Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.5 LAccepted-AOC | L1 | Accepted-AOC The rate quoted by BAIJU ROUTH, stands lowest and acceptable hence accepted | |
| 2 | L2₹1.5 L+₹1,664.59 (1.11%)Rejected-Finance | L2 | Rejected-Finance Not lowest | |
| 3 | L3₹1.5 L+₹3,164.22 (2.11%)Rejected-Finance | L3 | Rejected-Finance Not lowest |
Tender Value
₹1.5 L
EMD Value
₹2,999
Closing Date
2 Feb 2026, 3:00 pmClosed
CHAIRMAN MAL MUNICIPALITY
CHAIRMAN MAL MUNICIPALITY
ICDS CENTER UPGRADING ROOF TRUSS REPAIRING and NEW TRUSS INSTALLATION and PLUSTER REPAIRING, Ward - 2, AC-20 (Mal), Booth 116(Mal Adarsha Vidya Bhaban Room 3), Project(s) Id. No-APAS/01/020/116/0001, Source of Fund APAS Fund. (2nd Call)
2026_MAD_993887_11
MM/C/APAS/12/2025-26
Open Tender
CIVIL WORKS
Percentage
30 days
MAL MUNICIPALITY
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹2,999
Yes
12 May 2026
26 Jan 2026
4 Feb 2026
26 Jan 2026
2 Feb 2026
26 Jan 2026
Dismentling all types of plain cement concrete works, stacking serviceable materials at site and removing rubish as directed within a lead of 75m. In ground floor including roof. b) above 150mm thick
Dismentling all types of plain cement concrete works, stacking serviceable materials at site and removing rubish as directed within a lead of 75m. In ground floor including roof. b) above 150mm thick
Cement Concrete with 30 mm down graded shingles excluding shuttering N.B. Variety, In Ground Floor. a) 1:3:6 Proportion.
Hire & Labour charges for shuttering with centering and necessary staging upto 4 mt.using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs,beams and columns,lintels curved or straight including fitting,fixing and striking out after completion of works. (a)25mm to 30mm thick wooden shuttering as per decision & directionof Engineer-In-Charge.
f) 25mm.to 30mm.shuttering without staging in foundation.
Supplying and laying Polythene Sheet (150gm/sq.m.) over damp proof course or below flooring or roof terracing or in foundation trenches.
Filling in foundationorplinthby silver sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand.
Plaster (to wall, floor,ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (ground floor).(i) With 1:6 cement mortar, (b) 20mm thick plaster.
(c) 15 mm thick plaster
Neat cement punning about 1.5mm thick in wall,dado,window sills, floor etc. (NOTE: Cement 0.152 cu.m per 100 sq.m).
Acrylic Distemper to interior wall,ceiling with a coat of solvent based interior grade acrylic primer (as per manufacturer's specification) including cleaning and smoothning of surface.Two Coats
Ordinary Cement Concrete (Mix 1:1.5:3) with graded stone chips(20mm nominal size) excluding shuttering and reinforcement if any,In G.F. As per relevant I.S.Codes. (i) River Bazree (N.B. Variety).
Brick work with 1st class bricks in cement mortar (1:6) (b) In superstructure, ground floor
125mm. thickbrickworkwith1st class bricks incementmortar (1:4) in ground floor.
Reinforcement for reinforced concrete work in all sorts of structures including distribution bars,stirrups,binders etc.intial straightening and removal of loose rust(if necessary) cutting to requisite length,hooking and bending to correct shape,placing in proper position and binding with 16 gauge black annealed wire at every intersection,complete as per drawing and direction.a) For works in foundation,basement and upto roof of ground floor/4mt.i)Tor Steel/Mild Steel. (II) Other than SAIL/TATA/RINL.
Woodwork in door andwindow frame fitted and fixed in position complete including a protective coat of painting at the contact surface of the frame exluding cost of concrete,Iron Butt Hinges and M.S clamps. (c) Sal : Siliguri. (i) In Ground Floor
Supplying, fitting and fixing M.S.clamps for door and window frame made of flat bentbar, end bifurcated with necessary screws etc.by cement concrete (1:2:4) as per direction. (c) 40mm X 6mm, 125mm Length
M.S. structural works with hollow sections (square or rectangular shape) conforming to IS: 806-1968 & IS:1161-1998) connected to one another with bracket, gusset, cleat as per design, drawing & direction of Engineer-in-Charge complete including cutting to requisite shape & size, fabrication including metal arc welding conforming to IS: 816-1969 & IS: 9595 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. i) For roof truss works a) Span up to 12 Mtr In Ground Floor
Supplying, fitting & fixing Zn-Al alloy (55% Al & 45% Zn) coating of 150 grams per sq. metre (followed by colour coated on both side) steel sheet work having minimum yield strengthof 550 Mpa of trapizoidal profile of approved make(excluding the supporting frame work) fittd and fixed with 55mm & 25mm self tapping screw, EPDM Washer 16mmdia & 3mmth.washer etc. complete with150mm end lap and one corrugation minimum side lap. (i) In Roof:- a) With 0.5 mm thick sheet
Galvanised iron sheet ridging fittedwith necessary bolts, screws, washers etc complete.(225mm end lapping) (B) 450 mm lapping each way (a) With 0.60 mm sheet
Add GST @18%
Add Labour Welfare Cess @1%
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.02 MB
Tendernotice_2.pdf
PDF • 0.34 MB
Tendernotice_3.pdf
PDF • 0.26 MB
BOQ_2431484.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .