| 1 | L1₹1.4 CrAccepted-AOC | ₹1.4 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹1.4 Cr+₹7.0 L (5.15%)Rejected-Finance | ₹1.4 Cr+₹7.0 L (5.15%) | L2 | Rejected-Finance Reject due to 2nd lowest. |
| 3 | L3₹1.6 Cr+₹23.0 L (16.9%)Rejected-Finance | ₹1.6 Cr+₹23.0 L (16.9%) | L3 | Rejected-Finance Reject due to 3rd lowest. |
| 4 | L4₹1.6 Cr+₹26.8 L (19.7%)Rejected-Finance | ₹1.6 Cr+₹26.8 L (19.7%) | L4 | Rejected-Finance Reject due to 4th lowest. |
Tender Value
Refer Docs
EMD Value
₹3.7 L
Closing Date
28 Dec 2018, 5:00 pmClosed
SUPERINTENDING ENGINEER, MURSHIDABAD CIRCLE,P.H.En
4 No C.R.Das Road (1sT fLOOR), Berhampore, Murshidabad,Pin-742101
PlanningDesignInvestigationConstructionErectionInstallationCompletiontestingandCommissioninginallrespectofentireunitsofArseniccumIronRemovalPlantAIRPJuranpurWaterSupplyScheme
2018_PHED_198606_4
WBPHED/SE/MC/NIeQ-04of18-19
Open Tender
CIVIL WORKS
Lump-sum
365 days
Juranpur
Please refer Tender documents.
11 documents required · 11 mandatory
₹3.7 L
Yes
16 May 2025
29 Nov 2018
31 Dec 2018
30 Nov 2018
28 Dec 2018
30 Nov 2018
Amount
Type-1: Fully Gravity system with RG filter. Construction of Arsenic –cum-Iron Elimination Plant to reduce Arsenic concentration to 10ppb (0.01mg/l) and iron to 100 ppb (0.10mg/l)from influent concentration upto 500ppb (0.5mg/l) and 3,000ppb (3.0mg/l) respectively (single/multistage) based on oxidation followed by chemical Co-operation , Filtration, Adsorption etc. and departmental process/hydraulic design consisting of Oxidation chamber with 30minutes detection time. Mechanical Flash Mixer ,Mechanised Clarifloculator, Rapid Gravity (RG) Filter, Up-flow/Down flow Gravitational type Activated Alumina polishing unit as per Type-I departmental process design and drawing modified Sujapur-Sadipur model (with 2year packing media) with pneumatic valves and control arrangements, conforming to specification of latest CPHEEO manual /B.I.S codes Solid-Liuid sludge Separation Bed with 100% recirculation facility including the cost of all accessories ,pumps(e.g. Sludge and recirculation pump) and RCC Sludge storage Tank etc. CWR with minimum 30minuts detention time. Chemical House with chemical feeding, arrangement (e.g metering pump, agitator etc.) oxidation by chlorination and post chlorination facility with all safety device ,gadget etc.) Back washing arrangement with air and water, back wash water tank of suitable capacity and staging height, air compressor, blower, necessary pipe connections etc. with integration of total plant all complete with trial run of a period of 3(three)months and after successful trial 9 (Nine) months operation and maintenance after completion of work (Excluding the cost of Chemicals and Electricity Charges),showing all necessary arrangements, structural & hydraulic detail based on departmental drawing but excluding the cost of pumping machinery (e.g raw water , clean water pumps).
J.D.J. ENTERPRISE
ACQUA CONSTRUCTION CONSORTIUM
ANJAN INFRASTRUCTURE PVT LTD
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .