Tender Value
₹21.2 L
EMD Value
₹21,200
Closing Date
25 Sept 2026, 5:00 pm2d left
Superintending Engineer, MI Division Padampur
O/o The Superintending Engineer, MI Division Padampur Rajabodasambar Dist- Baragada
Improvement to BATTERMA MIP in Sohela Block of Bargarh District under CRITICAL grant for the Year 2026-27
2026_CEMIB_140865_5
SEMIDPDP_06_2026_27
Open Tender
Civil Works - Others
Percentage
120 days
Sohela Block
As per DTCN
2 documents required · 2 mandatory
₹6,000
₹21,200
Yes
11 Sept 2026
11 Sept 2026
28 Sept 2026
11 Sept 2026
25 Sept 2026
11 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Cleaning shurb jungle including uprooting stumps & small bushes and removal of rubbish up to a distance of 50m outside the periphery of the area. | 4,174 | One Sqm | 2.9 | ₹12,104.6 |
| 2 | Earthwork in Ordinary soil with initial lead of 50mtr and initial lift of 1.5m including rough dressing & breaking clods to maximum 5cm to 7 cm size & depositing the excavated materials in layers not exceeding 0.30mtr in depth etc complete and as directed by the Engineer-in-charge. | 336 | One Cum | 175.4 | ₹58,934.4 |
| 3 | Excavation, loading, unloading and carriage by mechanical means of all kind of soil including moorum. stoney earth, gravel etc. interspread with boulders up to 1/2 cum in size with all lifts and delifts including trimming of slopes and bed to design section and depositing the exca prials away from work site as per the specification and as directed by EIC within an initial lead of 1 km. from the place of excavation complete | 2,725.63 | One Cum | 81.9 | ₹2,23,229.1 |
| 4 | Excavation of foundation to proper profile in-all kinds of hard soil with all leads and lifts including dressing and leveling the bed to proper slope and level making it fit for laying concrete including depositing the excavated materials clear of work site with initial lead and lift of 50m & initial lift of 1.5m including dewatering from foundation if necessary complete as directed by the Engineer-in- charge. | 88.52 | One Cum | 282.9 | ₹25,042.31 |
| 5 | Earth work in hard soil within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and depositing the excavated material in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge. | 278.2 | One Cum | 235.7 | ₹65,571.74 |
| 6 | Cement concrete M15 grade with crushed granite coarse aggregate of 20 mm down graded mixed in concrete mixture including cost of all materials ,machineries and labouer with all lead for materials upto the mixing yard and transportation of mixed concrete within initial lead of 50m and laying in dams, barrages,power house and pen stock with all lift/delift upto 1.50m height above average ground level etc. complete in all respect to proper slope & level with all cost, conveyance, royalty & other taes of all materials complete in all respect as directed by the Engineer-in-charge. | 51.44 | One Cum | 5,687.92 | ₹2,92,586.6 |
| 7 | R.C.C. M20 grade with crushed granite coarse aggregate of 20 mm down graded mixed in concrete mixture including cost of all materials ,machineries and labouer with all lead for materials upto the mixing yard and transportation of mixed concrete within initial lead of 50m and laying in dams, barrages,power house and pen stock with all lift/delift upto 1.50m height above average ground level etc. complete in all respect to proper slope & level with all cost, conveyance, royalty & other taes of all materials complete in all respect as directed by the Engineer-in-charge. | 116.45 | One Cum | 6,190.2 | ₹7,20,848.79 |
| 8 | Straightening, cutting, bending, binding, and tying of HYSD steel rod of approved specification laying the grills as per approved design & placing in position including cost,conveyance and other taxes complete in all respect including all leads and lifts from bending yard to placement spot with supplying of labour and T&P required binding wire 18 to 20 gauge for the work etc complete as per drawing and technical specification.(Weight of binding wire will not be considered for payment purpose.) | 51.12 | One Qntl | 9,325.3 | ₹4,76,709.34 |
| 9 | Rigid smooth centering and shuttering for R.C.C works in foundation of all heights with wooden & steel shuttering plates including supply of ties supports rigidly fixed and removal including making good to the damaged surface where necessary with all scaffolding gangway etc. with cost, conveyance and other taxes of all materials including all labour and T&P materials required for the item complete in all respect as directed by the Engineer-in-charge. | 818.72 | One Sqm | 249.8 | ₹2,04,516.26 |
| 10 | Filling in foundation and plinth with excavated materials including watering and ramming as directed by the Engineer-in -charge. | 24 | One Cum | 157.2 | ₹3,772.8 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.87 MB
Tendernotice_2.pdf
PDF • 21.61 MB
BOQ_609418.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .