Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.2 CrAccepted-Finance MAHATODIH SARWAN DISTRICT DEOGHAR | DEOGHAR | JHARKHAND | 814112 | ₹3.2 Cr | L1 | Accepted-Finance L1 |
| 2 | L2₹3.4 Cr+₹12.2 L (3.77%)Rejected-Finance | ₹3.4 Cr+₹12.2 L (3.77%) | L2 | Rejected-Finance L2 |
| 3 | Rejected-Technical | - | - | Rejected-Technical Non Responsive |
| 4 | Rejected-Technical | - | - | Rejected-Technical Non Responsive |
| 5 | Rejected-Technical JHARKHAND | - | - | Rejected-Technical Non Responsive |
| Sl No | Description | Qty | Unit | MAHADEV CONSTRUCTION L1 | M/S ASHOK MANDAL L2 |
|---|---|---|---|---|---|
| 1.00 | Earthwork in excavation in foundation trenches in ordinary soil (vide classfication of soil item - A) and disposal of excavated earth a obtained to a distance up to 50M including all lifts with leveling ramming the foundation trenches removing roots of trees shurbs all complete as per approved design and per building specification and direction of E/I. | 1,397.82 | cu.m | 151.82 ₹2,12,217.34 Lowest | 151.82 ₹2,12,217.34 Lowest |
| 2.00 | Extra for earth work in hard soil as per specification and direction of E/I. (vide classfication of soil item - B) | 444.94 | cu.m | 15.51 ₹6,900.94 Lowest | 15.51 ₹6,900.94 Lowest |
| 3.00 | Earth filling in foundation trenches and plinth in layer not exceeding 150mm thick will watered rammed fully compacted and fine dressed with earth obtained from excavation of foundation trenched with a lead of 50mm and lift of 1.5M all complete as per building specification and direction of E/I. (Mode of measurement compacted volume). | 785.18 | cu.m | 55.28 ₹43,404.7 Lowest | 55.28 ₹43,404.7 Lowest |
| 4.00 | Filling in foundation trenches and plinth in layers. Not exceeding 150 mm thick well watered, rammed fully compacted and fine dressed with earth obtained after cutting within a lead of 50 M and lift of 1.5 M all complete as per building specification and direction of E/I (Mode of measurement compacted volume) | 1,789.95 | cu.m | 128.88 ₹2,30,688.88 Lowest | 128.88 ₹2,30,688.88 Lowest |
| 5.00 | Providing coarse clean sand in filling in foundation trenches or plinth including ramming and watering in layers not exceeding 150mm thick with all leads and lifts includng cost of all materials, Labour, rotalty and taxes all complete as per building specification and direction of E/I (Mode of measurement compacted volume). | 79.73 | cu.m | 589.51 ₹47,003.4 Lowest | 589.51 ₹47,003.4 Lowest |
| 6.00 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) | 19.43 | CUM | 3,751.64 ₹72,886.86 Lowest | 3,751.64 ₹72,886.86 Lowest |
| 7.00 | Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with front end loader at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. | 41.85 | M3 | 1,437.6 ₹60,163.56 Lowest | 1,437.6 ₹60,163.56 Lowest |
| 8.00 | Providing designation 75Bwork in C.M. (1:6) in foundation and plinth with approved quality of clean coarse sand of F.m. 2 to 2.5 including providing 10mm thick mortar joints, cost of screening materials ranking out joints to 15mm depth, curing taxes and royalty all complete as per building specification and direction of E/I. | 43.57 | M3 | 5,110.26 ₹2,22,659.14 Lowest | 5,110.26 ₹2,22,659.14 Lowest |
| 9.00 | Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5mm), including making drainage opening wherever required complete etc. as per direction of Engineer-in-charge (length of finished kerb edging shall be measured for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge). | 11.16 | M3 | 8,256.57 ₹92,143.32 Lowest | 8,256.57 ₹92,143.32 Lowest |
| 10.00 | Providing and laying 500x500x40 mm thick Turf paver (Turfpave XD) on 150 mm thick sub grade of compacted bed of 20 mm thick nominal size stone aggregate and base course and filling with 150 mm thick Jamuna sand, including spreading, well ramming, consolidating and finishing smooth etc. all complete as per direction of Engineer-in-charge. | 418.5 | M2 | 1,393.91 ₹5,83,351.34 Lowest | 1,393.91 ₹5,83,351.34 Lowest |
Tender Value
₹3.4 Cr
EMD Value
₹3.4 L
Closing Date
5 May 2026, 3:00 pmClosed
E.E., BCD, Building Division, Dhanbad
E.E., BCD, Building Division, Dhanbad
Renovation and New Construction Work for Gandhi Smarak High School, Sijua, Dhanbad
2026_BCD_113239_1
10/2025-26/EE/BCD/DHANBAD
Open Tender
Civil Works - Buildings
Works
390 days
Dhanbad
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
₹3.4 L
14 Jul 2026
22 Apr 2026
6 May 2026
22 Apr 2026
5 May 2026
22 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earthwork in excavation in foundation trenches in ordinary soil (vide classfication of soil item - A) and disposal of excavated earth a obtained to a distance up to 50M including all lifts with leveling ramming the foundation trenches removing roots of trees shurbs all complete as per approved design and per building specification and direction of E/I. | 0.8 | cu.m | - | - |
| 2Extra for earth work in hard soil as per specification and direction of E/I. (vide classfication of soil item - B) | |||||
| 3 | Earth filling in foundation trenches and plinth in layer not exceeding 150mm thick will watered rammed fully compacted and fine dressed with earth obtained from excavation of foundation trenched with a lead of 50mm and lift of 1.5M all complete as per building specification and direction of E/I. (Mode of measurement compacted volume). | 0.6 | cu.m | - | - |
| 4 | Filling in foundation trenches and plinth in layers. Not exceeding 150 mm thick well watered, rammed fully compacted and fine dressed with earth obtained after cutting within a lead of 50 M and lift of 1.5 M all complete as per building specification and direction of E/I (Mode of measurement compacted volume) | 0.4 | cu.m | - | - |
| 5 | Providing coarse clean sand in filling in foundation trenches or plinth including ramming and watering in layers not exceeding 150mm thick with all leads and lifts includng cost of all materials, Labour, rotalty and taxes all complete as per building specification and direction of E/I (Mode of measurement compacted volume). | 0.2 | cu.m | - | - |
| 6Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) | |||||
| 7Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with front end loader at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. | |||||
| 8 | Providing designation 75Bwork in C.M. (1:6) in foundation and plinth with approved quality of clean coarse sand of F.m. 2 to 2.5 including providing 10mm thick mortar joints, cost of screening materials ranking out joints to 15mm depth, curing taxes and royalty all complete as per building specification and direction of E/I. | 1 | M3 | - | - |
| 9Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5mm), including making drainage opening wherever required complete etc. as per direction of Engineer-in-charge (length of finished kerb edging shall be measured for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge). | |||||
| 10Providing and laying 500x500x40 mm thick Turf paver (Turfpave XD) on 150 mm thick sub grade of compacted bed of 20 mm thick nominal size stone aggregate and base course and filling with 150 mm thick Jamuna sand, including spreading, well ramming, consolidating and finishing smooth etc. all complete as per direction of Engineer-in-charge. | |||||
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.19 MB
SBD-01.pdf
Tender Documents • 3.93 MB
BOQ_152912.xls
BOQ • 0.37 MB
Corrigendum-10.pdf
Additional Documents • 0.08 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .