| 1 | L1₹48.0 LAccepted-Finance UTTAR PRADESH | UNNAO | UTTAR PRADESH | 209869 | ₹48.0 L | L1 | Accepted-Finance Found L1 |
| 2 | L2₹49.2 LRejected-Finance JALIF NAGLA ISLAMNAGAR MILAK RAMPUR UTTAR PRADESH | RAMPUR | UTTAR PRADESH | 244701 | ₹49.2 L | L2 | Rejected-Finance Found L2 |
| 3 | L3₹51.2 LRejected-Finance UTTAR PRADESH | MIRZAPUR | UTTAR PRADESH | 231001 | ₹51.2 L | L3 | Rejected-Finance Found L3 |
Tender Value
₹52.4 L
EMD Value
₹4.6 L
Closing Date
30 Mar 2026, 12:00 pmClosed
SUPERINTENDING ENGINEER RAMPUR CIRCLE PWD RAMPUR
SUPERINTENDING ENGINEER RAMPUR CIRCLE PWD RAMPUR
Fazalpur Majra to the Shamshanghat Road
2026_CEMBD_1125662_2
1597/ETEN_RC/25_26_D_09_03_26
Open Tender
Civil Works - Roads
180 days
RAMPUR
New Construction Under Rajya Sadak Nidhi Scheme With Maintenance cost
2 documents required · 2 mandatory
₹2,354
₹4.6 L
Yes
SUPERINTENDING ENGINEER RAMPUR CIRCLE PWD RAMPUR
28 Apr 2026
23 Mar 2026
30 Mar 2026
23 Mar 2026
30 Mar 2026
23 Mar 2026
27 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 2Cement Treated Sub-Base Providing, laying and spreading Material on a prepared sub grade, adding cement @2% by weight to the spread Material manually, mixed in place with rotavator and comacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base. Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 3Cement Treated Base Providing, laying and spreading Material on a prepared sub base, cement @ 4% by weight to the spread Material manually, mixing in place with rotavator and compacting with the road roller at OMC to achieve the desired uncomfired compressive strength and to form a layer of base. Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 4Providing and applying tack coat with VG-10 using bitumen distributor at the rate of 0.30 kg per sqm on the prepared granular surfaces treated with primer/ Bituminous surface as per Technical Specification Clause 503. Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 5Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates using VG-10 to required line, grade and level to serve as wearing course on a previously prepared base by manual means, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades as per Technical Specification Clause 508 (By Manual Means) Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 6Providing and laying Type "C" seal coat by manual means with VG-10 sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall as per Technical Specification Clause 510 ( By Manual Means) Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 7Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 7.1 | As per Dom | - | Cum | - | - |
| 7.2 | Construction of 350 mm dia NP3 Goul pipe | - | RM | - | - |
| 8Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 m, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections. Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.25 MB
BOQ_2098525.xls
BOQ • 0.28 MB
2T2.pdf
Tender Documents • 0.45 MB
Download all tender documents and submit your bid