| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹10.9 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹11.3 L+₹41,745.81 (3.84%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | L3₹12.6 L+₹1.7 L (15.9%)Rejected-Finance | L3 | Rejected-Finance Higher bid value | |
| 4 | L4₹12.9 L+₹2.0 L (18.1%)Rejected-Finance | L4 | Rejected-Finance Higher bid value | |
| 5 | Rejected-Technical | - | Rejected-Technical Improper credential |
Tender Value
₹12.2 L
EMD Value
₹24,484
Closing Date
4 Jun 2026, 5:00 pmClosed
Ex. Engineer, Msd. Highway Divn-II
Ex. Engineer, Msd. Highway Divn-II, C R Das Road, Berhampore, Murshidabad
Repair of 5 nos bridge i.e. Banki Bridge at ch. 5.840 Km of Gokarna-Chiruti Road......and Bridge at ch. 21.62 Km of Kuli-Moregram Road under Murshibad Highway Division No II during the year 2026-27
2026_WBPWD_5014093_3
EEMHDII/NIT1/2026-27
Open Tender
CIVIL WORKS
Percentage
30 days
in Different Roads
Please refer Tender documents.
4 documents required · 4 mandatory
₹24,484
Yes
12 Jun 2026
21 May 2026
8 Jun 2026
21 May 2026
4 Jun 2026
21 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Cleaning rubbish, sludge, weeds scum, liquid earth, mud etc.etc.from road side masonary drain/ hume pipe drain/ culvert etc. by mathor labour after removing concrete.Slab/manhole cover etc.without damaging the same and refixing the same properly after cleaning as necessary and removing the sludge etc.etc.by using iron pans,buckets including all labour, tools & plants including removing the spoils in dry condition and disposing the same by truck beyond the road side in conformity with municipal/corporation rules for such disposal including loading into truck and cleaning the road side in all respects as per direction of the Engineer in-Charge.
(Payment will be made on the basis of actual stack measurment of spoils in dry condition at roadside) | 66 | Cum | 289 | ₹19,074 |
| 2 | Removal of defective concrete, cleaning the surface thoroughly, applying the hotcrete mixture mechanically with compressed air under pressure, comprising of cement, sand, coarse aggregates, water and quick setting compound in the proportion as per clause 2807.1., sand and coarse aggregates conforming to IS: 383 and table 1 of IS: 9012 respectively, water cement ratio ranging from 0.35 to 0.50, density of gunite not less than 2000 kg/cum, strength not less than 25 MPa and workmanship conforming to clause 2807.6. (40 mm average thickness.) | 405.5 | Sqm | 261 | ₹1,05,835.5 |
| 3 | Guniting concrete surface with cement mortar (25 mm nominal thick) applied with ompressor after cleaning surface and spraying with epoxy complete as per Technical specification. | 405.5 | Sqm | 912 | ₹3,69,816 |
| 4 | Providing and inserting nipples with approved fixing compound after drilling holes for grouting as per Technical specifications including subsequent cutting/removal and sealing of the hole as necessary of nipples after completion of grouting with Cement/Epoxy | 299 | Each | 102 | ₹30,498 |
| 5 | Sealing of crack / porous concrete with Epoxy Grout by injection through nipples complete as per clause 2803.1. | 373.75 | Kg | 882 | ₹3,29,647.5 |
| 6 | Hire and Labour charges for staging with sal bullah for super structure of bridge ( Major and Minor) including stripping off and removing cleaning on compleation of work as per design and drawing approved by the Engineer-in-charge | 255 | Sqm | 31.4 | ₹8,007 |
| 7 | Uprooting and removing plants from the surface of walls parapet etc and making good damages. (Repairing of damages to be paid separately). Medium size plant of girth of exposed stem above 75 mm.
but not exceeding 150 mm. lift upto 6 mtr | 255 | Sqm | 67 | ₹17,085 |
| 8 | Hire and labour charges for staging with sal bullah for super structure of bridge (Major and Minor)
including stripping off and removing clearing on completion of work as per design and drawing approved by the Engineer-in-charge. | 396 | Cum | 199 | ₹78,804 |
| 9 | Drainage Spouts in Superstructure including providing drip mouldings and also including supplying, fitting and fixing approved type of materials complete as per drawing and Technical specification vide clause no. 2705 of MoRT&H’s Specification for Road & Bridge Works. | 8 | Nos | 783 | ₹6,264 |
| 10 | Uprooting and removing plants from the surface of walls parapet etc and making good damages. (Repairing of damages to be paid separately).
Medium size plant of girth of exposed stem above 75 mm. but not exceeding 150 mm. lift upto 6 mtr | 11 | Nos | 60 | ₹660 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.26 MB
Form_2911_ii.pdf
Tender Documents • 0.50 MB
BOQ_5082041.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .