Dr. Sunny Rao
Office of the Project Officer,WJ Area
Dismantling of 60lb track line from 400MH , transportation and maintained of 500MH track line Moonidih Colliery, W J Area
2026_BCCL_362357_1
BCCL/WJA/MND/SUR/2025-26/96
Open Tender
Miscellaneous Works
Percentage
30 days
Moonidih Colliery, WJ Area
Please refer to NIT.
11 documents required · 11 mandatory
₹10,259
22 Jul 2026
22 Jul 2026
3 Aug 2026
22 Jul 2026
1 Aug 2026
22 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Dismantling of 60lb track line from 400MH , transportation and maintained of 500MH track line Moonidih Colliery, W J Area | |||||
| 1.01 | dismantling of 60lbs trackline from 400 mHz Northern Crosscut of approx length 100m (40 rail) analysis 25m (both) track 6unskilled is required cost per m= (6x1367.6)/25= 328.22/m | 100 | m | 328.22 | ₹32,822 |
| 1.02 | transportation of trackline from dismantled place to 400 MH pit bottom manually arm trolley,in 1 arm is required for 6 track line. And 6 unskilled is required cost/trolly= (6x1367.6)/trolly=8205.60/trolly, trolly required 40/6= 6.6 say 7 trolly | 7 | trolly | 8,205.6 | ₹57,439.2 |
| 1.03 | loading of trackline in 400mHz cage and lowering in 500 MH and unloading the same 12 skilled is required for lowering pit bottom 12 rail , (1436.60x12)/12= 1436.6/rail | 40 | rail | 1,436.6 | ₹57,464 |
| 1.04 | transportation of trackline at different places ( near 1 sick line 500 loco lat) in 1 arm is required for 6 track line. And 6 unskilled is required cost/trolly= (6x1367.6)/trolly=8205.60/trolly, trolly required 40/6= 6.6 say 7 trolly | 7 | trolly | 8,205.6 | ₹57,439.2 |
| 1.05 | transportation of sleepers for replacing track line Approx 150 numbers ofsleeper replace, transport from surface , 8 unskilled manshift required for lowering transport of 4 minecar @ 30ng sleeper per mine car, mine car required 150/30= 5mine car cost/mine car= (8x1367.6)/4=2735.4/mine car, | 5 | mine car | 2,735.4 | ₹13,677 |
| 1.06 | laying and fitting and 150m, 6man shift required for 25m cost = (6x1367.60)/25=328.22/M | 150 | m | 328.22 | ₹49,233 |
| 1.07 | dismantling of 30lbs trackline 120m of length, (48 numbers track) analysis dimantling 40m (both) track 6unskilled is required cost per m= (6x1367.6)/40= 205.14/m | 120 | m | 205.14 | ₹24,616.8 |
| 1.08 | cleaning 120m, 120x2x 0.30m=72m³ analysis for cleaning 4m³ muck, 3unskilled is required, cost /m³= (3x1367.6)/4=1025.70/m³ | 72 | m³ | 1,025.7 | ₹73,850.4 |
| 1.09 | laying and fittin of trackline 120m, 6man shift required for 25m cost = (6x1367.60)/25=328.22/M | 120 | m | 328.22 | ₹39,386.4 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.60 MB
BOQ_375290.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].