Loading…
Loading…
Tender Value
₹2.4 Cr
EMD Value
₹4.8 L
Closing Date
13 Apr 2026, 3:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
Above/Below/Par
SIGNAL
16 conditions · 4 needing a document upload
Financial Eligibility Criteria: The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where: V= Advertised value of the tender in Crores of Rupees. N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover.
The Tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: 1Three similar works each costing not less than the amount equal to 30% of advertised value of the tender OR 2Two similar works each costing not less than the amount equal to 40% of advertised value of the tender OR 3One similar work costing not less than the amount equal to 60% of advertised value of the tender
UPLOADING OF THE CERTIFICATE:-The tenderers shall submit a copy of certificate stating that all their statements/documents submitted along with bid are true and factual. Standard format of certificate to be submitted by the bidder is enclosed as Annexure-V. In addition to Annexure-V, in case of other than Company/Proprietary firm. Annexure- V(A) shall also be submitted by the each member of a Partnership Firm/ Joint Venture (JV) / Hindu Undivided Family (HUF / Limited Liability Partnership (LLP)etc., as the case may be. Non submission of above certificate(s) by the bidder shall result in summarily rejection of his/their bid. It shall be mandatorily incumbent upon the tenderer to identify, state and submit the supporting documents duly self-attested/digitally signed by which they/he is qualifying the Qualifying Criteria mentioned in the Tender Document.
DEFINATION OF SIMILIAR NATURE OF WORK:-Any Signaling work of 1.1.1 EI/PI/RRI/IBH/ABH/LC gate interlocking/Track circuit works/Axle counter works etc
8 conditions · 2 needing a document upload
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
All payment and other conditions are attached with tender document.
Although year of specification is given in the schedule, last amendment, if any, shall apply.
All tenderer must have valid GSTN number and rates must be inclusive of GST Act and itsamendment.
Compliance of GST act/rules & correction/modification issue by railway board with regard toGST act shall be binding on contractor & railway.
Genral instruction :- 1 The offer will be evaluated based on certificates enclosed with theoriginal offer only. The Railways will not enter into any correspondence to get thesecertificates subsequently and the offer shall be evaluated based on the documents submittedalong with the offer.2 Tenderer may please note that meeting of eligibility criteria is strictlybased on completion certificates issued by the executive in charge of work and not linkedwith mere list of works claimed to have been executed by the tenderer or a copy of workorder from Railways. 3 Tenderer may please note that fulfilling of eligibility clause shall beascertained only from the completion certificates issued by the executive-in-charge of workand mere list of works claimed to have been executed by the tenderer or a copy of workorder from Railways shall not be enough. It may also be noted that cognizance of thoseworks, which are nearing completion or have been almost completed, shall not be taken onlythose completion certificates, wherein successful commissioning satisfactory performanceof work have been clearly unambiguously acknowledged by Executive-incharge of anyRailway Unit or any Govt. Dept./Undertaking for any similar work shall be considered for thispurpose.4 Any variation to quantities in any item and its associated wiring material account ofsupply and installation will have to be born by the tenderer. Railway Engineer s decision inthis regard shall be final.5 All drawings related with the work can be obtained from the officeof DRM Kota on any working day during office hours.
Life in Kota division. (02 Stations & 19 IBH)
KOTA-SNT-SIG-2025-52
KOTA-SNT-SIG-2025-52
Open
Works - General
12 Months
Kota, Rajasthan
₹0
₹4.8 L
13 Apr 2026
16 Mar 2026
30 Mar 2026
3 items across 1 schedule · ₹2,40,73,255.85 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | Supply. Installation, Wiring and commissioning of SMPS based integrated power supply system VRLA Batteries (2 Nos. of VRLA Batteries of 55+5 Stackable of 2V/300 AH capacity each Nos. each as per RDSO spcn IRS:S:93/96(A) with latest amendment ) spares and tools as per RDSO specification No. RDSO/SPN165/2023 ver 4.0 Amdt 1 or with latest amendment applicable as on date of tender notice for Station and as per drawing provided by Kota Division at the time of execution of work. Including Connection to change-over unit through underground cable duly supplied by railway. For connecting IPS to battery bank, 10 meter each of Red and Black colour cable of size as per battery AH capacity is to be supplied by tenderer. 12 Core x 1.5 Sq. mm signalling cable for connecting IPS to status monitoring panel will be supplied by Railway free of cost. Supply and commissioning of IPS should be as per RDSO letter No. STS/E/IPS/General dtd. 03.04.2008. This includes Transportation, Loading and Unloading of IPS system complete and batteries from depot to the site of installation. Erection of power distribution board & its connection to IPS, bus bars and relay racks in the IPS room and relay room (as per site engineer instructions) with contractor's own wiring materials. Lugs, Ladder, DWC pipe, 6/10/16/25 Sq mm power cable as per load etc. and as per requirement. This also include fabrication and fixing of AC/DC power distribution board made of phenolic laminated sheet erected on a relay rack (to be supplied by the Railways), All connectors as per site requirement to be supplied by Railway. Fan will be supplied by the railway. The contractor shall liason pursue/ chase with the IPS OEM for battery charging and commissioning of IPS as per schedule. This also includes supply of two sets of power cable route and equipment plan for IPS and relay room. ( I Nos = 1 Set of IPS with complete items and installation) | Numbers | 2.00 | 17,04,600.4 | 34,09,200.8 |
| 2 | Supply and commissioning of SMPS based integrated power supply (IPS) system with VRLA Batteries (of 55+5 Stackable of 2V/300 AH capacity each. RDSO Spcn IRS:S:93/96(A) with latest amendment) for LC gate for RE/ Non-RE area as per RDSO specification no. RDSO/SPN165/2023 ver 4.0 Amdt 1 or with latest amendment applicable as on date of tender notice and as per drawing provided by Kota Division. including supply of spares and tools. Forconnecting IPS to battery bank, 10 meter each of Red & Black colour cable of size as per battery AH capacity is to besupplied by tenderer. 12 Core X 1.5 sq. mm signalling cable for connecting IPS to status monitoring panel will besupplied by railway free of cost. Supply and Commissioning of the IPS should be as per RDSO letter no. STS/E/IPS/Genl. Dated 03.04.2008. Approved drawing shall be supplied during execution. This Includes Installation and Wiring of Integrated Power Supply System including Connection to change- over unit through underground cable duly supplied by railway. This includes Transportation, Loading and Unloading of IPS system complete and batteries from depot to the site of installation. Erection of power distribution board & its connection to IPS, bus bars and relay racks in the IPS room and relay room (as per site engineer instructions) with contractor's own wiring materials. Lugs, Ladder, DWC pipe, 6/10/16/25 Sq mm power cable as per load etc. and as per requirement. This also include fabrication and fixing of AC/DC power distribution board made of phenolic laminated sheet erected on a relay rack (to be supplied by the Railways), All connectors as per site requirement to be supplied by Railway. Fan will be supplied by the railway. The contractor shall liason pursue/ chase with the IPS OEM for battery charging and commissioning of IPS as per schedule. This also includes supply of two sets of power cable route and equipment plan for IPS and relay room. (1 Nos = 1 Set of IPS with complete items and installation) | Numbers | 19.00 | 10,54,423.95 | 2,00,34,055.05 |
| 3 | Supply Installation, commissioning of Class B&C Combined Coordinated Single Phase SPD, pluggable, with mechanical indication and potential free contacts, The supplied SPDs Shall have certification of IEC Standard. | Numbers | 35.00 | 18,000 | 6,30,000 |
| Schedule total | ₹2,40,73,255.85 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
TDKOTASTSIG202552final_compressed.pdf TD 2025 52
ATTACHMENT
TDKOTASTSIG202552final_compressed.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .