Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.8 CrAdmitted-Finance | ₹1.8 Cr | L1 | Admitted-Finance |
| 2 | L2₹1.8 Cr+₹2.5 L (1.40%)Admitted-Finance | ₹1.8 Cr+₹2.5 L (1.40%) | L2 | Admitted-Finance |
| 3 | L3₹1.8 Cr+₹7.2 L (4.08%)Admitted-Finance | ₹1.8 Cr+₹7.2 L (4.08%) | L3 | Admitted-Finance |
| 4 | L4₹1.9 Cr+₹9.5 L (5.36%)Admitted-Finance | ₹1.9 Cr+₹9.5 L (5.36%) | L4 | Admitted-Finance |
| 5 | L5₹1.9 Cr+₹10.5 L (5.92%)Admitted-Finance | ₹1.9 Cr+₹10.5 L (5.92%) | L5 | Admitted-Finance |
| Sl No | Description | Qty | Unit | Nisar Ahmed L11 | M/S ZARDEEP ENTERPRISES L9 | NUN KUN TRADER AND CONSTRUCTIONS L12 | M/s S. F. ENTERPRISES L6 | MERAKI CONSTRUCTIONS COMPANY L8 | MOHD TOHA L3 | M/S Mohd Sadiq L2 | M/S MOHD ISMAIL WAZIR L4 | M/S OOUN CONSTRUCTION COMPANY L13 | STAR STRUCTURAL CONSTRUCTIONS AND COMPANY L14 | M/S MOHMAD ALI L1 | M/S MOHD IBRAHIM L10 | m/s helbi construction L7 | MS Zakir Hussain L5 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.00Construction of Retaining & breast wall for Towers in District Kargil. (at 22 No Location in 66 kV Tr. Line from Gramthang to Sankoo) | |||||||||||||||||
| 1.01 | Excavation of earthwork for foundation.
Hard Soil 35 %
Soft rock 65 % | 1,245.2 | CUM | 550 ₹6,84,860 | 200 ₹2,49,040 | 200 ₹2,49,040 | 390 ₹4,85,628 | 370 ₹4,60,724 | 150 ₹1,86,780 Lowest | 200 ₹2,49,040 | 555 ₹6,91,086 | 250 ₹3,11,300 | 450 ₹5,60,340 | 224 ₹2,78,924.8 | 250 ₹3,11,300 | - | 150 ₹1,86,780 Lowest |
| 1.02 | plinth level in 1:4:8 aggregate 40 mm nominal size (crushed stone) | 155.54 | CUM | 4,000 ₹6,22,160 | 4,500 ₹6,99,930 | 200 ₹31,108 Lowest | 250 ₹38,885 | 4,200 ₹6,53,268 | 6,800 ₹10,57,672 | 5,000 ₹7,77,700 | 2,700 ₹4,19,958 | 4,000 ₹6,22,160 | 4,500 ₹6,99,930 | 4,700 ₹7,31,038 | 4,800 ₹7,46,592 | 4,000 ₹6,22,160 | 3,700 ₹5,75,498 |
| 1.03 | Random rubble masonary with hard stone from quarry in foundation plinth(1:6) 12 grade stone aggregate 20 mm nominal size at plinth level | 3,113 | CUM | 4,400 ₹1,36,97,200 | 4,200 ₹1,30,74,600 | 5,000 ₹1,55,65,000 | 3,800 ₹1,18,29,400 Lowest | 4,500 ₹1,40,08,500 | 4,500 ₹1,40,08,500 | 4,100 ₹1,27,63,300 | 4,100 ₹1,27,63,300 | 5,000 ₹1,55,65,000 | 5,000 ₹1,55,65,000 | 4,800 ₹1,49,42,400 | 5,000 ₹1,55,65,000 | 4,600 ₹1,43,19,800 | 4,350 ₹1,35,41,550 |
| 1.04 | Providing and laying of damp proof course 50 mm thick with cement concrete 1:2:4 dtone aggregate 20 mm nominal size | 1,019.7 | SQM | 350 ₹3,56,895 | 700 ₹7,13,790 | 3,700 ₹37,72,890 | 4,300 ₹43,84,710 | 500 ₹5,09,850 | 340 ₹3,46,698 | 500 ₹5,09,850 | 371 ₹3,78,308.7 | 200 ₹2,03,940 | 500 ₹5,09,850 | 318.6 ₹3,24,876.42 | 350 ₹3,56,895 | 400 ₹4,07,880 | 100 ₹1,01,970 Lowest |
| 1.05 | Earth filling in plinth , sides of foundation etc. Out site wall | 3,063.06 | CUM | 380 ₹11,63,962.8 | 400 ₹12,25,224 | 120 ₹3,67,567.2 | 220 ₹6,73,873.2 | 200 ₹6,12,612 | 70 ₹2,14,414.2 Lowest | 200 ₹6,12,612 | 415 ₹12,71,169.9 | 100 ₹3,06,306 | 200.36 ₹6,13,714.7 | 88.5 ₹2,71,080.81 | 150 ₹4,59,459 | 150 ₹4,59,459 | 150 ₹4,59,459 |
| 1.06 | Carriage of material like stone& aggregate by mechanical transport average lead of 20 KM | 3,261.28 | CUM | 444 ₹14,48,008.32 | 400 ₹13,04,512 | 150 ₹4,89,192 Lowest | 220 ₹7,17,481.6 | 400 ₹13,04,512 | 330 ₹10,76,222.4 | 300 ₹9,78,384 | 215 ₹7,01,175.2 | 400 ₹13,04,512 | 450 ₹14,67,576 | 155 ₹5,05,498.4 | 300 ₹9,78,384 | 350 ₹11,41,448 | 500 ₹16,30,640 |
| 1.07 | Carriage of material like cement by mechanical transport average lead of 20 KM | 315.48 | MT | 700 ₹2,20,836 | 400 ₹1,26,192 | 200 ₹63,096 Lowest | 220 ₹69,405.6 | 400 ₹1,26,192 | 300 ₹94,644 | 300 ₹94,644 | 205 ₹64,673.4 | 700 ₹2,20,836 | 500 ₹1,57,740 | 410 ₹1,29,346.8 | 300 ₹94,644 | 250 ₹78,870 | 500 ₹1,57,740 |
| 1.08 | Carriage of material like stone& aggregate by head load from unloading site average lead 1.5 km | 3,261.28 | CUM | 500 ₹16,30,640 | 400 ₹13,04,512 | 200 ₹6,52,256 | 220 ₹7,17,481.6 | 400 ₹13,04,512 | 330 ₹10,76,222.4 | 200 ₹6,52,256 | 611 ₹19,92,642.08 | 400 ₹13,04,512 | 1,500 ₹48,91,920 | 118 ₹3,84,831.04 Lowest | 400 ₹13,04,512 | 550 ₹17,93,704 | 500 ₹16,30,640 |
| 1.09 | Carriage of material likecementby head load from unloading site average lead 1.5 km | 315.48 | MT | 550 ₹1,73,514 | 400 ₹1,26,192 | 200 ₹63,096 | 220 ₹69,405.6 | 400 ₹1,26,192 | 330 ₹1,04,108.4 | 200 ₹63,096 | 575 ₹1,81,401 | 500 ₹1,57,740 | 900 ₹2,83,932 | 115 ₹36,280.2 Lowest | 400 ₹1,26,192 | 700 ₹2,20,836 | 1,000 ₹3,15,480 |
Tender Value
Refer Docs
EMD Value
₹5.5 L
Closing Date
12 Jun 2026, 4:00 pmClosed
Executive Engineer STD Kargil
1st floor LPDD Complex, Megawatt Kurbathang, opp. 220/66 kV GIS PDCIL Bypass road
Construction of Retaining and breast wall for Towers in District Kargil
2026_PDNRE_19010_1
e-NIT No 03 of STD Kargil of 2026
Open Tender
Civil Works - Others
Works
550 days
kargil
Please refer Tender documents.
4 documents required · 4 mandatory
₹1,000
Executive Engineer STD Kargil
₹5.5 L
3 Jul 2026
1 Jun 2026
13 Jun 2026
1 Jun 2026
12 Jun 2026
1 Jun 2026
1 Jun 2026 - 5 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Construction of Retaining & breast wall for Towers in District Kargil. (at 22 No Location in 66 kV Tr. Line from Gramthang to Sankoo) | |||||
| 1.01 | Excavation of earthwork for foundation.
Hard Soil 35 %
Soft rock 65 % | - | CUM | - | - |
| 1.02 | plinth level in 1:4:8 aggregate 40 mm nominal size (crushed stone) | 1 | CUM | - | - |
| 1.03 | Random rubble masonary with hard stone from quarry in foundation plinth(1:6) 12 grade stone aggregate 20 mm nominal size at plinth level | - | CUM | - | - |
| 1.04 | Providing and laying of damp proof course 50 mm thick with cement concrete 1:2:4 dtone aggregate 20 mm nominal size | - | SQM | - | - |
| 1.05 | Earth filling in plinth , sides of foundation etc. Out site wall | 1 | CUM | - | - |
| 1.06 | Carriage of material like stone& aggregate by mechanical transport average lead of 20 KM | - | CUM | - | - |
| 1.07 | Carriage of material like cement by mechanical transport average lead of 20 KM | - | MT | - | - |
| 1.08 | Carriage of material like stone& aggregate by head load from unloading site average lead 1.5 km | - | CUM | - | - |
| 1.09 | Carriage of material likecementby head load from unloading site average lead 1.5 km | - | MT | - | - |
stage.html
html • 0.05 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.43 MB
SBD.pdf
Tender Documents • 1.28 MB
DRAWING.pdf
Other Document • 0.48 MB
BOQ_45354.xls
BOQ • 0.25 MB
corrigendum3.pdf
PDF • 0.57 MB
corrigendum2.pdf
PDF • 0.45 MB
corrigendum_1.pdf
PDF • 0.81 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .