| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.3 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹1.6 L+₹27,344.86 (20.8%)Accepted-AOC | L2 | Accepted-AOC L2 |
Tender Value
₹1.9 L
EMD Value
₹4,694
Closing Date
4 Nov 2024, 1:00 pmClosed
EXECUTIVE ENGINEER
Executive engineer p.h division Thiruvalla
state plan 202425Relaying 90mm PVC line from Narayana bhavanam towards North in ward no 13 of Thakazhy Grama Panchayath Pipeline Work
2024_KWA_698281_1
15/2024-25/EE/PH/TVLA
Open Tender
Civil Works - Water Works
Item Rate
90 days
Thakazhy
Please refer Tender documents.
6 documents required · 6 mandatory
₹555
₹4,694
7 Jan 2025
21 Oct 2024
5 Nov 2024
21 Oct 2024
4 Nov 2024
21 Oct 2024
Amount
Working charges
100.59.1:Cutting the bituminous / concrete roads with cutting machine for a minimum depth of 200mm along the sides of proposed alignment of the pipe to be laid without causing any damage to other utilities, including the charges for hire and conveyance of tools and plant, cost of consumables and charges for lighting, watching, ribbon fencing, caution boards, traffic diversion, and as per the direction of departmental officers etc. complete, before carrying out the demolition of bituminous / concrete road by mechanical means and carrying out the excavation.
15.43.2:Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in-Charge:Bituminous road
100.1.1:Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in all kinds of soil.
100.8.2:Fencing 1.50m high with two rows of casuarina poles (girth 15cm to 24cm) tied with coir yarn on vertical casuarina pole (girth 15cm to 24cm) fixed at 1.5m intervals.
2.16.1:Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete (Measurements to be taken of the face area timbered).Depth not exceeding 1.5m
100.9.8:Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 90 mm nominal outside diameter pipes.
OD33159/2024-2025:Engaging man mazdoor for bailing out water from trenches
OD33160/2024-2025:Taking interconnection from the existing 90-90mm PVC/HDPE line with the newly laid PVC/HDPE line using suitable specials such as Tee, Saddle... including earthwork excavation in all kind of soil and cost of special. (TEE connection only)
4.1.2:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:1/2:3 (cement : 11/2 coarse sand : 3 graded stone aggregate 20 mm nominal size)
OD119855/2024-2025:Shifting existing house/ Tap connection from the existing line towards the new line including all earth work excavation and cost of materials- Average distance of 5 m
Material Cost
OD33158/2024-2025:Supply of 90mm PVC 6kg/cm2 pipe and specials as per relevent IS specification
KA JOSEPH
Bidder Name
KA JOSEPH
Joby K. Joseph
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1089720.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .