Tender Value
₹21.1 L
EMD Value
₹42,195
Closing Date
16 Jan 2024, 4:00 pmClosed
DGM ED Dharmanagar
O/O DGM ED Dharmanagar
Extension of HT LT line with DT sub station at different GP area under the jurisdiction of ESD Kadamtala Phase II
2024_POWER_45626_1
NIT/DGM/ED-DMR/23-24/09
Open Tender
Electrical Works
Turn-key
90 days
O/O DGM ED Dharmanagar
As per NIT
3 documents required · 3 mandatory
₹4,000
₹42,195
O/O DGM ED Dharmanagar
24 Jan 2024
6 Jan 2024
17 Jan 2024
6 Jan 2024
16 Jan 2024
6 Jan 2024
6 Jan 2024 - 9 Jan 2024
10 Jan 2024
Amount
SCHEDULE-A Supply
9 mtr Long PCC pole
8 mtr. Long PCC pole
8 mtr. Long steel pole
Stay set Complete
Stay wire 7/2.5mm
Stay insulator(HT)
Stay insulator (LT)
LT Shackle insulator
Straps with Nuts & Bolts
Nuts & bolts (Assorted size)
MS Channel 100X50X50X6 mm
MS Channel 75X40X40X6 mm
MS Angle 65X65X6 mm
MS Angle 50X50X6 mm
11 KV Polymer pin insulator
11 KV polymer disc insulator
11 KV Disc fittings
ACSR (6/1/2.59mm)
100 KVA Distribution Transformer
GI wire 8 SWG
11 KV GOS unit(3-phase)
11 KV DOF unit (3-phase)
11 KV polimeric L.A.(9 KV, 5KA)
Stay Clamps of MS Flat (50X6mm)
Febricated Brackets clamps of MS Flat (50X6mm)
LT AB cable 1X25+1X16+1X25 sq.mm.
Suspension clamp
Dead End clamp
Cable End Clamp
Eye Hook
Cable tie
100 Amp Cut out
LT PVC Cable 70 sqmm
Danger plate (HT)
40 mm dia GI pipe 2.5 mtr long (Make:-TATA/JINDAL)
60 kg salt & 55 kg Charcoal (For 1 pit)
SCHEDULE-B Erection
Erection of 9.00 mtrs length of PCC pole at any kind of soil upto a depth of 1/6th of pole height , i/c excavation of earth , refilling the pit with soil upto the ground level, ramming and making complete in all respect .
9mtr. Long steel pole
Erection of 8.00 mtrs length of PCC pole at any kind of soil upto a depth of 1/6th of pole height , i/c excavation of earth , refilling the pit with soil upto the ground level, ramming and making complete in all respect i/c Hand-cart carriage & mannual carriage with necessary loading & unloading.
Erection of stay set direct in earth complete with 19mm X 1800mm long stay rod , anchor plate of size 300X300x8 mm , thimble, turn buckle, 7/2.5mm dia GI stranded stay wire and stay insulator etc.with supply of MS clamp, nuts & bolts etc as required and making complete in all respect .
Erection of MS Channel cross arm 2.8 mt.long 100X50X50X6 mm for Sub-Station bracket (for line & txr base)
Erection of MS Channel cross arm 0.65 mt.long 100X50X50X6 mm for Sub-Station bracket ( for Txr base)
Erection of MS Channel cross arm 2.8 mt.long 75X40X40X6 mm for Sub-Station bracket (for GOS & DOF)
Erection of MS angle cross arm 2.8 mt.long 65X65X6 mm MS angle for Sub-Station bracket (for GOS Handle)
Erection of MS angle cross arm 3.1 mt.long 65X65X6 mm MS angle for Sub-Station Guard bracket
Erection of MS Channel cross arm 0.3 mt.long 75X40X40X6 mm (SP Top Bracket for 11KV line)
Erection of MS Channel cross arm 1.2 mt.long 75X40X40X6 mm (SP Bottom Bracket for 11KV line)
Erection of MS angle cross arm 1.5 mt.long 65X65X6 mm ( SP guard Bracket for 11KV line)
Erection of MS angle cross arm bracket for LT line upto 1.2 mtr. Long of 50X50X6 mm
Erection of shackle insulator of size 75 mm X 90 mm/ 100 mmm X15mm with straps & bolts/ clamps on poles
Erection of 11 KV Polymer pin insulator
Erection of 11 KV polymer disc insulator set alongwith necessary fittings
Laying & stringing of 1 km (single conductor ) ACSR 6/1/2.59mm dia weasel i/c hoisting & binding etc. complete as reqd.
Laying & stringing of 1 km (single conductor ) 8 SWG GI wire i/c hoisting & binding etc. complete as reqd.
Erection of 11 KV 200 Amps GOS unit set of three nos i/c necessary connection complete as per technical specification
Erection of 11 KV DOF unit set of three nos i/c necessary connection complete as per technical specification
Erection of 9 KV, 5KA single pole metal oxide gapless type i/c necessary connection complete as per technical specification
Installation / positioning of 11/0.430 KV , 3-phase 100 KVA of distribution transformer on pole with necessary connection and fitting fixing of all allied assessories components as required for making complete in all respect for energizing .
Earthing with GI pipe 2.5 mtr. Long and 40 mm dia i/c excavation , refilling with alternate layer of salt and charcoal as per drawing
Laying of 8 SWG GI wire at 300 mm below the ground level for earthing of sub-station equipments from the earth electrode.
Febrication of cross arms by MS Channel/ MS Angle as per specification
Erection of Danger plate on OH lines (11KV/415 volts)
Providing protective Sub-Station fencing of approve quality as per technical specification i/c supply of all materials.
Erection of 11 KV protective guarding by GI wire 8 SWG as per technical specification, across road/river/telecom line etc. in horizontal formation complete
Erection of 11 KV protective guarding/ Cross lacing for 415/240 volt line by GI wire 8/10 SWG as per technical specification, across road/river/telecom line etc. in horizontal/vertical formation complete with spool/ reel insulator.
Jungle Cutting
SCHEDULE-C Carriage of 11/0.430, 3-Phase 100 KVA by Mechanical Transport from the Site /Store/Worshop to working site Vis-a-vis including loading, unloading and placing on base, as required,a) Upto the lead range 25KM From Sub Division Store to site
a) Upto the lead range 25km
SCHEDULE-D Carriage of 9.0mtr. Length of PCC poles by Mechanical Transport from the factory / Sub-divisional store to working site Vis-à-vis i/c. loading, unloading and stacking as required :-
a) Upto the lead range 25 KM For maximum 04(four) poles
b) Beyond 04(four) poles
SCHEDULE-E Carriage of 8.00 mtr. Length of PCC poles by Mechanical Transport from the factory / Sub-divisional store to working site Vis-à-vis i/c. loading, unloading and stacking as required :-
a) Upto the lead range 25 KM (for max. 5nos. Poles)
b) Beyond 05(five) poles
SCHEDULE-F Carriage of 8.00 mtr. Length of steel poles by Mechanical Transport from the factory / Sub-divisional store to working site Vis-à-vis i/c. loading, unloading and stacking as required :-
a) Upto the lead range 25 KM (for max. 8nos. Poles)
a)Beyond 8 nos pole Upto the lead range 25 KM
SCHEDULE-G Carriage of materials such as cable, AAC, AAAc, ACSR, GI wire, cross-arm, stay set, insulators etc. by Mechanical Transport from factory / the Sub-Divisional store yard to working site Vis-à-vis i/c. loading, unloading and stacking as required :-PCC poles by Mechanical Transport from the Sub-Divisional store yard working site Vis-à-vis i/c. loading, unloading and stacking as required :-
a) Upto the lead range 25 KM
SCHEDULE-H Carriage of G.O.S., D.O.F. L. A. etc. by Mechanical Transport from factory /the Sub-Divisional store yard to working site Vis-à-vis i/c. loading, unloading and stacking as required :-
a) Upto the lead range 25 KM
SCHEDULE-H Grouting of 19 nos. 8mtr steel tubular pole of ratio 1:2:4(1cement: 2 river send: 4 jhama brick aggregate) of 20mm normal size i/c. Supply of cement,send & jhama brick aggregate complect excavation,refilling & ramming of cach alongwith centering & shuttaring ang clamping.(per pole= 0.392cum)
a) 19 nos pole (per pole= 0.392cum)
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .