Tender Value
₹109.1 Cr
EMD Value
₹15 L
Closing Date
13 Aug 2026, 4:00 pm
Additional Chief Engineer (P&C)
Supply, installation, testing & commissioning of conversion of (1) 66kV Jarod - Amliyara S/C line (2) 66kV Gotri - Vidyutnagar 1&2 D/C line (3) 66kV Karjan – Kashipura S/C line (4) 66kV Jambuva B - Dabhoi S/C line (5) 66kV Karjan - Gotri B Line-1 & 2 D/C line (Karjan & Gotri Juridiction) (6) 66kV Karjan - Gotri B 1 & 2 D/C lineTap to Atladara (tap portion) (7) 66kV Karjan - Gotri B Line-1 & 2 D/C line tap to Makarpura (tap portion including Vadsar LILO Portion) (8) 66kV Sankheda - Rustamura S/C line (9) 66kV Nandesari -Mogar-2-ND1 S/C line (10) 66kV Gorwa - Chhani A 1 & 2 D/C line (11) 66 kV Sama - Chhani A S/C line (12) 66 kV Amaliyara - Chhani A S/C line with ACSR DOG conductor into equivalent HTLS Conductor (Equivalent weight of ACSR DOG conductor with Higher Ampacity) of Jambuva Circle (Except Gap Type conductor)
326550
ACE(P&C)/Contracts/E-497/Uprating/66kV/S&E
Open
Electrical Works
Works
Vadodara
45 documents required · 37 mandatory · 8 optional
₹11,800
Gujarat Energy Transmission Corporation Limited
₹15 L
23 Jul 2026
23 Jul 2026
23 Jul 2026
13 Aug 2026
23 Jul 2026
General 23.1 (a) The estimated cost for of 23.1 (a) The estimated cost of Tender is
Conditions of Tender is more than Rs. 100 lacs, the more than Rs. 100 lacs, the EMD is
Contract/ EMD is payable as under: payable as under:
and its sub- 50 % of EMD by DD in favor of 50 % of EMD by DD in favor of
clauses Gujarat Energy Transmission Gujarat Energy Transmission
Corporation Ltd. on any Corporation Ltd. on any
Scheduled Bank in Vadodara Scheduled Bank in Vadodara and
and Balance 50 % by Bank Balance 50 % by Bank Guarantee
Guarantee from any from any Nationalized Bank in the
Nationalized Bank in the format provided herein.
format provided herein.
(b) The estimated cost of tender is less
(b) The estimated cost of tender is than Rs.100 Lacs, the EMD is payable as
less than Rs.100 Lacs, the EMD is under: -
payable as under: -
100 % of EMD by DD in favor of
100 % of EMD by DD in favor Gujarat Energy Transmission
of Gujarat Energy Corporation Ltd. on any
Transmission Corporation Ltd. Scheduled Bank in Vadodara.
on any Scheduled Bank in
(c) Payment by Cheque / Coop Bank
(c) Payment by Cheque / Coop Bank Guarantee/ Company Guarantee is not
Guarantee/ Company Guarantee is permissible.
not permissible.
(d) Validity Period: - The offer should be
(d) Validity Period: - The offer should valid for a minimum period of 180 days
be valid for a minimum period of 180 from the date of opening of Technical bid.
Seal & Signature of Bidder
days from the date of opening of (e) Payment of EMD will be accepted
Technical bid. by RTGS / NEFT / online or Demand
draft or Banker’s cheque or Pay order
-- or Bank Guarantee
23.2 The bid security is required to
23.2 The bid security is required to protect the owner against the risk of
protect the owner against the risk of Bidder’s conduct, which would warrant
Bidder’s conduct, which would the guarantee forfeiture, pursuant to
warrant the guarantee forfeiture, relevant paras elsewhere
pursuant to relevant paras elsewhere
The bid guarantee shall be made payable
The bid guarantee shall be made to the Owner without any condition
payable to the Owner without any whatsoever.
condition whatsoever.
23.3.1 Any bid not secured in
23.3.1 Any bid not secured in accordance with Para 23.1 above will be
accordance with Para 23.1 above will rejected by the Owner as non-
be rejected by the Owner as non- responsive. No exemptions are made in
responsive. No exemptions are made the furnishing of the security.
in the furnishing of the security.
23.3.2 Unsuccessful Bidder’s bid
23.3.2 Unsuccessful Bidder’s bid security/EMD will be returned/refunded
security/EMD will be
forthwith on finalization of tender i.e.,
returned/refunded on
finalization of tender or three once the award of contract, after opening
months-from the date of of price bids. However, the Bid Security/
submission of tender EMD of the bidder ranked next (L2) to the
whichever is later. bidder determined as the successful
bidder (L1) shall be retained by GETCO,
along with the Bid Security/ EMD of the
successful bidder. Bid Security/ EMD of
L2 bidder shall be returned immediately
after the Letter of Acceptance/ Award
(LOA) is issued by GETCO to the
successful bidder and acknowledged/
accepted by the successful bidder or the
Contract is signed with the successful
bidder, whichever event occurs earlier.
However, if there is a delay of 21 days or
more in aforesaid events reckoned from
the date of approval of award of contract
by the competent authority, as aforesaid,
the Bid Security/ EMD of the L2 bidder
shall be released immediately after the
said period of 21 days.
If the validity of the bid expires and any
bidder chooses not to extend the bid
validity, the Bid Security/ EMD of such
bidder shall be returned forthwith.
Seal & Signature of Bidder
23.3.3 The successful bidders, Bid 23.3.3 The successful bidders, Bid
Security will be discharged Security will be discharged upon,
upon, furnishing the contract furnishing the contract security deposit /
performance guarantee performance guarantee.
23.4 The bid guarantee may be 23.4 The bid guarantee may be forfeited.
a) If a Bidder withdraws its bid
a) If a Bidder withdraws its bid during the period of bid validity
during the period of bid validity specified by the bidder on the bid
specified by the bidder on the Form:
bid Form: b) If a bidder refuses to accept the
b) If a bidder refuses to accept contract or fails to commence the
the contract or fails to works (including supplies within
commence the works thirty days of letter of award of
(including supplies within thirty contract)
days of letter of award of
2. Part –I 86.0 Terms of Payment 86.0 Terms of Payment
General The payment for materials to be The payment for materials to be supplied
Conditions of supplied and erected shall be made and erected shall be made as under only
Contract/ as under only after execution of the after execution of the contract
Clause 86.0 contract documents/furnishing of documents/furnishing of Security Deposit
and its sub- Security Deposit and on execution of and on execution of transmission line
clauses transmission line work. work.
86.1 For supply
86.1 For Supply
86.1.1 Interest Bearing Advance
(i) Interest Bearing Advance
(Optional*): Ten percent (10%) of the
total Ex-works price component of
Tower / Tower Parts (including Bolts &
Nuts) and all other materials shall be
paid as an interest bearing initial
advance, at the rate of interest as per (ii)
below, after signing the Contract
Agreement and on submission of the
(a) Proforma invoice(s),
(b) Advance Bank Guarantee for [{110%
(one hundred ten percent) of the amount
of Advance}], from a Public Sector Indian
bank/Scheduled, Commercial Bank in the
form attached herewith as Annexure-i
(The guarantee shall be initially valid up
to 90 days after the Time of Completion
and shall be reduced at the end of every
Quarter prorata to the advance adjusted),
(c) Performance Securities in line with
GCC Clause 40.0 including its sub-
Seal & Signature of Bidder
Provided further that the Proforma
Invoice(s) for advance payment along
with all supporting documents is
submitted by the Contractor to the
Employer within 3 months from the date
of Letter/ Notification of Award. In case
the Contractor does not submit the
requisite documents including applicable
Bank Guarantee(s) /Security(ies) within
the aforesaid period, the advance shall
not be payable. The Contractor shall,
within 7 days from the date of receipt of
Advance, furnish an Advance Receipt
Voucher to the Employer, as prescribed
under the GST Law.
Note: * This payment is an optional
payment. The Contractor has the option
of taking the interest bearing initial
advance or otherwise. The option for
advance payment is to be indicated by
the bidder in its bid as per the format
attached herewith as Annexure–iii and
shall be deemed to be part of the bidding
scheduled referred as SCHEDULED-21
to be submitted by the bidder with
(ii) Interest rate applicable on advance
payment to the Contractor shall be at the
rate equal to one-year MCLR rate [One-
year Tenor rate p.a.] published by State
Bank of India prevailing as on the date of
drawl of advance. The said interest rate
shall remain fixed and shall be applicable
till the advance amount is fully repaid.
The interest will be charged considering
proportionate adjustment of advance
against progressive payment as per
86.1.2 below. The interest shall be
calculated on the daily progressive
balances outstanding as on the date of
recovery/adjustment. It is the Employer’s
understanding that as per extant
provisions, GST is not payable on
interest paid on the amount of Advance.
The Contractor is, however, advised to
check the position from their own
sources. If payable even at later stage,
the same shall be to the Contractor’s
account and Employer shall not
reimburse any GST on this account.
Recovery of this advance shall be
adjusted in such a way that that all the
sums of advance with interest thereon
Seal & Signature of Bidder
shall be fully recovered 3 months prior to
the scheduled Time of Completion, failing
which the whole amount of advance
along with interest thereon shall be
recovered immediately from the
payments due to the Contractor.
The contractor may however, return / pay
to GETCO the unadjusted advance
amount at any stage during the execution
of the work along with the accrued
interest thereon till the time of return /
payment. Alternatively, the contractor
may also request GETCO for early
adjustment of the advance along with
accrued interest.
Further, the Contractor shall submit the
certificate of Tax Deduction at Source
(TDS) on interest within 3 months from
the end of the quarter in which
adjustment of advance has been made
for claiming refund from Employer. No
claim for refund will be entertained after
end of the aforesaid period of 3 months.
Further, while submitting the TDS
Certificate the details of Contract No,
Project, Region, Quarter etc to which the
TDS certificate pertains, shall also be
submitted tallying the amount with the
TDS Certificate.
In case, the Contractor opts not to take
interest bearing advance as above, it
would be mandatory for him to submit the
documents listed at Sl. No. (i) (c) above
within twenty-eight (28) days of issuance
of Letter/ Notification of Award.
86.1.2 Progressive Payments
(i) 80% of supply value for each (i) (a) 70 % of supply value for fabricated
consignment of material on tower parts & stubs and 80% of supply
submission of invoice along with value for all other line material, hardware
100% GST, duties, F & I shall be paid and accessories etc. if contractor opts to
within 30 days from the actual take interest bearing initial advance or
material receipt date mentioned in SR
Note after verifying the following (b) 80% of supply value instead of 70% of
documents by field office and duly supply value for fabricated tower parts &
recorded. stubs and 90% of supply value instead
of 80% of supply value for all other line
A. Tax invoice. material, hardware and accessories etc.,
B. Delivery challan. if contractor opts not to take interest
C. Endorsed RR / LR copy.
Seal & Signature of Bidder
D. Dispatch clearance certificate / bearing initial advance or has opted to
letter wherever applicable. take interest bearing initial advance but
E. E Way Bill, if applicable the advance payment has become
inadmissible for each consignment of
material on submission of invoice along
with 100% GST, duties, F & I shall be
paid within 30 days from the actual
material receipt date mentioned in SR
Note after verifying the following
documents by field office and duly
A. Tax invoice.
B. Delivery challan.
C. Endorsed RR / LR copy.
D. Dispatch clearance certificate / letter
wherever applicable.
E. E Way Bill, if applicable
(ii) 10% payment out of balance 20% (ii) 10% of the of supply value for
of supply value shall be paid on fabricated tower parts & stubs shall be
completion of erection & testing of the paid progressively on completion of
transmission line and completion erection of complete tower (including tack
certificate from Engineer-in-charge welding and earthing) and furnishing of
and Chief Engineer (Procurement & completion certificate from Engineer-in-
Contracts)) or equivalent. charge and Chief Engineer (Projects).
(iii) Balance 10% of supply value shall (iii) Balance 10% of supply value shall be
be paid on successful commissioning paid on quarterly basis on erection
of transmission line against (including stringing) of transmission line
completion certificate and only after in stretches cumulatively not less than
settlement of material account 10% of original length of line in all
statement of items supplied, used, respects and rectification of
erected and successful defects/deficiencies of corresponding
commissioning is settled for complete stretch on progressive basis and on
lot and balance 10% will be release completion certificate from Engineer-in-
only after passing of final bill. No charge and Chief Engineer (Projects).
extra payment will be released for This payment shall be released on
the tower materials and line submission along with the invoice for first
materials which are not required for such payment, of an unconditional &
completion of line if supplied irrevocable Bank Guarantee of 10% of
excess during execution of work contract price of supply portion, initially
and recovery will be made in final valid till 3 months beyond the scheduled
bill accordingly. date of completion of testing &
commissioning of the transmission line
and its taking over by the GETCO and
shall be extended from time to time till the
actual date of successful completion of
testing & commissioning of line and its
taking over by the GETCO.
GETCO should accept the Tower and
line materials if excess as per
approved check survey only. No other
payment will be made and no other
material shall be accepted.
(iv) Welfare Cess
(iv) Welfare Cess
Seal & Signature of Bidder
The modality of payment/ The modality of payment/
reimbursement of welfare cess will be reimbursement of welfare cess will be
as under. as under.
On receipt of A/T, the contractor / On receipt of A/T, the contractor /
bidder will get them registered under bidder will get them registered under
Welfare Cess Act and submit the Welfare Cess Act and submit the
documentary evidence to the documentary evidence to the concern
concern office. office.
Before release of payment of first Before release of payment of first
R.A.Bill, the contractor has to submit R.A.Bill, the contractor has to submit
the documentary evidence of the documentary evidence of
registration. Only thereafter, the bill registration. Only thereafter, the bill will
will be processed for payment. be processed for payment.
Before release of payment of Before release of payment of
subsequent R.A.Bills, the contractor subsequent R.A.Bills, the contractor
has to submit the documentary has to submit the documentary
evidence of payment of welfare cess evidence of payment of welfare cess of
of previous R.A.Bill. previous R.A.Bill.
Before release of payment of Final Before release of payment of Final Bill,
Bill, the contractor has to submit the the contractor has to submit the
documentary evidence of payment documentary evidence of payment of
of welfare cess of previous R.A.Bill welfare cess of previous R.A.Bill as
as well as the final bill. well as the final bill.
If the R.A.Bill happens to be first and If the R.A.Bill happens to be first and
final bill, then before release of final bill, then before release of
payment, contractor has to submit payment, contractor has to submit
documentary evidence of documentary evidence of registration
registration under Welfare Cess Act under Welfare Cess Act and evidence
and evidence of payment of welfare of payment of welfare cess.
cess. The welfare cess shall be reimbursed
The welfare cess shall be to the contractor on submission of
reimbursed to the contractor on copy of documentary evidence of
submission of copy of payment by observing due
documentary evidence of payment formalities.
by observing due formalities.
86.2 For Erection works. 86.2 For Erection works.
86.2.1 A. Survey
Payment for survey shall be paid on pro-
rata basis on completion of survey and
approval of the same by the Employer.
86.2.1 B. Interest Bearing Initial
Advance (Optional ^^) Ten percent
(10%) at the rate of interest as per
86.2.1 B.1 1st Installment of 05% (Five)
of the total Installation price component
(excluding the price component for
survey) shall be paid on Establishment of
Contractor’s site offices, commencement
of stub setting work & certification by
Project Manager that satisfactory
Seal & Signature of Bidder
mobilization for erection exists and on
submission of the following:
(a) Proforma invoice,
(b) Advance Bank Guarantee for [{110%
(one hundred ten percent) of the amount
of Advance} Plus {amount of GST
reimbursable on Advance as per the
Proforma invoice}] from a Public Sector
Indian bank/Scheduled, Commercial
Bank in the form attached herewith as
Annexure-i (The guarantee shall be
initially valid up to 90 days after the Time
of Completion and shall be reduced at the
end of every Quarter prorata to the
advance adjusted),
(c) Performance Securities in line with
GCC Clause 40.0 including its sub-
86.2.1. B.2 2nd Installment of 05%
(Five)^^ of the total Installation price
component (excluding the price
component for survey) shall be paid on
commencement of stringing activities &
certification of the same by Project
Manager and on submission of the
(a) Proforma invoice(s),
(b) Advance Bank Guarantee for [{110%
(one hundred ten percent) of the amount
of Advance} Plus {amount of GST
reimbursable on Advance as per the
Proforma invoice}] from a Public Sector
Indian bank/Scheduled, Commercial
Bank in the form attached herewith as
Annexure-i (The guarantee shall be
initially valid up to 90 days after the Time
of Completion and shall be reduced at the
end of every Quarter prorata to the
advance adjusted),
(c) Performance Securities in line with
GCC Clause 40.0 including its sub-
Seal & Signature of Bidder
(d) A declaration by the Contractor
stating that 1st Installation (5%) of
advance has been utilized against the
mobilization works for the subject
Recovery of this advance shall be
adjusted in such a way that that all the
sums of advance with interest thereon
shall be fully recovered 3 months prior to
the scheduled Time of Completion, failing
which the whole amount of advance
along with interest thereon shall be
recovered immediately from the
payments due to the Contractor.
The contractor may however, return / pay
to GETCO the unadjusted advance
amount at any stage during the execution
of the work along with the accrued
interest thereon till the time of return /
payment. Alternatively, the contractor
may also request GETCO for early
adjustment of the advance along with
accrued interest.
Note: ^^ This payment is an optional
payment. The Contractor has the option
of taking the interest bearing advance or
otherwise. The option for advance
payment is to be indicated by the bidder
in its bid as per the format attached
herewith as Annexure–iii and shall be
deemed to be part of the bidding
scheduled referred as SCHEDULE-21 to
be submitted by the bidder with Technical
Note: After release of various advances,
the rate of recovery of the advance shall
be re-adjusted.
Provided further that the Proforma
Invoice(s) for advance payment along
with all supporting documents as per
para B.1 and B.2 above is submitted by
the Contractor to the Employer within
months from the date of fulfillment of the
requisite activities, as per the L2 network.
In case the Contractor does not submit
the requisite documents including
applicable Bank Guarantee(s)/
Seal & Signature of Bidder
Security(ies) within the aforesaid period,
the advance at B.1 & B.2 above shall not
The Contractor, shall, within 7 days from
the date of receipt of Advance, furnish an
Advance Receipt Voucher to the
Employer, as prescribed under the GST
86.2.1 B3. Interest rate applicable on
advance payment to the Contractor shall
be at the rate equal to one year MCLR
rate [One-year Tenor rate p.a.] published
by State Bank of India prevailing as on
the date of drawl of advance. The said
interest rate shall remain fixed and shall
be applicable till the advance amount is
fully repaid. The interest will be charged
considering proportionate adjustment of
advance against progressive payment for
the work done as per 86.2.2 below. The
interest shall be calculated on the daily
progressive balances outstanding as on
the date of recovery/adjustment. It is the
Employer’s understanding that as per
extant provisions, GST is not payable on
Interest paid on the amount of Advance.
The Contractor may, however, advised to
check the position from their own
sources. If payable, the same shall be to
the Contractor’s account and Employer
shall not reimburse any GST on this
Further, the Contractor shall submit the
certificate of Tax Deduction at Source
(TDS) on interest within 3 months from
the end of the quarter in which
adjustment of advance has been made
for claiming refund from Employer. No
claim for refund will be entertained after
end of the aforesaid period of 3 months.
Further, while submitting the TDS
Certificate the details of Contract No,
Project, etc to which the TDS certificate
pertains, shall also be submitted tallying
the amount with the TDS Certificate.
In case, the Contractor opts not to take
interest bearing advance as above, it
Seal & Signature of Bidder
would be mandatory for him to submit the
document listed at Sl. No. B1 (c) and,
B2(c) above within twenty-eight (28) days
of issuance of Letter / Notification of
(i) 90% payment of amount claimed 86.2.2 (i) (a) 70% payment if contractor
covering various activities such as opts to take interest bearing mobilization
excavation, foundation, tower advance or (b) 80% payment instead of
erection, earthing, tack welding 70% payment if contractor opts not to
stringing of conductor and OPGW take interest bearing mobilization
including insulator hoisting works
advance or has opted to take interest
against R.A. bills duly certified by EIC
within 30 days from the date of R.A. bearing initial mobilization advance but
bill. the advance payment has become
inadmissible, of amount claimed
covering various activities such as
excavation, foundation, tower erection,
earthing, tack welding stringing of
conductor and OPGW including insulator
hoisting works against R.A. bills duly
certified by EIC within 30 days from the
date of R.A. bill.
86.2.2 (ii) 10% of erection value shall be
(ii) 10% of erection value shall be paid
paid in three equal parts, each on
against commissioning of
transmission line only after settlement physical construction and erection of
of material account statement of items 33% of line work including stringing of the
supplied, used, erected and Transmission Line, complete in all
successful commissioning of respects, including rectification of
transmission line the same amount defects/deficiencies on the line and
will be release in final bill only and certificate from Engineer-in-charge and
payment will be made only after
Chief Engineer (Projects).
passing of final bill.
86.2.3. Balance 10% of erection value
shall be paid against commissioning of
transmission line only after settlement of
material account statement of items
supplied, used, erected and successful
commissioning of transmission line. The
same amount will be released in final bill
only and payment will be made only after
passing of final bill.
(iii) Payment of ROW compensation (iii) Deleted.
amount will be given as below only Note: ROW is now proposed to be in the
after submission of necessary scope of GETCO. Hence, this clause is
supporting documents. deleted.
1) 40% amount after completion
of foundation work
2) 40% amount after completion
of erection work
3) 20% amount after completion
of stringing work in all respects
Seal & Signature of Bidder
List of supporting documents:
1) Copy of form-7/12
2) Parishisht ‘A’ and ‘B’ of GoG
3) Document of Online Jantri
Rate of respective Survey No.
If online Jantri Rates are not
available, then land cost shall
be certified by competent
Revenue Authority.
4) Copy of APMC rate based on
which compensation is paid
towards damage of tree-crop
5) ‘Panchnama’ duly certified by
concern Sarpanch / Talati /
Mamlatdar or concern
Revenue Authority
6) Documents for the
compensation cost paid to
Govt. Trasurer as per GoG
Tharav for the line passing
through Govt. Waste Land. /
Govt. Organization.
(iv) Welfare Cess
(iv) Welfare Cess
The modality of payment/
The modality of payment/ reimbursement of welfare cess will be
reimbursement of welfare cess will as under.
On receipt of A/T, the contractor /
On receipt of A/T, the contractor / bidder will get them registered under
bidder will get them registered under Welfare Cess Act and submit the
Welfare Cess Act and submit the documentary evidence to the concern
documentary evidence to the office.
concern office. Before release of payment of first
Before release of payment of first R.A.Bill, the contractor has to submit
R.A.Bill, the contractor has to submit the documentary evidence of
the documentary evidence of registration. Only thereafter, the bill will
registration. Only thereafter, the bill be processed for payment.
will be processed for payment. Before release of payment of
Before release of payment of subsequent R.A.Bills, the contractor
subsequent R.A.Bills, the contractor has to submit the documentary
has to submit the documentary evidence of payment of welfare cess of
evidence of payment of welfare cess previous R.A.Bill.
of previous R.A.Bill. Before release of payment of Final Bill,
Before release of payment of Final the contractor has to submit the
Bill, the contractor has to submit the documentary evidence of payment of
documentary evidence of payment welfare cess of previous R.A.Bill as
of welfare cess of previous R.A.Bill well as the final bill.
as well as the final bill. If the R.A.Bill happens to be first and
If the R.A.Bill happens to be first final bill, then before release of
and final bill, then before release of payment, contractor has to submit
payment, contractor has to submit documentary evidence of registration
documentary evidence of under Welfare Cess Act and evidence
registration under Welfare Cess Act of payment of welfare cess.
Seal & Signature of Bidder
and evidence of payment of welfare The welfare cess shall be reimbursed
cess. to the contractor on submission of
The welfare cess shall be copy of documentary evidence of
reimbursed to the contractor on payment by observing due formalities.
submission of copy of documentary
evidence of payment by observing
due formalities.
3. Part –I 2.0 Tender Fee 2.0 Tender Fee
Special The tender fee plus GST as The tender fee plus GST as
Conditions of applicable specified in notice applicable specified in notice
Contract/ inviting tender is payable by inviting tender is payable by
Clause 2.0 Demand Draft (DD) at Demand Draft (DD) at Vadodara
Vadodara drawn on any drawn on any Scheduled Bank in
Scheduled Bank in favour of favour of Gujarat Energy
Gujarat Energy Transmission Transmission Corporation Ltd.
Corporation Ltd. The same will The same will be furnished in
be furnished in Cover-1 of Bid Cover-1 of Bid along with EMD
along with EMD (Bid Security). (Bid Security).
Payment of Tender fee
accepted by RTGS / NEFT /
5. Part –I 5.0 QUALIFYING REQUIREMENT a) QUALIFYING
(SCC)/ REQUIREMENT
Special [A] Technical Requirement:
Contract/ [A] Technical Requirement:
1.0 Individual Bidders
Clause 5.0 1.0 Individual Bidders
and its sub- a) The bidder shall be Original
clauses a) The bidder shall be Original
Equipment Manufacturer
(OEM). The offered high Equipment Manufacturer
ampacity conductor/HTLS (OEM). The offered high
conductor of equivalent size ampacity conductor/HTLS
and weight that of ACSR Dog conductor of equivalent
conductor suitable for size and weight that of
existing 66kV Towers & H-
ACSR Dog conductor
frame has to be designed,
suitable for existing 66kV
manufactured and tested as
per relevant IS/IEC/ANSI Towers & H-frame has to
with latest amendments. be designed, manufactured
and tested as per relevant
IS/IEC/ANSI with latest
b) The bidder shall have amendments.
supplied at least 100km of
high ampacity b) The bidder shall have
conductor/HTLS supplied at least 100 km of
conductor of equivalent proposed high ampacity
size and weight that of
conductor/HTLS conductor
ACSR Dog conductor or
of equivalent size and
above size during the last
weight that of ACSR Dog
conductor or above size
c) The bidder shall have
during the last five years.
carried out stringing of
Seal & Signature of Bidder
Route km of 66 kV & above
voltage class transmission c) The bidder shall have
line on towers in any single carried out stringing of
year during the last five Route km of 66kV & above
years. voltage class transmission
line on towers/H-Frame in
any single year during the
last five years. Sublet
experience also allowed
subject to provided Work
order/PO copy of original
contract and Sub-
contractor, experience
certificate from main
contractor and statement of
financial transaction for the
d) The proposed high
work order/PO are to be
ampacity conductor/HTLS
submitted to ascertain
conductor of equivalent
size and weight that of
experience of line erection
ACSR Dog conductor of work of 66KV and/or above
similar or higher ratings class.
must be in service for a
minimum period of one d) The proposed high
year at the time of bid ampacity conductor/HTLS
opening. Supporting conductor of equivalent
documents/Certificates of size and weight that of
original customer to be ACSR Dog conductor of
similar or higher ratings
must be in service for a
e) The bidder shall have in
house design and testing
minimum period of Two
facility years in India at the time of
bid opening. Supporting
f) The high ampacity documents/Certificates of
conductor/HTLS original customer to be
conductor of equivalent submitted.
size and weight that of
ACSR Dog conductor or e) The bidder shall have in
above size proposed to be house design and testing
supplied shall have valid
type test certificates from
any NABL accredited
laboratory (National
f) The high ampacity
accreditation body of the conductor/HTLS conductor
country where laboratory is of equivalent size and
located) not older than 7 weight that of ACSR Dog
years & must be valid till conductor or above size
the expiry of validity of proposed to be supplied
offer. shall have valid type test
Seal & Signature of Bidder
However, Successful bidder has to certificates from any NABL
carry out all the type test as per accredited laboratory
relevant standard for the offered (National accreditation
HTLS conductor without affecting body of the country where
delivery schedule.
laboratory is located) not
older than 10 years & must
g) For experience of
stringing, certificate issued
be valid till the expiry of
by the state transmission validity of offer considering
utilities/central on last date of submission
transmission utilities/joint of bid.
Venture Company of
Central utility / However, Successful bidder has
Transmission Licensee to carry out all the type test as per
from Private Sector of relevant standard for the offered
Indian Origin only shall be HTLS conductor without affecting
delivery schedule.
h) The bidder shall have valid
g) For experience of stringing,
Electrical Contract License
certificate issued by the state
and should have GST
transmission utilities/central
registration, PF
transmission utilities/joint
Registration Certificate.
Venture Company of Central
i) In case of bidder meet the utility / Transmission Licensee
above requirement at 1.0 from Private Sector of Indian
(d) but not supplied from Origin only shall be
Indian Manufacturing Unit, considered.
then the offered HTLS
conductor of equivalent h) The bidder shall have valid Electrical
size and weight that of Contract License and should have
ACSR DOG conductor GST registration, PF Registration
suitable for existing 66kV Certificate.
Towers & H Frame shall be
supplied from Indian i) In case of bidder meet the above
Manufacturing Unit only. requirement at 1.0 (d) but not
supplied from Indian Manufacturing
j) The bidder shall comply Unit, then the offered HTLS
the public procurement conductor of equivalent size and
guidelines of Government weight that of ACSR DOG conductor
of India dated 04.06.2020 suitable for existing 66kV Towers & H
and 23.07.2020. Frame shall be supplied from Indian
Manufacturing Unit only.
2.0 In case the bidder does not
meet technical experience j) The bidder shall comply the public
specified at 1.0 above at its procurement guidelines of
own, the bidder should Government of India dated
associate with firm(s) to form a 04.06.2020 and 23.07.2020.
JV/Consortium and the
JV/Consortium shall 2. In case the bidder does not meet
collectively meet the technical experience specified at
requirement as per 1.0 above. 1.0 above at its own, the bidder
Seal & Signature of Bidder
should associate with firm(s) to
3.0 However, in respect of supply
form a JV/Consortium and the
qualifications for supply
JV/Consortium shall collectively
requirement as per 1(b) & 1(d)
& 1(f), the Indian Licensee /
meet the requirement as per
Licensor arrangement is above.
permitted provided Licensor
meeting the requirement of 3. However, in respect of supply
1(b) ,1(d) & 1(f) stated herein qualifications for supply
above and shall also meet the requirement as per 1(b) & 1(d) &
following conditions; 1(f), the Indian Licensee / Licensor
I. Manufacturer / Licensee arrangement is permitted provided
shall have adequate design Licensor meeting the requirement
infrastructure and of 1(b) ,1(d) & 1(f) stated herein
manufacturing facility and above and shall also meet the
capacity and procedures following conditions;
including quality control.
I. Manufacturer / Licensee
II. A qualified Licensee of a shall have adequate design
qualified manufacturer / infrastructure and
Licensor shall comply with
manufacturing facility and
all the following
capacity and procedures
requirements and furnish a
Joint Undertaking by the
including quality control.
Licensor along with the II. A qualified Licensee of a
bidder in its bid as per the qualified manufacturer /
Performa enclosed at Licensor shall comply with all
the following requirements
a) Any design undertaken by the and furnish a Joint
Licensee shall be approved by the Undertaking by the Licensor
Licensor. along with the bidder in its bid
as per the Performa
b) Manufacturing by the Licensee
enclosed at ANNEXURE-I.
shall be done with the approval of a) Any design undertaken
the Licensor and Employer under by the Licensee shall be
a quality assurance programme approved by the
approved and monitored by the
b) Manufacturing by the
Licensee shall be done
with the approval of the
c) Licensee must furnish back-up Licensor and Employer
guarantee from the Licensor for under a quality
individual and overall performance assurance programme
of all materials supplied under the approved and monitored
contract. by the Licensor.
c) Licensee must furnish
back-up guarantee from
the Licensor for
individual and overall
Seal & Signature of Bidder
d) Licensor must guarantee performance of all
sequential and timely supply of materials supplied under
materials and submission of the contract.
technical information and data as
desired by the Employer so as to d) Licensor must guarantee
meet the overall construction sequential and timely
schedule and supply of materials and
submission of technical
information and data as
desired by the Employer
e) The agreement between Licensee so as to meet the overall
and Licensor (copy to be construction schedule
submitted along with the bid) shall and
be valid for a period of at least five
(5) years after the guarantee e) The agreement between
period of equipment and materials Licensee and Licensor
under supply is over. (copy to be submitted
along with the bid) shall
be valid for a period of at
least five (5) years after
4.0 Bidders under Manufacturer the guarantee period of
Authorization: - equipment and materials
under supply is over.
Bidders who are not OEMs are also
eligible to quote under manufacturer’s 4. Bidders under Manufacturer
authorization from Indian conductor Authorization: -
manufacturer who meets the
qualifying requirement as per 1.0 as Bidders who are not OEMs
above and the bidder shall satisfy are also eligible to quote
other requirement of 1.0. under manufacturer’s
authorization from Indian
It is also mandatory for such bidders
conductor manufacturer who
to provide the manufacturer’s
meets the qualifying
authorization as per attached
Annexure – I.A requirement as per 1.0 (a, b,
d, e, f, i & j) and the bidder
Bidders quoting under manufacture’s shall satisfy all other
authorization must have valid requirement as per clause
Electrical Contractor License, 1.0.
registered under GST Act and should
have PF Registration Certificate. It is also mandatory for such
bidders to provide the
manufacturer’s authorization
as per attached Annexure –
5.0 New bidders with
Bidders quoting under
proposed manufacturing
manufacture’s authorization
facilities in India:
must have valid Electrical
Contractor License,
registered under GST Act and
Seal & Signature of Bidder
New bidders with proposed should have PF Registration
manufacturing facilities in Certificate.
India shall be eligible to bid
provided the Technical criteria 5. New bidders with proposed
as per [A] 1.0 and financial manufacturing facilities in
criteria as per [B] are to be
fully met jointly with their
principal as under: -
New bidders with proposed
(i) It should be established manufacturing facilities in India
through authenticated shall be eligible to bid provided
documents like land, the Technical criteria as per [A]
Board of directors of the 1.0 and financial criteria as per
company, company [B] are to be fully met jointly
registration, collaboration with their principal as under: -
documents etc., that (i) It should be established
Indian unit is at the through authenticated
matured stage of documents like land, Board of
construction with required
directors of the company,
machinery. This will be
company registration,
verified by GETCO as a
part of technical bid collaboration documents etc,
evaluation prior to price that Indian unit is at the
bid opening. The decision matured stage of construction
of GETCO to qualify or with required machinery. This
not to qualify will be final will be verified by GETCO as a
and binding. part of technical bid evaluation
prior to price bid opening. The
(ii) 100% HTLS conductor decision of GETCO to qualify
offered by bidder shall be
or not to qualify will be final and
supplied from Indian
Manufacturing Unit only
(ii) 100% HTLS conductor
(iii) The new bidder shall carry offered by bidder shall be
out type test report as per supplied from Indian
technical specification Manufacturing Unit only.
before commencement of (iii) The new bidder shall carry
supply and without out type test report as per
affecting delivery technical specification before
schedule. commencement of supply and
without affecting delivery
[B] Financial Requirement
1. Minimum Annual Turnover (MAT)
for best three individual years [B] Financial Requirement
out of last five financial years
shall not be less than the 1. Bidder’s Minimum Average Annual
estimated cost. (For individual Turnover (MAAT) for best three
bidders) years out of last five financial years
shall not be less than the 50% of
2. Minimum Average Annual
Turnover (MAAT) of the estimated amount of this tender.
Seal & Signature of Bidder
consortium/ Joint Venture (JV) Minimum Average Annual
company added together for Turnover (MAAT) of the
best three individual years out of consortium/ Joint Venture (JV)
last five financial years shall not company added together for best
be less than the estimated cost.
three individual years out of last
However Minimum Average
five financial years shall not be
Annual Turnover (MAAT) for
best three individual years out of
less than the 50% of the estimated
last five financial years of the cost. However Minimum Average
lead partner shall be at least Annual Turnover (MAAT) for best
50% & for each other partners three individual years out of last
shall be at least 50 % of the five financial years of the lead
estimated cost. partner shall be at least 25% of the
estimated cost & for each other
3. If the bid is submitted for supply
partners shall be at least 17% of
portion under Licensee /
the estimated cost.
Licenser agreement, then the
financial criteria under [B] 2 is to
be satisfied considering Licenser Note: - For the purpose of arriving
as one of the JV partner at MAAT, revenue from operation
(Condition 3 (II) of [A] shall be shall be considered only excluding
applicable). non-recurring income / other
income / interest income etc.
4. Further, in case of the bid to be
furnish as a JV/Consortium 2. Last financial year liquid assets
partners then each should not be less than 20% of
JV/Consortium partners has to estimated amount of this tender.
furnish 5% of the overall tender Last financial year liquid asset of
cost towards the B.G. in addition the consortium/ Joint Venture (JV)
to the 10% of the Bank
company added together should
Guarantee to be submitted by
not be less than 20% of estimated
the lead partner (as security
deposit). The terms, conditions
amount of offered quantities as on
& validity of all such BG’s shall invitation of tender. However, last
be the same. financial year Liquid assets of the
lead partner shall be 10% of
5. Bidders quoting under estimated Cost as on invitation of
manufacture’s authorization will tender and for each other partners
have to furnish 5% of the overall shall be at least 7% of estimated
order value towards the B.G. in
cost as on invitation of tender.
addition to the 10% of the Bank
guarantee (as security deposit).
The terms, conditions & validity
Note: For the purpose of arriving at
of all such BG’s shall be the LA current assets less inventories
same. shall be considered.
6. New Bidders with proposed 3. Bidder’s/ all the partner of
manufacturing facilities in India consortium/joint venture net
will have to furnish 5% of the worth for last financial years
overall order value towards the should be positive.
B.G. in addition to the 10% of the
Bank guarantee (as security
Seal & Signature of Bidder
deposit). The terms, conditions Net worth means paid up share
& validity of all such BG’s shall capital, Share Application Money
be the same. pending allotment* and reserves#
less accumulated losses and
deferred expenditure to the extent
not written off.
# Reserves to be considered for
the purpose of net worth shall be
all reserves created out of the
profits and securities premium
account but shall not include
reserves created out of revaluation
of assets, write back of
depreciation and amalgamation
* Share application money pending
allotment will be considered only in
respect of share to be allotted.
4. The bidder / all the partner of
consortium/joint venture should not
have been referred to NCLT under
insolvency & bankruptcy code (IRP
has been appointed or liquidation
proceedings have been initiated
Bidder to evidence the meeting of
financial criteria shall submit:
(i) CA Certificate with valid UDIN
Number failing which certificate shall
not be considered for the purpose of
(ii) Audited balance sheet and profit
& loss account along with the
schedules referred therein and the
auditor’s Report for the preceding
five financial years, in line with one
of the following
(a) In case last financial year’s
closing date was within 6 months
prior to bid due date and audited
Balance Sheet and Profit & Loss
account of last financial year are not
available, bidder has the option to
submit the financial details of five
previous years immediately prior to
the last financial year. For example,
in case bid due date is up to 30th
Seal & Signature of Bidder
September and financial details of
immediate preceding financial years
(year ending 31st March of same
year) are not available, the financial
details of the five previous years
immediately prior to the last financial
year may be submitted.
(b) Otherwise it is compulsory to
submit the financial details of
immediate preceding five financial
Details as per qualifying requirement
to be uploaded along-with offer.
CA certificate to be attached
The owner may assess the capacity & for MAAT, Liquid Assets and
capability of the bidders, to Net-worth. (This is must).
successfully execute the scope of Under taking in respect of
work covered under the work with in reference to NCLT under
stipulated completion period. This Insolvency & Bankruptcy
assessment shall inter-alia include. Code. The undertaking is to be
furnish by the bidder in its bid
as per the format attached
1) Document verification
herewith as Annexure–iv and
2) Bidders work/manufacturing shall be deemed to be part of
facilities visit the bidding scheduled referred
as Annexure–4 to be
3) Manufacturing capacity, uploaded by the bidder with
details of work executed, QR bid.
Supply/Order executed details
works in hand, anticipated in
for offered items with name of
future & the balance capacity purchaser, date and location to
available for the present scope be mentioned.
Performance certificate for
satisfactory operation/working
4) Details of testing facilities, for period as per qualifying
manpower and financial requirement attached with
specification. (This is must for
resources getting the offer qualified)
5) Details of quality system in
6) Past experience &
7) Customer feed back
8) Banker’s feed back
Details as per qualifying requirement
to be submitted along-with offer, in a
separate cover.
Seal & Signature of Bidder
CA certificate to be attached for
MAT. (This is must)
Supply/Order executed details for
offered items with name of
purchaser, date and location to be
Performance certificate for
satisfactory operation/working for
period as per qualifying
requirement attached with
specification. (This is must for
getting the offer qualified)
4. Part –I 5.0 Additional Documents: 5.0 Additional Documents:
Special Apart from various documents to be Apart from various documents to be
Conditions of furnished along with the Bid as furnished along with the Bid as required
Contract/ required in the GCC and ECC, the in the GCC and ECC, the following
Clause 5.0 following documents/details are to be documents/details are to be furnished by
and its sub- furnished by the Bidder: the Bidder:
clauses 1. GST Registration No. and 1. GST Registration No. and date
date 2. Registration. No. under Shops &
2. Registration. No. under Establishment Act/ issuing
Shops & Establishment Act/ authority
issuing authority 3. Details of Partners/Directors of
3. Details of Partners/Directors the Firm/Company.
of the Firm/Company.
4. Experience Record and 4. Experience Record and details of
details of orders pending / orders pending / executed for
executed for various utilities various utilities
5. Last five years Audited 5. Last five years Audited Accounts
Accounts 6. Detail of Manufacturing/
6. Detail of Fabrication facilities along with list
Manufacturing/Fabrication of Testing Equipment calibrated
facilities along with list of up to date. The detail for the same
Testing Equipment may be submitted.
calibrated up to date. The 7. Factory Registration / License
detail for the same may be details
8. P.F registration
7. Factory Registration /
License details
8. Solvency certificate from
Bank (20 % of Bid value).
9. P.F registration
5. Part –I 10.0 PENALTY FOR DELAY: 10.0 LIQUIDATED DAMAGES (LD)
(SCC)/ FOR DELAY:
Conditions of 10.1 The tenderer should note that the 10.1 The tenderer should note that the
Contract/ completion time allowed for carrying completion time allowed for carrying out
Clause 10.0 out the work should be strictly the work should be strictly observed. Any
and its sub- observed. Any delay that may take
delay that may take place in achieving
clauses place in supply and erection beyond
Contractual cut-off date stated as per Completion of the works beyond
stipulated delivery period shall be Contractual Time of Completion in the
subject to the penalty at the rate of ½ Contract shall be subject to Liquidated
% of the contract value per week plus Damages (LD), and not by way of
Seal & Signature of Bidder
GST as applicable on delayed work penalty, at the rate of ½ % of the Contract
(supply and erection work) with a Price plus GST as applicable, per week
ceiling of 10% of the total contract or part thereof of the delay subject to a
value plus GST as applicable.
ceiling of 10% (ten percent) of the
Contract Price plus GST as applicable.
10.2 In event of failure of the 10.2 In cases where the Completion of
Contractor to pay the amount of the works/ along with supplies extend
Penalty as demanded, the Owner beyond the contractual completion
shall be entitled to deduct the period, without prejudice to any other
amount of Penalty for delay from
right that it may have under the Contract
the amounts payable to the
Contractors under any bills raised or in law, the Owner shall be entitled to
under this contract or any other deduct the amount of LD from the
amount payable under any other amounts payable to the Contractors
contract with the GUVNL and its under any bills raised under this
Subsidiary companies i.e. GETCO, Contract or any other amount payable
GUVNL, GSECL, MGVCL, DGVCL, under any other contract with the
PGVCL, UGCVL. It is permissible for
GUVNL and its Subsidiary companies
the Owner to adjust the amount of
Penalty of delay against any Bank i.e. GETCO, GUVNL, GSECL, MGVCL,
Guarantee furnished by the DGVCL, PGVCL, UGCVL. It is
Contractor under this contract or any permissible for the Owner to adjust the
other contract with GUVNL and/or its amount of LD against any Bank
subsidiary companies. Guarantee furnished by the Contractor
under this contract or any other contract
with GUVNL and/or its subsidiary
10.3 Tenderer shall have to supply 10.3 Notwithstanding the provision of
all materials to match with the erection
activities. Clause 10.2, if so requested by the
Contractor, amount from the RA bills,
pending settlement of Liquidated
Damages (LD), shall not be withheld/
retained by the Owner, if adequate
retention payment [over and above
security deposit/ Contract Performance
Guarantee (CPG)] remains to be
released as per Contract. In case, it is not
so, it shall be examined by the Owner
whether BGs/other securities (excluding
CPG/Security Deposit) furnished by the
Contractor are available with GETCO,
which have partly or fully served their
purpose, and can therefore be utilized by
GETCO to recover LD, if finally levied. If
available, it will be further checked
whether the contractor is willing to furnish
a suitable undertaking authorizing
GETCO to retain those BGs/security (for
such value which along with retention
payments remaining with GETCO is
considered to be sufficient to take care of
maximum leviable LD) to be kept valid till
Seal & Signature of Bidder
6 months beyond the anticipated
completion of the works/ supplies under
the Contract. If the Contractor requests
and gives the undertaking as above and
validity of BG is suitably extended
wherever required, amount from RA bills,
pending settlement of LD, shall not be
withheld/ retained on account of LD.
10.4 Tenderer shall have to supply all
materials to match with the erection
Seal & Signature of Bidder
BANK GUARANTEE FORM FOR ADVANCE PAYMENT
(For the purpose of verification/confirmation of this Bank Guarantee by the GETCO, the Bank
shall indicate 2 official email ids of the authorized signatories from Issuing Branch and also of
the designated higher office (Corporate Office, Zonal Office etc) in the covering letter of the Bank
forwarding the Bank Guarantee.)
Bank Guarantee No. …………………… Date...................
…………..[Name of Contract]…………………….
To: [Name and address of the Employer/ Owner]
Dear Ladies and/or Gentlemen,
We refer to the Contract ("the Contract") vide Letter of Award issued on ............ (insert date of the letter
of award)….by you (the Employer/ Owner) to M/s ................. (Name of Contractor) ..................,
signed on ..............(insert date of the Contract)…..... between you and M/s ................. (Name of
Contractor) ..................,
having its Principal place of business at ………....(Address of Contractor) ............................... and
Registered Office at ………....(Registered address of Contractor)
…….................….. (Indicate brief scope of work) ............................... for the complete execution of the
…… (insert name of Package along with name of the Project)……..
Whereas, in accordance with the terms of the said Contract, the Employer has agreed to pay or cause
to be paid to the Contractor an interest bearing Advance Payment against furnishing of an irrevocable
bank guarantee for an amount of ………………………..(Amount in figures and words) ……………which
is equal to [{110% (one hundred ten percent) of the amount of Advance} Plus {amount of GST
reimbursable on Advance as per the Proforma invoice, if applicable}].
By this letter we, the undersigned, ………(insert name & address of the issuing bank) ………, a Bank
(which expression shall include its successors, administrators, executors and assigns) organized under
the laws of .................................... and having its Registered/Head Office at …..…….(insert address of
registered office of the bank)……..... do hereby irrevocably guarantee repayment of ………….(Amount
of the bank guarantee in figures and words)…………… upon the first demand of the Employer without
cavil or argument in the event that the Contractor fails to commence or fulfill its obligations under the
terms of the said Contract for reasons whatsoever.
Provided always that the Bank's obligation shall be limited to the amount of this Bank guarantee or an
amount equal to the outstanding balance of the Advance Payment and the accrued interest on the
Advance Payment, taking into account such amounts, which have been repaid by the Contractor from
time to time in accordance with the terms of payment of the said Contract, as certified by you.
This Guarantee shall remain in full force from the date upon which the said Advance Payment is received
by the Contractor up to ninety (90) days beyond the date on which the entire Advance Payment along
with the accrued interest if any due thereon has been fully adjusted in terms of the Contract i.e., up to
ninety (90) days beyond the date of Completion of the Facilities under the Contract. This Guarantee may
be extended from time to time, as may be desired by M/s. ……………………….. on whose behalf this
Guarantee has been issued.
Seal & Signature of Bidder
Any claims to be made under this Guarantee must be received by the Bank during its period of validity,
i.e. upto ninety (90) days beyond the date of Completion of the Facilities by the Employer i.e. upto and
inclusive of ……………. (dd/mm/yy).
Notwithstanding anything contained herein:
1. Our liability under this Bank Guarantee shall not exceed _________ (value in
2. This Bank Guarantee shall be valid upto ________(validity date)__________.
3. We are liable to pay the guaranteed amount or any part thereof under this Bank Guarantee
only & only if we receive a written claim or demand on or before ________ (validity date)
For and on behalf of the Bank
[Signature of the authorised signatory(ies)]
Designation_______________________
Contact Number(s): Tel.______________Mobile______________
Common Seal of the Bank______________________
Contact Number(s): Tel.______________Mobile______________
1. For the purpose of executing the Bank Guarantee, the non-judicial stamp papers of appropriate
value shall be purchased in the name of Bank who issues the ‘Bank Guarantee’.
2. The Bank Guarantee shall be signed on all the pages by the Bank Authorities indicating their
POA nos. and should invariably be witnessed.
3. The Bank Guarantee should be in accordance with the proforma as provided. However, in
case the issuing bank insists for additional paragraph regarding applicability of ICC
publication No: 758, the following may be added at the end of the proforma of the Bank
Guarantee [i.e., end paragraph of the Bank Guarantee preceding the signature(s) of the
issuing authority(ies) of the Bank Guarantee]:
“This Guarantee is subject to Uniform Rules for Demand Guarantee, ICC publication No.
758 except that article 15(a) is hereby excluded.”
Seal & Signature of Bidder
Specification No: ACE(P&C)/Contracts/E-497/Uprating/66kV/S&E
Sub: Supply, Installation, Testing & Commissioning of conversion of (1) 66kV Jarod -
Amliyara S/C line (2) 66kV Gotri - Vidyutnagar 1&2 D/C line (3) 66kV Karjan – Kashipura
S/C line (4) 66kV Jambuva B - Dabhoi S/C line (5) 66kV Karjan - Gotri B Line-1 & 2 D/C line
(Karjan & Gotri Juridiction) (6) 66kV Karjan - Gotri B 1 & 2 D/C lineTap to Atladara (tap
portion) (7) 66kV Karjan - Gotri B Line-1 & 2 D/C line tap to Makarpura (tap portion
including Vadsar LILO Portion) (8) 66kV Sankheda - Rustamura S/C line (9) 66kV
Nandesari -Mogar-2-ND1 S/C line (10) 66kV Gorwa - Chhani A 1 & 2 D/C line (11) 66 kV
Sama - Chhani A S/C line (12) 66 kV Amaliyara - Chhani A S/C line with ACSR DOG
conductor into equivalent HTLS Conductor (Equivalent weight of ACSR DOG conductor
with Higher Ampacity) of Jambuva Circle(Except Gap Type conductor).
Option for Initial Advance (either Interest Bearing Initial Advance of No Initial Advance or No Initial
Addl. Chief Engineer (Procurement & Contracts)
Gujarat Energy Transmission Co. Ltd.,
Corporate office,
I. We have read the provision in the Bidding Documents regarding furnishing the option for
advance payment. Accordingly, as per clause GCC 86.1.1 (For Supply) and GCC 86.2.1 (b)
(For Erection) provided in Amendment-I of the Bidding Documents, we hereby confirm to opt
Interest Bearing Initial Advance:
Supply Portion: (Ref GCC 86.1.1) *
Erection Portion: (Ref GCC 86.2.1 (b)) *
* ‘Yes’ or ‘No’ to be filled up by the Bidder. ‘Yes” shall mean that Bidder has opted for the Interest
Bearing Advance and ‘No’ shall mean that Bidder has not opted for the Interest Bearing Advance.
If nothing is mentioned, it shall mean that Bidder has not opted for the Interest Bearing Advance.
(Name of Authorized Signatory of Bidder)
Seal & Signature of Bidder
Specification No: ACE(P&C)/Contracts/E-497/Uprating/66kV/S&E
Sub: Supply, Installation, Testing & Commissioning of conversion of (1) 66kV Jarod -
Amliyara S/C line (2) 66kV Gotri - Vidyutnagar 1&2 D/C line (3) 66kV Karjan – Kashipura
S/C line (4) 66kV Jambuva B - Dabhoi S/C line (5) 66kV Karjan - Gotri B Line-1 & 2 D/C line
(Karjan & Gotri Juridiction) (6) 66kV Karjan - Gotri B 1 & 2 D/C lineTap to Atladara (tap
portion) (7) 66kV Karjan - Gotri B Line-1 & 2 D/C line tap to Makarpura (tap portion
including Vadsar LILO Portion) (8) 66kV Sankheda - Rustamura S/C line (9) 66kV
Nandesari -Mogar-2-ND1 S/C line (10) 66kV Gorwa - Chhani A 1 & 2 D/C line (11) 66 kV
Sama - Chhani A S/C line (12) 66 kV Amaliyara - Chhani A S/C line with ACSR DOG
conductor into equivalent HTLS Conductor (Equivalent weight of ACSR DOG conductor
with Higher Ampacity) of Jambuva Circle(Except Gap Type conductor).
In connection with above subject, I / we confirm that our firm is not declared in NCLT under
Insolvency & Bankruptcy Code. Further, I / we also agree that, if any found NCLT under
Insolvency & Bankruptcy Code, the offer shall be out rightly rejected without assigning any
reason thereof.
Signature of Authorized
Representative of Company/Agency
Name of bidder Company
Seal & Signature of Bidder
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
8. EMD BG Format.pdf
2. Amendment -I Part-I Tender Specifications_JMB E-497.pdf
3. L2 Schedule E-497.pdf
5. PB Part-III Jambuva Circle E-497.pdf
6. R1_66KV_HTLS_specs.pdf
6.1 Addendum for core.pdf
7. Annexure I and IA.pdf
8. EMD BG Format.pdf
9. MAAT LA Networth Form.pdf
10. ONLINE SCHEDULE_TECH - E-497.pdf
11. Online Schedule-QR-E-497.pdf
12. Public Procurement Circular of GOI.pdf
13. Tower Schedule of 66KV Amaliyara-Jarod Line.pdf
14. Tower Schedule of 66kV Gotri - Vidyutnagar 1n2 line.pdf
15. Tower Schedule of 66kV Karjan - Kashipura line.pdf
16. Tower Schedule of 66kV Jambuva B-Dabhoi line.pdf
17. Tower Schedule of 66kV Amaliyara Chhani A line.pdf
18. Tower Schedule of 66kV Gotri-Karjan line MAIN PORTION.pdf
19. Tower Schedule of ATLADARA TAP PORTION 66kV Gotri-Karjan.pdf
20. Tower Schedule of 66KV Gotri-Karjan 1n2.pdf
21. Tower Schedule of 66kV Sankheda - Rustampura line.pdf
22. Tower Schedule of 66KV Nandesari-Mogar Line.pdf
23. Tower Schedule of 66kV Gorwa Chhani A line 1n2.pdf
24. Tower Schedule of 66KV Sama-Chhani A Line.pdf
25. SD cum PBG Format.pdf
26. Form of LD undertaking 1A.pdf
27. Form of LD undertaking 1B.pdf
4. Tender Notice E-497_Jambuva.pdf
1. Part-I Tender Spe. - Uprating of 66kV lines_JMB E-497.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].