Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹60.7 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹67.6 L+₹6.9 L (11.4%)Rejected-Finance | L2 | Rejected-Finance Lowest Two | |
| 3 | L3₹70.5 L+₹9.8 L (16.1%)Rejected-Finance ASSAM RIFLES BAZAR NON CSD CANTEEN HAPPY VALLEY SHILLONG SHILLONG MEGHALAYA 793007 UDYAM ML 04 0000191 17AAJHS0378E3ZZ B R | EAST KHASI HILLS | MEGHALAYA | 793007 | L3 | Rejected-Finance Lowest Three | |
| 4 | L4₹72.5 L+₹11.8 L (19.5%)Rejected-Finance | L4 | Rejected-Finance Lowest Four |
Tender Value
₹77.2 L
EMD Value
₹1.5 L
Closing Date
6 Jun 2023, 12:00 pmClosed
COL ADM HQ IGAR EAST
HQ IGAR EAST SRIKONA
Provision of protective work incl retaining wall and adjacent road to landslide prone area uptill Bn Area 39 Assam Rifles at Srikona
2023_ARMHA_753662_1
VIII.11014/7668/39 AR Srikona/Engr/2023
Open Tender
Civil Works
Works
90 days
Srikona
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,500
COL ADM HQ IGAR EAST
₹1.5 L
HQ IGAR EAST SRIKONA
28 Jul 2023
17 May 2023
7 Jun 2023
17 May 2023
6 Jun 2023
18 May 2023
18 May 2023 - 24 May 2023
22 May 2023
Schedul "A" part -I (RCC Retaining wall 6.00M Height) Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.
M/L for PCC 1:3:6 (1 Cement : 3 coarse sand (zone-III): 6 graded stone aggregate 40 mm nominal size)
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering,shuttering, finishing and reinforcement - All work up to plinth level 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size)
Reinforced cement concrete work 1:1.5:3 Type A1 using 20 mm gd in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement
Centering and shuttering including strutting, propping etc. and removal of form for footings
Centering and shuttering including strutting, propping etc. and removal of form for RCC retaining wall
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete
S/F PVC (SWR) pipes 110 mm dia as in weep hole
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.
SCHEDULE "A" PART-II (RCC RETAINING WALL 4.00 M HEIGHT) Earth work in excavation by mechanical means (Hydraulic excavator) /manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m and getting out hard/dense soil
M/L for PCC 1:3:6 (1 Cement : 3 coarse sand (zone-III): 6 graded stone aggregate 40 mm nominal size)
Providing and laying in position specified grade of reinforced cement concrete, 1:1.5:3 Type A1 using 20 mm gd aggrgate excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :
Reinforced cement concrete work 1:1.5:3 Type A1 using 20 mm gd aggregate in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement
Centering and shuttering including strutting, propping etc. and removal of form for footings
Centering and shuttering including strutting, propping etc. and removal of form for RCC retaining wall
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete
S/F PVC (SWR) pipes 110 mm dia as in weep hole
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.
SCHEDULE "A' PART-III (HARD STANDING) Providing and laying 75 mm thick compacted bed of dry brick aggregate of 40 mm thick nominal size including spreading, well ramming, consolidating and grouting with jamuna sand, including finishing smooth etc. complete as per direction of Engineer-in-charge.
Providing and laying in position cement concrete 1:3:6 (1 Cement : 3 coarse sand (zone-III) : 6 graded stone aggregate 20 mm nominal size) excluding the cost of centering and shuttering - All work up to plinth level :
SCHEDULE "A' PART-IV (DRAIN 0.30M WIDE) Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m and getting out hard/ dense soil.
M/L for PCC 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size)
Brick work wih common burnt clay F.P.S. (non modular) briks of class designation 7.5 in fou8nsation and plinth in CM 1:6.
15 mm cement plaster on rough side of single or half brick wakk finisher with a floating coat of neat cement of mix CM 1:4.
SCHEDULE "A' PART-V (RCC ROAD) Providing and laying 75 mm thick compacted bed of dry brick aggregate of 40 mm thick nominal size including spreading, well ramming, consolidating and grouting with jamuna sand, including finishing smooth etc. complete as per direction of Engineer-in-charge.
Providing and laying in position specified grade of reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level
Centering and shuttering including strutting, propping etc. and removal of form for edges of hard standing
M/S B T ENGINEERS
Shree Meghalaya Construction & Supply Co.
M/S PARADISE ENTERPRISE
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .