| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.7 CrAccepted-AOC | ₹8.7 Cr | L1 | Accepted-AOC Being L1 |
| 2 | L2₹8.7 Cr+₹5.3 L (0.61%)Rejected-Finance | ₹8.7 Cr+₹5.3 L (0.61%) | L2 | Rejected-Finance Being L2 |
| 3 | L3₹8.8 Cr+₹16.0 L (1.84%)Rejected-Finance | ₹8.8 Cr+₹16.0 L (1.84%) | L3 | Rejected-Finance Being L3 |
| 4 | L4₹9.0 Cr+₹32.4 L (3.73%)Rejected-Finance | ₹9.0 Cr+₹32.4 L (3.73%) | L4 | Rejected-Finance Being L4 |
| 5 | L5₹10.2 Cr+₹1.5 Cr (17.3%)Rejected-Finance | ₹10.2 Cr+₹1.5 Cr (17.3%) | L5 | Rejected-Finance Being L5 |
Tender Value
₹10.0 Cr
EMD Value
₹20.1 L
Closing Date
31 Mar 2022, 6:00 pmClosed
AGM (Engg-Civil)
AGM (Engg-Civil), O/o the Airport Director, MBB Airport, Agartala
Construction of Perimeter wall at Khowai Airport Tripura
2022_AAI_107924_1
AAI/MBBA/CMD/ P.Wall(KHO) /21-22
Open Tender
Civil Works
Item Rate
240 days
Khowai Airport
Please refer Tender documents.
16 documents required · 16 mandatory
₹3,540
₹20.1 L
Yes
4 Jul 2022
4 Mar 2022
8 Apr 2022
4 Mar 2022
31 Mar 2022
15 Mar 2022
4 Mar 2022 - 10 Mar 2022
Amount
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge. (a) All kinds of soil
Extra rates for quantities of works, executed: In or under water and/or liquid mud, including pumping out water as required
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.
Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete
Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials. All kinds of soil
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : (a) 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : (a)1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size)
Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing: (a) 1:3:6 (1 cement : 3 coarse sand (zone-III) : 6 graded stone aggregate 20 mm nominal size)
Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-in-charge. (Note :- Cement content considered in this item is @ 330 kg/cum. Excess/ less cement used as per design mix is payable/recoverable separately). (a) All works upto plinth level
Centering and shuttering including strutting, propping etc. and removal of form for all heights : (a) Foundations, footings, bases of columns, etc. for mass concrete
Centering and shuttering including strutting, propping etc. and removal of form for : (a) Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
Centering and shuttering including strutting, propping etc. and removal of form for all heights : (a) Lintels, beams, plinth beams, girders, bressumers and cantilevers
Centering and shuttering including strutting, propping etc. and removal of form for all heights : (a)Columns, Pillars, Piers, Abutments, Posts and Struts
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. (a) Thermo Mechanically Treated bars of grade Fe-500D or more.
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level. (a) Thermo-Mechanically Treated bars of grade Fe-500D or more.
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in: (a) Cement mortar 1:6 (1 cement : 6 coarse sand)
Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.
12 mm cement plaster of mix :(a) 1:6 (1 cement: 6 fine sand)
15 mm cement plaster on the rough side of single or half brick wall of mix : (a) 1:6 (1 cement: 6 fine sand)
Finishing walls with water proofing cement paint of required shade : (a) New work (Two or more coats applied @ 3.84 kg/10 sqm)
Painting with synthetic enamel paint of approved brand and manufacture to give an even shade : (a) Two or more coats on new work
Making AAI logo of height 450 mm with cement plaster by using cement mortar 1:4 (1 cement: 4 fine sand) projecting out by 12 mm thick on newly plastered surface of boundary wall and painted the same with blue color synthetic enamel paint of approved brand & manufacturer to give an even shade using cutting stencil of acrylic sheet of 12 mm as per drawing and direction of Engg. - in - charge. Note: Other dimensions shall be worked in accordance with drawing.
Proving and applying / painting warning instruction of 'TRESPASSING AND PHOTOGRAPHING PROHIBITED' letter height 100mm (in bold arial font) on AAI perimeter boundary walls with synthetic enamel paint of approved brand and maufacture of required color to give an even shade using cutting stencil aluminium 16 guage thick material , all complete as per drawing and direction of Engineer-in- charge.
Carrying out soil investigation with all relevant tests as per the speciification attached in the tender document for boundary wall work to ascertain the requisite datas for structural design. The relevent tests shall be carried out through the specialized agency as enlisted by AAI or as approved by Engineer-in-charge. The test report shall be submitted to Engineer-in-charge for carrying out the structural design through AAI's Structural Directorate. The spacing of the bore holes for Boundary wall work shall also be kept as 500m..
Providing and submitting the preliminary drawings, carrying out structural design, preparation of detailed structural drawing and developing working architectural drawings of RCC strcuture as per site requirement. The structural design and drawings shall be got vetted by IIT/NIT. The design and drawing so submitted shall be got approved by Engineer-in-charge before execution of work. After approval of structural design and drawing by AAI 5(five) set of Good for Construction" design and drawings showing all relevant details shall be submitted duly signed by the consultant. Consultant shall also submit any other details required relevant to the scope and completion of work.
TAPAN SAHA
DEBASIS BHATTACHARYYA
Uttam Deb
Vishal Builders
L K BUILDERS
KISHORE ROY
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
93628408.html
Tender Document • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .