Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹47.5 LAccepted-Finance NO 3 MEENATCHIPURAM THIRUPPATHURAI PERUGAMANI TRICHY 639115 | TIRUCHIRAPPALLI | TAMIL NADU | 639115 | ₹47.5 L | L1 | Accepted-Finance Quoted L1 Rate |
| 2 | L2₹48.1 LRejected-Finance | ₹48.1 L | L2 | Rejected-Finance Quoted L2 Rate |
| 3 | L3₹51.0 LRejected-Finance 184 KEELA STREET NEIKULAM NEDUNGUR LALGUDI 621105 | TIRUCHIRAPPALLI | TAMIL NADU | 621105 | ₹51.0 L | L3 | Rejected-Finance Quoted L3 Rate |
| Sl No | Description | Qty | Unit | SRE BALAJI AND CO L2 | ASV CONSTRUCTION L3 | KALINGA CONSTRUCTIONS L1 |
|---|---|---|---|---|---|---|
| 1.00 | Strengthening the Kodiyalam Alangulam road in Kodiyalam Panchayat in Andhanallur Block km 0/0- 1/350 .Clearing the light jungle including al labour charges for cutting, burring, buried etc. complete. | 972 | Sqm | 10 ₹9,720 | 6.5 ₹6,318 | 5.94 ₹5,773.68 Lowest |
| 2.00 | Picking the existing mettaled surface and sectioning including all labour charges etc, complete. | 1,350 | Cum | 30 ₹40,500 | 25 ₹33,750 | 21.84 ₹29,484 Lowest |
| 3.00 | Collection and supply and laying of U.S.gravel including cost and conveyance of all materials and all labour charges etc. complete.Km 0/0-1/0 | 60 | Cum | 500 ₹30,000 | 500 ₹30,000 | 482.53 ₹28,951.8 Lowest |
| 4.00 | Km 1/0-1/350 | 21 | Cum | 500 ₹10,500 | 550 ₹11,550 | 494.23 ₹10,378.83 Lowest |
| 5.00 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in Subbase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. | 607.5 | Cum | 2,600 ₹15,79,500 | 2,800 ₹17,01,000 | 2,585.81 ₹15,70,879.58 Lowest |
| 6.00 | Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. | 4,050 | Sqm | 90 ₹3,64,500 | 100 ₹4,05,000 | 83.46 ₹3,38,013 Lowest |
| 7.00 | Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Complete | 4,050 | Sqm | 20 ₹81,000 | 30 ₹1,21,500 | 19.5 ₹78,975 Lowest |
| 8.00 | BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5 | 121.5 | Sqm | 12,100 ₹14,70,150 | 12,500 ₹15,18,750 | 12,065 ₹14,65,897.5 Lowest |
| 9.00 | Supplying and fixing Hecta Metre stones including painting and lettering as directed by the departmental officers etc., complete | 8 | no | 800 ₹6,400 | 820 ₹6,560 | 780 ₹6,240 Lowest |
| 10.00 | Supplying and fixing Kilo Metre stones including painting and lettering as directed by the departmental officers etc., complete | 1 | no | 2,800 ₹2,800 | 3,000 ₹3,000 | 2,730 ₹2,730 Lowest |
Tender Value
₹51.3 L
EMD Value
₹52,000
Closing Date
2 Jul 2025, 3:00 pmClosed
Project Director
DRDA Tiruchirappalli
Strengthening the Kodiyalam Alagalam road in Kodiyalam Panchayat,Andhanallur Block,Tiruchirappalli District,under NABARD XXXI 2025-26pkg1
2025_RDTN_567880_1
DIPR/2866/Tender/2025 dt 06.06.2025
Open Tender
Civil Works - Roads
Item Wise
180 days
Tiruchirappalli
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹52,000
DRDA Tiruchirappalli
28 Jul 2026
12 Jun 2025
2 Jul 2025
12 Jun 2025
2 Jul 2025
12 Jun 2025
17 Jun 2025
Amount
Strengthening the Kodiyalam Alangulam road in Kodiyalam Panchayat in Andhanallur Block km 0/0- 1/350 .Clearing the light jungle including al labour charges for cutting, burring, buried etc. complete.
Picking the existing mettaled surface and sectioning including all labour charges etc, complete.
Collection and supply and laying of U.S.gravel including cost and conveyance of all materials and all labour charges etc. complete.Km 0/0-1/0
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in Subbase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Complete
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Supplying and fixing Hecta Metre stones including painting and lettering as directed by the departmental officers etc., complete
Supplying and fixing Kilo Metre stones including painting and lettering as directed by the departmental officers etc., complete
Providing and erecting of Retro - Reflectorised Cautionary, Mandatory and informatory signs (without definition board) including all charges etc.,60cm Equilateral triangle cautionary signboard
Providing and erecting of Retro - Reflectorised Cautionary, Mandatory and informatory signs (without definition board) including all charges etc 60cm circle mandatory signboard
Providing and erecting of Retro - Reflectorised Cautionary, Mandatory and informatory signs (without definition board) including all charges etc 90cm shevron signboard
Towards the charges for routline maintenance of the road work executed under NABARD XXX including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP- 20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
SRE BALAJI AND CO (BID ID -1379916)
ASV CONSTRUCTION (BID ID -1379343)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].