| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹72.6 LAccepted-AOC AT WARD NO 10 PO MANDUA DIST KEONJHAR PIN 758014 | KEONJHAR | KEONJHAR | ODISHA | 758014 | 1 | Accepted-AOC Agrt Done | |
| 2 | 2₹77.3 LSame as 1Rejected-Finance | 2 | Rejected-Finance 2nd | |
| 3 | Rejected-Technical AT KUNJABANGADA PO DASAPALLA NAC PS DASAPALLA DIST NAYAGARH PIN 752084 | DASAPALLA | NAYAGARH | ODISHA | 752084 | - | Rejected-Technical Failed to Furnish Original Document | |
| 4 | Not Admitted-Finance JANGHAR PADMAPUR KEONJHAR 758021 | KENDUJHAR | ODISHA | 758021 | - | Not Admitted-Finance Others-Document Flase Written by Paper Owner |
Tender Value
₹77.3 L
EMD Value
₹77,290
Closing Date
14 Jul 2026, 5:00 pmClosed
Divisional Officer
RURAL WORKS DIVISION NO.II, KEONJHAR
Balibandha to Naradpur_Road_SDBC, Road Furniture_1.000 to 1.100 1.880 to 2.400 3.800 to 5.180 10.388 to 11.765 12.054 to 13.236
2026_CERWI_134096_1
NCB 01 OF 2026-27
National Competitive Bid
Civil Works - Roads
Percentage
10 days
Keonjhar
3 documents required · 3 mandatory
₹10,000
₹77,290
Yes
14 Oct 2026
2 Jul 2026
15 Jul 2026
2 Jul 2026
14 Jul 2026
2 Jul 2026
2 Jul 2026 - 13 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing & grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, sapling & trees girth upto 300 mm , removal of stumps of trees cut earlier 7 disposal of un service material to be used for auctioned up to a lead of 1000 mtr including removal & disposal of top organic soil not exceeding 150 mm thickness etc complete. | 29,122 | sqm | 8.63 | ₹2,51,322.86 |
| 2 | Clearing the existing black topped surface including removal of binding materials & other foreign materials with wire brush & small picks, sweeping with brush/ broom & finally dusting with old gunny bags or compressed air to receive bitumen etc complete as per direction of Engineer-in-charge | 17,096.25 | sqm | 5.59 | ₹95,568.04 |
| 3 | Labour for applying tack coat with rapid Emulsion (RS) including cost, conveyance, etc complete as per direction of Engineer-in-charge. | 17,096.25 | sqm | 16.21 | ₹2,77,130.21 |
| 4 | Labour for scrapping cleaning road surface applying tack coat using 3.00 kg of Bitumen for 10 sqm and laying 37.5 mm thick BUSG in one layerusing 0.45 cum of 25 mm to 40 mm size Granite metal and 12.00 kg Bitumen of penetration Grade for 10 sqm with 0.12 cum of 12 mm size chips as key stone for 10 sqm spreading over and laying including heating pouring and spreading over and preading bitumenmetal chips and rlling with PRR and all other machineries including cost and conveyance of all materials etc complete | 1,538.66 | sqm | 399.08 | ₹6,14,049.63 |
| 5 | Providing & laying semidense bituminous concrete with Hot mix plant using crushed aggregate of specified grading, premixed with bituminous binder (60/70) penetration Grade of Bitumen, transporting the hot mix to the site, laying with aMechanical paver Finisher to the required grade, level & alignmen, rolling with smooth wheeled vibratory & tandem Roller to achieve the desired compaction as per clause 508 of Mo SRT&H Specifications etc complete. | 427.41 | cum | 10,429.21 | ₹44,57,548.65 |
| 6 | E/W in hard soil including ordinary compaction including cost of all labour, T&P etc complete as per direction of Engineer-in-charge | 911.8 | cum | 302.61 | ₹2,75,919.8 |
| 7 | Providing & applying 2 coats of weather coat to unplastered surface after cleaning the surface of dirt, dust, oil, greases, efflorescens & applying paint @ 1litre per 2 sqms etc complete as per direction of Engineer-in-Charge. | 258 | sqm | 145.5 | ₹37,539 |
| 8 | Supplying & fixing 15 cm dia 1.00 m long guard posts of RCC (1:2:4) using 7.5 kg of steel for each guard post with 12 mm size black hard granite chips including cost of all reinforcement and materials, centering, shuttering and watering, carrying etc complete as per direction of Engineer-in-Charge. | 71 | nos | 948.89 | ₹67,371.19 |
| 9 | Earth work in excavation of Foundation in all kinds of soil including roudressing, levelling the bed etc complete as per direction of Engineer-in-charge | 352.6 | cum | 311.5 | ₹1,09,834.9 |
| 10 | Filiing Foundation and plinth with sand including watering, ramming etcincluding cost, conveyance, royality and all taxes including additional charges, DMF and EMF etc complete | 127.61 | cum | 1,111.93 | ₹1,41,893.39 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_2.pdf
PDF • 5.04 MB
Tendernotice_1.pdf
PDF • 1.19 MB
BOQ_599262.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .