
6 Aug 2026
6 Aug 2026
6 Aug 2026
17 Aug 2026
6 Aug 2026
Item Qty. Description Total Unit Amount
1 109.50 Dismentaling tiled of stone floors laid in mortar including
Cmt stacking of sericeable materilas and disposal of unserviveable
materials with all lead and lift(REMOVING OLD GUTTER TOP
SLAB & BOTTAM SLAB ) 550.40 Cmt
2 Excavation for foundation in Loose or soft soil 1.5 mt. Depth
including sorting out and stacking of useful materials and
depositing of the excavated stuff for all the leads and lift etc.
complete as directed by Engineer-in-charge.
3 Extra for Dewatering for excavation in wet condition and in all
4 20.50 Providing and laying cement concrete 1:3:6 (1-Cement : 3-
Cmt. coarse sand : 6- hand broken stone aggregates 40 mmnominal
size) and curing complete excluding cost of formwork in (A)
Foundation and Plinth 3005.76 Cmt.
5 Providing and laying controlled cement concrete M-200 and
curing complete excluding the cost of formwork and
reinforcement of reinforced concrete work in.
a 20.25 -- do -- for R.C.C bottam slab 4491.32 Cmt.
b. 34.00 -- do -- for R.C.C Vertical Wall 4515.37 Cmt.
c. 25.00 -- do -- for R.C.C Top Slab/PRE-CAST SLAB 4491.32 Cmt.
6 7900.00 Providing TMT Bar FE 500D reinforcement for R.C.C. work
Kgs. including bending, binding and placing in position complete upto
floor two level 76.21 Kg.
SBD SECTION-7 BILL OF QUANTITIES-138
7 Providing Formwork of ordinary timber plankings so as to give a
rough finished including centering, shuttering, struting and
propping etc. height of propping and centering below supporting
floor to ceiling not exceeding 4.0 Mt. and removal of the same for
cast in situ reinforced concrete and plain concrete work.
a. 450.00 For Vertical Wall 235.43 Smt.
b. 108.50 For Slab 251.34 Smt.
I / We am/are willing to carry out the work at _____________ % above / below (percent should be written in figure and in words)
of the estimated rates mentioned above. Amount of my/our tender works out as under.
( In words ) _________________________ Percentage above / below the estimated rate.
Estimated Amount put to tender Rs.
Deduct _______ % below Rs. Rs.
Estimated Amount put to tender
Add _______ % above Rs. Rs.
Total Amount Rs.
Total Amount Rs.
*( Please strike out whichever is not applicable)
Note :1 All work shall be carried out as per Public Works Department Hand Book and other specifications of Division or as
Note :2 Rates quoted include clearance of site (prior commencement of work and its close) in all respects and hold good for
Note :3 I/ We have read the conditions mentioned in this tender and agree to abide by the same.
Note :4 18 % GST Will be paid separately by Valsad Nagarpalika.
Signature of Contractor President Chief Officer
Valsad Municipality Valsad Municipality
SBD SECTION-7 BILL OF QUANTITIES-139
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
BOQ.pdf
Notes.pdf
SBD.pdf
OTHER IMPORTANT-1.pdf
OTHER IMPORTANT-2.pdf
OTHER IMPORTANT-3.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].