| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹20.0 LAccepted-AOC | L1 | Accepted-AOC Committee Approved Lowest 1 | |
| 2 | L2₹28.6 L+₹8.6 L (43.1%)Rejected-AOC | L2 | Rejected-AOC LOWEST 2 |
Tender Value
₹22 L
EMD Value
₹22,000
Closing Date
7 Dec 2023, 3:00 pmClosed
SE EUDC
35-B RAMPUR GARDEN BAREILLY
ELECTRICAL WORK UNDER EUDD-I BAREILLY
2023_MVVNL_865393_1
T-97/EUDCB/2023-24
Open Tender
Electrical Works
Item Rate
60 days
EE EUDD-I BAREILLY
AS PER TENDER FORM
3 documents required · 3 mandatory
₹3,540
SE EUDC
₹22,000
3 May 2024
25 Nov 2023
7 Dec 2023
25 Nov 2023
7 Dec 2023
25 Nov 2023
Amount
For the work of Up gradation High Loss LT Conductor in various areas’ under EUDD-I, Bareilly , for system strengthening for providing uninterrupted 24*7 power supply under the head of ( ADD. B.P. 2023-2024)
Carriage of following materials from E.S.CS store C.B Ganj to work site including loading & unloading
AB Cable (3x120 sqmm)
Distribution BOX 03 Phase
Other Line Materials.
Errection work
Sagging & Stringing of AB Cable (3x120 sqmm).
Erection of 03 Phase Distribution box with 02 nos. clamps along with making all connections
Fixing of associated Items i.e. LT Clamps-102 No. Shekel Insulator- 102 Nos.
Providing & Fixing of Perching Connector
Providing & Fixing of PG Clamps
For the work of additional LT Circuit in the different areas under EUDD-I, Bareilly for system strengthening for providing uninterrupted 24*7 power supply under the head of ( ADD. B.P. 2023-2024)
Carriage of following materials from E.S.CS store C.B Ganj to work site including loading & unloading
AB Cable (3x120 sqmm)
Distribution BOX 03 Phase
Other Line Materials.
Errection work
Sagging & Stringing of AB Cable (3x120 sqmm).
Erection of 03 Phase Distribution box with 02 nos. clamps along with making all connections
Fixing of associated Items i.e. LT Clamps-290 No. Shekel Insulator- 290 Nos.
Providing & Fixing of Perching Connector
Providing & Fixing of PG Clamps
Providing & Fixing of Nut & Bots for shekel Insulator
For the work of addition of new Poles in Long Span in LT Lines in the different areas under EUDD-I, Bareilly for system strengthening for providing uninterrupted 24*7 power supply under the head of ( ADD. B.P. 2023-2024)
Safe Carriage of following materials from E.S.CS store C.B Ganj to work site including loading & unloading .
ST Pole (09 Meter Long)
Distribution BOX 03 Phase
Other Line Materials
Errection work
Erection of ST D/ Pole including digging of pit & grouting work complete and fitting of all accessories complete.
Earthing of Pole by MS Earthing rod (20x2500mm) and 6 swg earthing wire.
Erection of 03 Phase Distribution box with 02 nos. clamps along with making all connections
Fixing of associated Items i.e. LT Clamps-225 No. Shekel Insulator- 225 Nos.
Providing & Fixing of Perching Connector
Providing & Fixing of PG Clamps
Providing & Fixing of Nut & Bots for shekel Insulator
Providing & Fixing of Stone PAD
TYCOON ENGINEERS
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .